Texas Journeyman Plumber Exam — All Questions
50 questions
Under Occupations Code §1301.002, how many hours of work at the trade must an applicant have before sitting for the Journeyman Plumber examination?
- a.At least 10,000 hours
- b.At least 8,000 hours✓
- c.At least 4,000 hours
- d.At least 6,000 hours
The statute defines a journeyman plumber as a person with at least 8,000 hours at the trade who has passed the examination. The 4,000-hour figure belongs to the Tradesman Plumber-Limited licence, and 6,000 and 10,000 hours do not appear in the definitions.Tex. Occ. Code §1301.002
A Tradesman Plumber-Limited licensee is sent to rough in the plumbing for a new restaurant with no licensed plumber directing the job. Under the Plumbing License Law this is:
- a.Outside the licence only where the restaurant has a grease interceptor
- b.Allowed, because a tradesman may work on any building under 5,000 sq ft
- c.Outside the licence, which covers one- and two-family dwellings✓
- d.Allowed, as long as a plumbing permit has been issued for the address
The tradesman licence is limited to constructing, installing, changing, repairing, servicing or renovating plumbing for one-family and two-family dwellings. Floor area, a permit and the presence of an interceptor do not change the scope; commercial work needs a journeyman or master, or supervision by one.Tex. Occ. Code §1301.002; 22 TAC §365.1
Which person is a "Responsible Master Plumber" under Occupations Code §1301.002?
- a.A master plumber who lets a plumbing company use the licence to offer and perform plumbing✓
- b.A journeyman plumber who has been put in charge of a job by the owner of the company
- c.Any licensed plumber named by a city as the contact for a permit that has been issued
- d.A master plumber who has held the licence for 10 years and supervises five journeymen
A responsible master plumber (RMP) is a licensed master plumber who allows a person or company to use the master licence to offer and perform plumbing work, is authorised to obtain permits, and has filed a certificate of insurance. Years of service and crew size are not part of the definition, and a journeyman cannot fill the role.Tex. Occ. Code §1301.002
Under 22 TAC §367.5, for how many companies may a master plumber act as the responsible master plumber of record at the same time?
- a.Two
- b.Any number within one county
- c.One✓
- d.Three
A master plumber may act as RMP of record for only one person or company at a time. No county-based or numerical allowance for more than one exists in the rule.22 TAC §367.5(a)
A master plumber stops serving as the responsible master plumber for a company on June 1. Under 22 TAC §367.5, written notice must reach the Board within:
- a.30 calendar days after the change takes effect
- b.10 business days after the change takes effect✓
- c.60 calendar days after the change takes effect
- d.5 business days before the change takes effect
The rule requires written notification, in the form the Board specifies, within ten business days after the effective date of being added or removed as RMP. Thirty days is the period for a name or address change; 60 days and advance notice are not in the rule.22 TAC §367.5(a)
Occupations Code §1301.552 sets the minimum commercial general liability coverage a responsible master plumber must show at:
- a.$300,000 for all claims arising in a one-year period✓
- b.$100,000 for all claims arising in a one-year period
- c.$500,000 for each claim arising in a one-year period
- d.$1,000,000 for all claims over the life of the licence
The certificate of insurance must show coverage of not less than $300,000 for all claims arising in a one-year period. The other amounts are common contract figures but are not the statutory minimum.Tex. Occ. Code §1301.552
A licensed journeyman is stopped on a job by a city plumbing inspector who asks to see a licence. Under §1301.351 and 22 TAC §367.12, the journeyman must:
- a.Carry the licence pocket card while working and show it✓
- b.Refer the inspector to the responsible master plumber
- c.Give the licence number verbally, which is sufficient
- d.Show it at the Board office within ten business days
A person engaged in plumbing must carry the licence or registration and present it on request. Reciting a number, producing it later, or pointing to the RMP does not satisfy the duty to have the card on the job.Tex. Occ. Code §1301.351; 22 TAC §367.12
Which task may a registered plumber's apprentice perform on a job site?
