Texas Master Electrician Exam — All Questions
The figures these questions turn on, pooled by value and printable, with a side to write them from memory: Texas Master Electrician (TDLR / PSI, 2026 NEC) cheat sheet PDF — $9.99 →
53 questions
A dwelling has one 4-kW electric clothes dryer. What value must be used as the dryer demand load in the service calculation?
- a.5,500 VA
- b.4,500 VA
- c.4,000 VA
- d.5,000 VA✓
The dryer load is the nameplate rating or 5,000 VA, whichever is larger. Since 4,000 VA is below 5,000 VA, 5,000 VA must be used.2026 NEC §120.54
For a 200-A dwelling service using the 83% conductor allowance, what is the smallest copper ungrounded conductor (75 C) permitted for the main power feeder?
- a.#1/0 AWG
- b.#3/0 AWG
- c.#2/0 AWG✓
- d.#4/0 AWG
200 A x 0.83 = 166 A required ampacity. At 75 C, #2/0 Cu is rated 175 A, which satisfies 166 A, so #2/0 is the smallest permitted.2026 NEC §310.12
A one-family dwelling has a total general load (lighting, small-appliance, laundry, fastened appliances, ranges) of 40,000 VA before HVAC. Using the optional method of 120.82(B), what is the demand for these general loads?
- a.20,800 VA✓
- b.16,000 VA
- c.40,000 VA
- d.22,000 VA
2026 NEC 120.82(B) takes 100% of the first 8 kVA plus 40% of the remainder: 8,000 + 0.40 x 32,000 = 8,000 + 12,800 = 20,800 VA. Trap: 22,000 VA keeps the first 10 kVA at 100%, which is not the 2026 rule; 16,000 VA applies 40% to the whole 40,000.2026 NEC §120.82(B)
Under the optional dwelling calculation, the supplemental electric heating of a central electric space-heating system is included at what percent of its nameplate rating?
- a.100%
- b.65%✓
- c.40%
- d.75%
2026 NEC 120.82(C)(3) takes the heat pump compressor at 100% and the supplemental electric heating of a central electric space-heating system at 65% of nameplate. Trap: the 40% figure in 120.82(C)(5) applies only to four or more separately controlled electric-heat units, not to central heat.2026 NEC §120.82(C)
Transformer secondary conductors run 8 ft to a panelboard under the 10-ft secondary rule. Their ampacity must be not less than:
- a.10% of the primary overcurrent device rating
- b.the primary conductor ampacity
- c.the rating of the device or busbar they supply✓
- d.at least 300% of the transformer's rated secondary current
2026 NEC 240.21(C)(2) allows transformer secondary conductors up to 10 ft without overcurrent protection at the secondary if their ampacity is at least the calculated load and at least the rating of the equipment or overcurrent device they supply. The other choices do not state this requirement.2026 NEC §240.21(C)(2)
The optional calculation for a multifamily dwelling (120.84) may be used only where the building has at least how many dwelling units?
- a.3✓
- b.2
- c.5
- d.10
2026 NEC 120.84 applies to multifamily dwellings of three or more units that meet the stated conditions (single feeder per unit, electric cooking, and electric heat or air-conditioning). Trap: 5 confuses this with range-table diversity, not the unit-count threshold.2026 NEC §120.84
A service neutral carries a maximum unbalanced load of 250 A. Applying the neutral demand allowance, what is the calculated neutral load?
- a.250 A
- b.235 A✓
- c.225 A
- d.210 A
2026 NEC 120.61(B)(2) permits 70% on the portion of neutral load over 200 A: 200 + 0.70 x 50 = 200 + 35 = 235 A. Trap: 250 A ignores the reduction; only the amount above 200 A is reduced.2026 NEC §120.61(B)(2)
Under the optional method for adding load to an existing dwelling (120.83), after taking 100% of the first 8 kVA, the remainder of the existing load is calculated at what percent?
- a.40%✓
- b.35%
- c.50%
- d.65%
2026 NEC Table 120.83 takes 100% of the first 8 kVA and 40% of the remainder of the existing load. Trap: 50% is the factor for other new loads being added, and 35% is the general-lighting remainder factor from the standard method, not this table.2026 NEC Table 120.83
A large multifamily building has 900,000 VA of connected load and an applicable 120.84 demand factor of 32%. What is the calculated demand load?
- a.450,000 VA
- b.900,000 VA
- c.288,000 VA✓
- d.360,000 VA
The optional multifamily method multiplies connected load by the Table 120.84(C) demand factor: 900,000 x 0.32 = 288,000 VA. Trap: 360,000 VA uses 40%; the demand factor falls as the number of units rises.2026 NEC Table 120.84(C)
A dwelling's total calculated load is 27,600 VA on a 240-V, single-phase service. What is the calculated service current?
- a.100 A
- b.120 A
- c.115 A✓
- d.96 A
Current = volt-amperes / voltage: 27,600 / 240 = 115 A.
Want these explained in order? Texas Master Electrician Exam — Open-Book Study Guide (2026 NEC) — PDF + EPUB, $14.99 · 14-day refund →
In a commercial service calculation, the largest motor has a 65-A full-load current. How much is added for the largest-motor 25% factor?
- a.13 A
- b.81.25 A
- c.16.25 A✓
- d.65 A
Under 2026 NEC 430.24 the largest motor is taken at 125%, so 25% of its FLC is added on top of the motor loads: 0.25 x 65 = 16.25 A.2026 NEC §430.24
A 208-V, three-phase service carries a calculated load of 90,000 VA. What is the calculated service current?
- a.250 A✓
- b.144 A
- c.216 A
- d.433 A
Three-phase current = 90,000 / (1.732 x 208) = 250 A.
In other than dwelling units, service and feeder-supplied equipment likely to be examined or serviced while energized must carry what type of permanent marking?
- a.Voltage rating only
- b.Phase-sequence label
- c.An arc-flash hazard marking✓
- d.Equipment grounding conductor size
Under 110.16, a permanent arc-flash marking, field or factory applied, is required on this equipment. It shows the nominal system voltage, the arc flash boundary, the available incident energy or minimum PPE level, and the date of the assessment.2026 NEC §110.16
One of the primary purposes of system grounding under 2026 NEC 250.4(A)(1) is to:
- a.limit the voltage imposed by lightning, line surges, or unintentional contact with higher-voltage lines✓
- b.carry normal load current
- c.eliminate the need for overcurrent protection
- d.reduce conductor resistance
250.4(A)(1): system grounding limits the voltage imposed by lightning, line surges, and unintentional contact with higher-voltage lines, and stabilizes the voltage to earth during normal operation.2026 NEC §250.4(A)(1)
What is the maximum number of service disconnecting means permitted for a single set of service-entrance conductors (each in a separate enclosure)?
- a.Eight
- b.Six✓
- c.One
- d.Four
A service normally has one disconnecting means, but 230.71(B) allows two to six disconnects where each is in its own enclosure, section or compartment. Six is the most that can be used.2026 NEC §230.71(B)
A service uses #2/0 Cu ungrounded conductors. What is the minimum copper grounding electrode conductor?
- a.#4 AWG✓
- b.#2 AWG
- c.#8 AWG
- d.#6 AWG
Table 250.66 puts 2/0 and 3/0 copper service conductors in the same row, which calls for a #4 copper grounding electrode conductor.2026 NEC Table 250.66
Where the grounding electrode conductor connects only to a made ground rod, what is the largest copper conductor size ever required?
- a.#4 AWG
- b.#6 AWG✓
- c.#8 AWG
- d.#2 AWG
The portion of the GEC connecting solely to a rod, pipe, or plate electrode need not be larger than #6 Cu.2026 NEC §250.66(A)
A service has 500-kcmil Cu ungrounded conductors per phase. What is the minimum copper grounded (neutral) service conductor for bonding purposes?
- a.1/0 AWG✓
- b.#1 AWG
- c.#2 AWG
- d.#4 AWG
The grounded service conductor must be at least the size in Table 250.102(C)(1); for 500-kcmil Cu phase conductors that value is 1/0 Cu.2026 NEC Table 250.102(C)(1)
Service phase conductors total 1,500 kcmil Cu per phase (over 1,100 kcmil). Using the 12.5% rule, what is the minimum copper main bonding jumper?
- a.4/0 AWG✓
- b.250 kcmil
- c.2/0 AWG
- d.3/0 AWG
Above 1,100 kcmil, the main bonding jumper is at least 12.5% of the phase area: 0.125 x 1,500 = 187.5 kcmil, so 4/0 Cu (211.6 kcmil) is the smallest that qualifies.2026 NEC §250.28(D)(1)
What is the minimum service disconnecting-means rating for a one-family dwelling?