- a.Install a gas water heater alone after two years at the trade
- b.Sign for the final plumbing inspection on a single-family house
- c.Assist with plumbing work under the supervision of a licensed plumber✓
- d.Obtain the plumbing permit when the master plumber is out of town
An apprentice works as an assistant under the supervision and direction of a licensed plumber. Working alone on installations, signing inspections and pulling permits are reserved to licensees; only an RMP obtains permits.Tex. Occ. Code §§1301.002, 1301.351
Under Occupations Code §1301.404, how many hours of Board-approved continuing professional education must a licensed plumber complete each year to renew?
- a.Eight hours
- b.Four hours
- c.Six hours✓
- d.Twelve hours
A licence holder must complete at least six hours of approved continuing professional education each licence year. Four, eight and twelve hours are requirements in other trades or states, not in the Plumbing License Law.Tex. Occ. Code §1301.404
Of the six yearly continuing education hours under §1301.404, three must cover:
- a.Customer service, marketing and advertising of plumbing work
- b.Estimating, bidding and business management for contractors
- c.Workers' compensation law and payroll tax reporting duties
- d.Health protection, energy conservation and water conservation✓
The statute requires three of the six hours to be in health protection, energy conservation and water conservation. Business, tax and marketing topics are not the mandated subjects.Tex. Occ. Code §1301.404
A journeyman licence expired 60 days ago. Under Occupations Code §1301.403, the plumber may renew by paying:
- a.The renewal fee plus a late fee equal to the renewal fee
- b.The renewal fee only, because 90 days have not passed
- c.A new examination fee and passing the written exam
- d.The renewal fee plus a late fee of half the renewal fee✓
A licence expired for 90 days or less is renewed by paying the renewal fee and a fee equal to one-half of it. The late fee equals the full renewal fee only after 90 days, there is no free grace period, and re-examination applies only at two years or more.Tex. Occ. Code §1301.403; 22 TAC §361.6
A plumber let a licence lapse and it has now been expired for 14 months. Under §1301.403 the plumber may:
- a.Renew by paying the renewal fee plus a late fee equal to the renewal fee✓
- b.Renew by paying the renewal fee plus a late fee of half the renewal fee
- c.Not renew, and must apply as a new applicant and pass the exam again
- d.Renew at no added cost after completing twelve hours of education
Between 90 days and two years after expiry, the licence is renewed by paying the renewal fee and a late fee equal to it. The half-fee applies at 90 days or less, and the licence cannot be renewed at all only when it has been expired two years or more.Tex. Occ. Code §1301.403
A licence that has been expired for two years or more:
- a.Can be renewed by paying three times the renewal fee and a reinstatement fee
- b.Can be renewed after 24 hours of continuing education and a Board interview
- c.Cannot be renewed; the person must meet the requirements and pass the exam again✓
- d.Is restored automatically once the person is hired by a responsible master plumber
After two years the licence may not be renewed, and the person must comply with the requirements for a new licence, including the examination. No triple fee, education substitute or automatic reinstatement is provided.Tex. Occ. Code §1301.403
Under Occupations Code §1301.401, a plumbing licence or registration is valid for:
- a.One year✓
- b.Three years
- c.Two years
- d.Five years
Licences, endorsements and registrations are issued for one year and renewed annually. Longer terms are not provided in the Plumbing License Law.Tex. Occ. Code §1301.401
A homeowner replaces the water heater in the house where the homeowner lives, with no licence. Under Occupations Code §1301.051 this work is:
- a.Exempt from licensing, because it is done by the owner in the owner's homestead✓
- b.Allowed only if a licensed plumber signs the invoice for the materials
- c.Exempt from licensing and also exempt from any city permit or inspection rule
- d.A violation, because water heater work always requires a master plumber
A property owner may do plumbing in the owner's homestead without a licence. The exemption is from licensing; it does not remove a city's permit and inspection requirements, and it does not depend on a plumber's signature.Tex. Occ. Code §1301.051
An apartment complex employs a maintenance person who does incidental plumbing repairs on the property as part of the job. Under the Board's rules, this person may NOT:
- a.Replace a leaking faucet washer in one of the apartment units
- b.Clear a stopped lavatory drain using a hand-operated cable
- c.Cut into fuel gas piping or install a gas-fuelled water heater✓
- d.Replace a worn flapper in the tank of a tenant's water closet
The maintenance exemption covers incidental work on the employer's property and does not extend to cutting into fuel gas plumbing or installing gas-fuelled water heaters. Faucet washers, a drain stoppage and a flapper are ordinary maintenance.Tex. Occ. Code §1301.053; 22 TAC §361.1
An appliance dealer's employee delivers and connects appliances for customers. Under Occupations Code §1301.053, the licensing exemption for appliance installation does NOT cover connecting:
- a.An ice maker
- b.A clothes washer
- c.A water heater✓
- d.A dishwasher
The exemption for appliance installation and service by dealers and their employees expressly excludes water heaters, which must be installed by a licensed plumber. Washers, dishwashers and ice makers fall within the exemption.Tex. Occ. Code §1301.053
Occupations Code §1301.551 requires a municipality to regulate plumbing by ordinance when it has more than how many inhabitants?