- a.200 A
- b.125 A
- c.60 A
- d.100 A✓
The service disconnecting means for a one-family dwelling must be rated at least 100 A. The 60 A figure applies to other installations, not to a one-family dwelling.2026 NEC §230.79(C)
What is the minimum vertical clearance for an overhead service drop, not over 300 V to ground, above a residential driveway that is not subject to truck traffic?
- a.15 ft
- b.12 ft✓
- c.10 ft
- d.18 ft
Service-drop conductors up to 300 V to ground require 12 ft of clearance over residential property and driveways not subject to truck traffic.2026 NEC §230.24(B)(2)
At a separately derived system such as a transformer, what conductor connects the grounded conductor to the system grounding electrode?
- a.Equipment bonding jumper
- b.Main bonding jumper
- c.Grounding electrode conductor✓
- d.System bonding jumper
Under 250.30(A)(5), the grounding electrode conductor connects the grounded conductor of a separately derived system to the grounding electrode. Trap: the system bonding jumper in 250.30(A)(1) ties the grounded conductor to the equipment grounding path and enclosure, not to the electrode.2026 NEC §250.30(A)(5)
A single made electrode (ground rod) must be supplemented unless its resistance to earth does not exceed what value?
- a.10 ohms
- b.1 ohm
- c.25 ohms✓
- d.5 ohms
A single rod, pipe, or plate electrode must be supplemented by a second electrode. The Exception to 250.53(A)(2) drops that requirement where the single electrode has a resistance to earth of 25 ohms or less; the question directs you to it by asking when the supplement is not needed.2026 NEC §250.53(A)(2)
A metal underground water pipe qualifies as a grounding electrode if it is in direct contact with earth for at least how many feet?
- a.10 ft✓
- b.3 ft
- c.1 ft
- d.5 ft
A metal underground water pipe counts as a grounding electrode only if it is in direct contact with the earth for 10 ft or more.2026 NEC §250.52(A)(1)
A concrete-encased electrode (Ufer) must consist of at least how many feet of 1/2-in. or larger rebar or bare #4 Cu conductor?
- a.20 ft✓
- b.15 ft
- c.25 ft
- d.10 ft
A concrete-encased electrode requires at least 20 ft of 1/2-in (or larger) rebar or 20 ft of bare #4 Cu encased in the concrete footing/foundation.2026 NEC §250.52(A)(3)
A transformer (separately derived system) has 3/0 AWG copper derived (secondary) phase conductors. What is the minimum copper grounding electrode conductor for the SDS?
- a.#6 AWG
- b.#2 AWG
- c.#1 AWG
- d.#4 AWG✓
250.30(A)(5) sizes the grounding electrode conductor of a separately derived system from Table 250.66 using the derived phase conductors: 2/0 or 3/0 copper requires #4 copper. Trap: #6 is the limit only where the conductor connects solely to a rod, pipe or plate electrode.2026 NEC §250.30(A)(5)
A separately derived system has 250-kcmil copper derived conductors. Using the bonding table, what is the minimum copper system/supply-side bonding jumper?
- a.#2 AWG✓
- b.#4 AWG
- c.#1 AWG
- d.1/0 AWG
250.30(A)(1) and (A)(2) size these jumpers from Table 250.102(C)(1): over 3/0 through 350 kcmil copper requires a #2 copper bonding jumper. Trap: #4 is the value for 2/0 or 3/0 copper, one row too small for 250 kcmil.2026 NEC Table 250.102(C)(1)
Service-entrance conductors supply a 200-A continuous load. What minimum conductor ampacity is required?
- a.160 A
- b.200 A
- c.230 A
- d.250 A✓
230.42(A)(1) requires service-entrance conductors to carry the noncontinuous load plus 125% of the continuous load: 200 x 1.25 = 250 A. Trap: 200 A ignores the continuous-load multiplier.2026 NEC §230.42(A)(1)
A service has 500-kcmil copper ungrounded conductors. What is the minimum copper bonding jumper for the metal underground water pipe?
- a.1/0 AWG✓
- b.#2 AWG
- c.#4 AWG
- d.#3 AWG
250.104(A)(1) sizes the water-pipe bonding jumper from Table 250.102(C)(1): over 350 through 600 kcmil copper requires 1/0 copper. Trap: #2 is the value for over 3/0 through 350 kcmil, one row too small for 500 kcmil.2026 NEC §250.104(A)(1)
A service uses #3/0 AWG copper ungrounded conductors. What is the minimum copper grounding electrode conductor?
- a.#8 AWG
- b.#6 AWG
- c.#2 AWG
- d.#4 AWG✓
2026 NEC Table 250.66: 3/0 AWG copper ungrounded service conductors fall in the 2/0 or 3/0 row, which calls for a 4 AWG copper grounding electrode conductor.2026 NEC Table 250.66
A service uses 400-kcmil copper ungrounded conductors. What is the minimum copper grounding electrode conductor?
- a.1/0 AWG✓
- b.#2 AWG
- c.#3 AWG
- d.#1 AWG
2026 NEC Table 250.66: 400 kcmil copper ungrounded service conductors fall in the over 350 through 600 kcmil row, which calls for a 1/0 AWG copper grounding electrode conductor.2026 NEC Table 250.66
Where the grounding electrode conductor connects solely to a concrete-encased (Ufer) electrode, what is the largest copper size it is ever required to be?
- a.#2 AWG
- b.#4 AWG✓
- c.#8 AWG
- d.#6 AWG
2026 NEC 250.66(B): where the grounding electrode conductor connects only to a concrete-encased electrode, it never has to be larger than 4 AWG copper, whatever the service conductor size.2026 NEC §250.66(B)
A service has 3/0 AWG copper ungrounded conductors. What is the minimum copper grounded (neutral) service conductor for bonding purposes?
- a.#6 AWG
- b.#4 AWG✓
- c.#2 AWG
- d.#8 AWG
2026 NEC 250.24(D)(1) sizes the grounded service conductor from Table 250.102(C)(1): for 2/0 or 3/0 copper ungrounded conductors, the grounded conductor is at least 4 AWG copper.2026 NEC §250.24(D)(1)
Service ungrounded conductors are 350-kcmil copper per phase. Using the bonding table, what is the minimum copper main bonding jumper?
- a.#1 AWG
- b.#2 AWG✓
- c.#4 AWG
- d.1/0 AWG
2026 NEC 250.28(D)(1) with Table 250.102(C)(1): 350 kcmil copper falls in the over 3/0 through 350 kcmil row, which requires a 2 AWG copper main bonding jumper.2026 NEC §250.28(D)(1)
Service phase conductors total 2,000 kcmil Cu per phase (over 1,100 kcmil). Using the 12.5% rule, what is the minimum copper main bonding jumper?
- a.3/0 AWG
- b.350 kcmil
- c.250 kcmil✓
- d.4/0 AWG
2026 NEC 250.28(D)(1) and Table 250.102(C)(1), Note 1: above 1,100 kcmil copper the main bonding jumper must have at least 12.5% of the ungrounded conductor area: 0.125 x 2,000 = 250 kcmil.2026 NEC §250.28(D)(1)
Where two ground rods are used as the grounding electrode, what is the minimum required spacing between them?
- a.8 ft
- b.3 ft
- c.10 ft
- d.6 ft✓
2026 NEC 250.53(A)(3): where more than one rod, pipe, or plate electrode is installed, they must be at least 6 ft apart.2026 NEC §250.53(A)(3)
A driven ground rod electrode must have a minimum length in contact with the soil of:
- a.10 ft
- b.6 ft
- c.4 ft
- d.8 ft✓
2026 NEC 250.52(A)(5) and 250.53(A)(4): rod electrodes must be at least 8 ft long and installed so that at least 8 ft of length is in contact with the soil.2026 NEC §250.53(A)(4)
Overhead service-drop conductors must maintain what minimum vertical clearance above public streets, roads, and alleys?
- a.15 ft
- b.12 ft
- c.18 ft✓
- d.10 ft
2026 NEC 230.24(B)(4): overhead service conductors need 18 ft of vertical clearance over public streets, alleys, roads, and parking areas subject to truck traffic.2026 NEC §230.24(B)
A service has 250-kcmil copper ungrounded conductors. What is the minimum copper grounded (neutral) service conductor required by 250.24(D)(1)?