- a.10,000
- b.25,000
- c.2,500
- d.5,000✓
A municipality with more than 5,000 inhabitants must regulate, by ordinance, the material, construction, alteration and inspection of plumbing. The other populations are not the statutory threshold.Tex. Occ. Code §1301.551
Under §1301.551, which job may a licensed plumber do without a municipal plumbing permit?
- a.Relocating a bathroom lavatory
- b.Replacing a kitchen faucet✓
- c.Replacing a gas water heater
- d.Replacing a building sewer
The statute lists work for which a permit is not required: repairing leaks and replacing lavatory or kitchen faucets, ballcocks or water control valves, garbage disposals and water closets. Water heater replacement, relocating a fixture and sewer replacement are permit work.Tex. Occ. Code §1301.551
A plumbing company's service truck must show the licence number of the responsible master plumber. Under 22 TAC §367.10, the number must be:
- a.On the driver's door only, in any size the company chooses to use
- b.On a card behind the windshield that can be read from the kerb
- c.On both sides of the vehicle, in contrasting characters at least 2 inches high✓
- d.On the rear of the vehicle only, in reflective characters at least 4 inches high
The rule requires the RMP licence number on both sides of each vehicle used for plumbing, in a colour that contrasts with the background and at least two inches high. One side, the rear only or a windshield card does not comply.22 TAC §367.10
Under 22 TAC §367.10, the licence number displayed on a company vehicle is preceded by:
- a."TX", "TSB" or "PLB"
- b."J", "JPL" or "TPL"
- c."LIC", "REG" or "CERT"
- d."M", "MPL" or "RMP"✓
The number must be the RMP's master licence number preceded by M, MPL or RMP. Journeyman or tradesman prefixes and the other abbreviations are not what the rule calls for.22 TAC §367.10
A plumbing company hands a customer a written proposal. Under 22 TAC §367.10, the first page must include the Board's name, mailing address and telephone number and the statement that the company is:
- a.Bonded and insured by the State of Texas plumbing fund
- b.Approved by the International Code Council as an installer
- c.Regulated by the Texas State Board of Plumbing Examiners✓
- d.Certified by the Texas Commission on Environmental Quality
Proposals, invoices and written contracts must show the RMP's name and licence number and state that the work is regulated by the Texas State Board of Plumbing Examiners, with the Board's contact information. The State does not bond plumbers, and TCEQ and ICC do not license them.22 TAC §367.10
When a plumbing job is finished, 22 TAC §367.3 requires the licensee to give the customer:
- a.A written one-year warranty on all labour and all installed materials
- b.A notarised statement that the work passed the city's final inspection
- c.A copy of the plumber's licence card and proof of continuing education
- d.An invoice or completed contract document, even if no fee was charged✓
The standards of conduct require an invoice or completed contract document on completion of the job, whether or not a fee was charged. The rule does not require a warranty, copies of credentials or a notarised inspection statement.22 TAC §367.3(a)
A home warranty company hires a plumbing company to repair a leak at a policyholder's house. Under 22 TAC §367.3, who is the "customer" who must receive the invoice?
- a.The insurance carrier of the plumbing company
- b.The homeowner who received the plumbing service✓
- c.The city plumbing inspector who covers the address
- d.The home warranty company that issued the work order
The customer is the person to whom the plumbing services were provided, even when the work is done under a contract with a third party such as a home warranty company. The warranty company, an inspector and an insurer are not the customer for this duty.22 TAC §367.3(a)(5)
A licensed plumber moves to a new home address. Under 22 TAC §365.8, the Board must be told within:
- a.90 days
- b.60 days
- c.30 days✓
- d.10 days
Licensees and registrants must notify the Board of a change of name or address within 30 days. Ten business days is the period for RMP changes; 60 and 90 days are not in this rule.22 TAC §365.8
Under Occupations Code §1301.508, performing plumbing without the licence the chapter requires is:
- a.A state jail felony
- b.A Class C misdemeanor✓
- c.A civil infraction only
- d.A Class A misdemeanor
A violation of the chapter or a Board rule is a Class C misdemeanor. The statute does not make it a Class A misdemeanor or a felony, and it is a criminal offence in addition to any administrative penalty.Tex. Occ. Code §1301.508
The Board may impose an administrative penalty under Occupations Code §1301.702 of up to:
- a.$5,000 for each violation, with each day a separate violation✓
- b.$10,000 for each violation, regardless of how long it continues
- c.$500 for each violation, with a cap of $2,500 per year
- d.$1,000 for each violation, with each week a separate violation
The penalty may not exceed $5,000 per violation, and each day a violation continues or occurs is a separate violation. The other figures are not in the statute.Tex. Occ. Code §1301.702
A plumber receives a Notice of Alleged Violation proposing an administrative penalty. Under 22 TAC §367.17, the plumber must respond in writing within:
- a.30 days after receiving the notice
- b.10 days after receiving the notice
- c.20 days after receiving the notice✓
- d.45 days after receiving the notice
The respondent has until the 20th day after receipt to accept the staff's determination or request a hearing before the State Office of Administrative Hearings. Missing that date allows staff to propose a default order.22 TAC §367.17
Who may issue a citation under Occupations Code §1301.502 to a person doing plumbing without a licence?
- a.Any licensed master plumber who witnesses the unlicensed work in progress
- b.A plumbing inspector of a municipality or a Board field representative✓
- c.A supply house employee who sold the materials to the unlicensed person
- d.A building owner who has a signed contract with the unlicensed person
Citations may be issued by a municipal plumbing inspector, certain water district inspectors and Board field representatives. Private persons such as other plumbers, owners or suppliers may file complaints but cannot issue citations.Tex. Occ. Code §1301.502
Which act is a ground for discipline under Occupations Code §1301.452?
- a.Obtaining a licence through error or fraud✓
- b.Declining a job outside the plumber's training
- c.Charging more than a competitor for the same job
- d.Working for more than one employer in a year
The grounds include obtaining a licence through error or fraud, wilful or negligent violation of the chapter, and misrepresentation. Turning down work, pricing and changing employers are not violations.Tex. Occ. Code §1301.452
A person's plumbing licence is revoked. Under Occupations Code §1301.451, the person may apply for a new licence no earlier than:
- a.The first anniversary of the revocation✓
- b.The third anniversary of the revocation
- c.The date the next renewal would fall due
- d.The 90th day after the revocation
A person whose licence has been revoked may not apply for a new licence before the first anniversary of the revocation. The shorter and longer periods are not what the statute provides.Tex. Occ. Code §1301.451
A candidate fails the journeyman written examination for the first time. Under 22 TAC §363.22, the candidate must wait at least how long before retaking it?
- a.30 days✓
- b.14 days
- c.90 days
- d.60 days
The waiting period is 30 days after a first failure, 60 days after a second, and 90 days after a third or later failure. There is no 14-day period.22 TAC §363.22
Under 22 TAC §363.22, a candidate passes an examination part with a score of at least:
- a.80 percent
- b.75 percent
- c.65 percent
- d.70 percent✓
A score of 69.9 or less is failing, so 70 percent is the pass mark. The other percentages are used by other licensing programmes.22 TAC §363.22
Under Occupations Code §1301.354 and Board rules, how many hours of approved classroom training must an applicant complete before taking the Journeyman Plumber examination?
- a.96 hours
- b.12 hours
- c.24 hours
- d.48 hours✓
Journeyman applicants need 48 hours of approved training; the Tradesman Plumber-Limited examination requires 24 hours. Twelve and 96 hours are not requirements.Tex. Occ. Code §1301.354; 22 TAC §363.5
An applicant completed a U.S. Department of Labor approved apprenticeship programme. On written request, the Board may credit the applicant with up to how many hours toward the experience required for an examination?
- a.4,000 hours
- b.1,000 hours✓
- c.500 hours
- d.2,000 hours
On written request the Board may credit up to 1,000 hours of the work experience required for the examination when the applicant has completed the classroom portion of a training program approved by the U.S. Department of Labor, Office of Apprenticeship, or a Board-approved program. The other amounts are not provided in the statute or rules.Tex. Occ. Code §1301.354(c); 22 TAC §363.5(c)
Under 22 TAC §363.7, the minimum age to register as a plumber's apprentice is:
- a.18 years
- b.14 years
- c.16 years✓
- d.21 years
An applicant for a Plumber's Apprentice Registration must be at least sixteen years old. The other ages are not the rule's threshold.22 TAC §363.7
Under Occupations Code §1301.359, a plumbing licence issued by the Board is valid:
- a.Throughout the state, after a local test in each city
- b.Only in cities that have adopted the same plumbing code
- c.Only in the county where the examination was taken
- d.Throughout the state, without a separate city examination✓
A Board licence is valid statewide, and a municipality may not require a licensee to pass a local examination. Validity is not tied to a county or to the code a city adopted.Tex. Occ. Code §1301.359
Which plumbing codes has the Board adopted under 22 TAC §367.2?
- a.The 2024 International Plumbing Code only, with Texas amendments
- b.The 2021 National Standard Plumbing Code and the 2021 Uniform Plumbing Code
- c.The 2012 Uniform Plumbing Code and the 2012 International Plumbing Code
- d.The 2018 Uniform Plumbing Code and the 2018 International Plumbing Code✓
The Board's rule adopts the 2018 editions of the UPC and the IPC, the IPC adoption including the International Fuel Gas Code and the International Residential Code. The 2012, 2021 and 2024 answers do not match the rule.22 TAC §367.2; Tex. Occ. Code §1301.255
In an area where no plumbing code has been adopted by a city, Occupations Code §1301.255 requires plumbing installed by a licensee to comply with:
- a.Federal housing standards only
- b.A plumbing code adopted by the Board✓
- c.The code used in the nearest large city
- d.The plumber's own company standards
Outside a political subdivision that has adopted a code, plumbing installed by a licensed plumber must meet a code adopted by the Board. The nearest city's code, company standards and federal housing standards are not the legal baseline.Tex. Occ. Code §1301.255
Under the Board's definition in 22 TAC §361.1, "direct supervision" of a registrant by remote audio-visual means is permitted only for:
- a.Medical gas brazing in hospitals and surgery centres where the endorsement holder is on call by telephone
- b.New rough-in plumbing in any building where a plumbing permit has been issued
- c.Fuel gas piping tests in commercial kitchens where the inspector is present
- d.Repair or replacement of existing fixtures in one- and two-family dwellings, not gas appliances✓
The definition allows supervision through real-time audio-visual communication for repair and replacement of existing fixtures in one- and two-family dwellings, and excludes gas appliances. New construction, gas work and medical gas work need on-site supervision.22 TAC §361.1
A drain cleaner registrant under §1301.002 is authorised to:
- a.Disconnect and reset a gas water heater to reach a floor drain behind it
- b.Install a new two-way cleanout on a building drain that does not have one
- c.Replace a section of building sewer that was found to be collapsed during the cleaning
- d.Clear obstructions in sewer and drain lines through a code-approved existing opening✓
A drain cleaner removes obstructions through existing code-approved openings, such as cleanouts, and may remove and reset p-traps. Replacing sewer pipe, cutting in a cleanout and gas appliance work are plumbing that needs a licence.Tex. Occ. Code §1301.002; 22 TAC §361.1
A Residential Utilities Installer registrant may install, under supervision:
- a.Yard water service piping and building sewers for one- and two-family dwellings✓
- b.Building sewers and grease interceptors for small commercial buildings
- c.Fuel gas yard lines from the meter to a one- or two-family dwelling
- d.Water heaters, fixture supplies and fixtures inside one- and two-family dwellings
The registration covers yard water service piping and building sewers for one- and two-family dwellings and requires 2,000 hours of experience. Work inside the building, commercial work and gas piping are outside it.Tex. Occ. Code §1301.002
Which licence endorsement authorises a plumber to perform customer service inspections of a public water system connection?
- a.Water Supply Protection Specialist✓
- b.Medical Gas Piping Installation
- c.Residential Utilities Installer
- d.Multipurpose Residential Fire Protection Sprinkler Specialist
The Water Supply Protection Specialist endorsement covers customer service inspections and the installation of rainwater and reclaimed water treatment. The medical gas and sprinkler endorsements cover other work, and Residential Utilities Installer is a registration, not an endorsement.Tex. Occ. Code §§1301.002, 1301.357
A journeyman is asked to braze oxygen piping in a new surgery centre. Under Occupations Code §1301.356 and 22 TAC §367.7, the journeyman may do this only when:
- a.Holding a current Medical Gas Piping Installation Endorsement✓
- b.Working under a hospital facilities permit from the city
- c.Holding a current Water Supply Protection Specialist endorsement
- d.Working under a mechanical engineer's sealed drawings
Medical gas pipe assembly, brazing and marking may be done only by a licensee who holds a current Medical Gas Piping Installation Endorsement. Engineer drawings, a different endorsement or a permit do not substitute for it.Tex. Occ. Code §1301.356; 22 TAC §367.7
Under Occupations Code §1301.351(c), continuous on-the-job oversight by a licensed plumber is not required for a registered apprentice working on:
- a.A new one- or two-family dwelling in an unincorporated area✓
- b.A remodel of a school building during the summer break
- c.A new apartment building of no more than three stories
- d.A new restaurant inside a city with fewer than 5,000 people
The statute relaxes continuous oversight only for new one-family or two-family dwellings in unincorporated areas of the state, where the RMP remains responsible for the work. Commercial, institutional and multifamily jobs do not qualify.Tex. Occ. Code §1301.351(c)
After January 1, 2009, Occupations Code §1301.551 bars a municipality from adopting an ordinance that requires, in a new one- or two-family dwelling:
- a.A multipurpose residential fire protection sprinkler system✓
- b.A thermal expansion device on the water heater
- c.A pressure-reducing valve on the water service line
- d.A two-way cleanout at the junction of building drain and sewer
The statute prohibits new municipal ordinances that mandate fire sprinkler systems in new or existing one- or two-family dwellings. Pressure regulators, expansion control and cleanouts are ordinary code items a city may enforce.Tex. Occ. Code §1301.551
Under 22 TAC §367.4, a licensed plumbing inspector may NOT:
- a.Have a financial or advisory interest in a plumbing company✓
- b.Hold a current journeyman or master plumber licence as well
- c.Be employed by a political subdivision to inspect plumbing
- d.Put the inspector licence number on a notice of correction
The standards of conduct bar an inspector from having any financial or advisory interest in a plumbing company. Holding a plumber's licence, working for a city and writing the licence number on documents are allowed or required.22 TAC §367.4
Under 22 TAC §367.2, a water closet tank fill valve must be an antisiphon type with its critical level at least how far above the top of the overflow tube?
- a.1/2 inch
- b.1 inch✓
- c.6 inches
- d.2 inches
The Board's rule calls for an antisiphon fill valve (ballcock) with the critical level at least one inch above the full opening of the overflow pipe. Six inches is the atmospheric vacuum breaker height above a fixture flood rim, a different rule.22 TAC §367.2; IPC §425.3.1
An RMP's company runs a newspaper advertisement for plumbing services. Under 22 TAC §§367.9 and 367.10, the advertisement must:
- a.Include the company's insurance policy number and expiry date
- b.Include the journeymen's licence numbers and home telephone numbers
- c.Include the RMP's licence number and not be false or misleading✓
- d.Be filed with the Board for approval 30 days before it is published
Advertising must carry the RMP's licence number, subject to listed exceptions, and may not be false, misleading or deceptive. The rules do not require employee details, pre-approval by the Board or insurance policy numbers.22 TAC §§367.9, 367.10
Under 22 TAC §367.6, a customer asks the plumbing company for information about its liability insurance. The company must provide it within:
- a.30 days of the request✓
- b.3 days of the request
- c.60 days of the request
- d.90 days of the request
On written request, the RMP or owner of the plumbing company must give the customer the insurance carrier's name and the agent's name, address and telephone number within 30 days. The shorter and longer periods are not in the rule.22 TAC §367.6(c)