- a.1/0 AWG
- b.#4 AWG
- c.#2 AWG✓
- d.#1 AWG
2026 NEC 250.24(D)(1) with Table 250.102(C)(1): 250 kcmil copper falls in the over 3/0 through 350 kcmil row, which requires a 2 AWG copper grounded conductor.2026 NEC §250.24(D)(1)
A service uses 1/0 AWG copper ungrounded conductors. What is the minimum copper grounding electrode conductor?
- a.#4 AWG
- b.#2 AWG
- c.#6 AWG✓
- d.#8 AWG
2026 NEC Table 250.66: 1/0 AWG copper ungrounded service conductors fall in the 1 or 1/0 row, which calls for a 6 AWG copper grounding electrode conductor.2026 NEC Table 250.66
A service uses 750-kcmil copper ungrounded conductors. What is the minimum copper grounding electrode conductor?
- a.2/0 AWG✓
- b.3/0 AWG
- c.1/0 AWG
- d.#1 AWG
2026 NEC Table 250.66: 750 kcmil copper ungrounded service conductors fall in the over 600 through 1,100 kcmil row, which calls for a 2/0 AWG copper grounding electrode conductor.2026 NEC Table 250.66
A separately derived system (transformer) has 600-kcmil copper derived conductors. What is the minimum copper supply-side bonding jumper?
- a.1/0 AWG✓
- b.#1 AWG
- c.2/0 AWG
- d.#2 AWG
2026 NEC 250.30(A)(2) sizes a wire-type supply-side bonding jumper from Table 250.102(C)(1): 600 kcmil copper is in the over 350 through 600 kcmil row, which requires 1/0 AWG copper.2026 NEC §250.30(A)(2)
Service-entrance conductors supply a 150-A continuous load. What minimum conductor ampacity is required?
- a.187.5 A✓
- b.150 A
- c.200 A
- d.165 A
2026 NEC 230.42(A)(1): service-entrance conductors must have an ampacity of at least the noncontinuous load plus 125% of the continuous load: 150 x 1.25 = 187.5 A.2026 NEC §230.42(A)(1)
A service has 3/0 AWG copper ungrounded conductors. What is the minimum copper bonding jumper for the metal underground water pipe?
- a.#2 AWG
- b.#6 AWG
- c.#4 AWG✓
- d.#8 AWG
2026 NEC 250.104(A)(1) sizes the metal water piping bonding jumper from Table 250.102(C)(1): 2/0 or 3/0 copper service conductors require a 4 AWG copper bonding jumper.2026 NEC §250.104(A)(1)
Service phase conductors total 1,100 kcmil Cu per phase. Using the bonding table, what is the minimum copper main bonding jumper?
- a.1/0 AWG
- b.2/0 AWG✓
- c.#1 AWG
- d.3/0 AWG
2026 NEC 250.28(D)(1) with Table 250.102(C)(1): 1,100 kcmil copper is still in the over 600 through 1,100 kcmil row, which requires a 2/0 AWG copper main bonding jumper.2026 NEC §250.28(D)(1)
What is the maximum setting permitted for the ground-fault protection of equipment on a service disconnecting means?
- a.600 amperes
- b.800 amperes
- c.1000 amperes
- d.1200 amperes✓
Section 230.95(C) caps the ground-fault protection setting at 1200 amperes. The 1000 ampere figure is the disconnect rating at which the protection becomes required under 230.95(A), not the pickup setting.2026 NEC §230.95(C)
For ground-fault currents of 3000 amperes or more, what is the maximum time delay permitted for service ground-fault protection of equipment?
- a.1 second✓
- b.2 seconds
- c.5 seconds
- d.10 seconds
Section 230.95(C) limits the time delay to one second for ground-fault currents equal to or greater than 3000 amperes. Longer delays would let a high level arcing fault burn well past what the rule allows.2026 NEC §230.95(C)
When a service ground-fault protection system is first installed on site, how must it be performance tested?
- a.By operating the push-to-test button on the relay
- b.By an insulation resistance test of the service conductors
- c.By secondary injection
- d.By primary current injection✓
Section 230.95(E) requires the system to be performance tested when first installed on site, by qualified persons using a primary current injection process that follows the instructions provided with the equipment, with a written record kept available to the authority having jurisdiction. A push-to-test button, secondary injection and an insulation resistance test are not the process the rule names.2026 NEC §230.95(E)
Where the main bonding jumper in a service panelboard is a screw only, how must the screw be identified?
- a.By a white or gray marking on the screw head
- b.By a tag reading BONDING attached next to the screw
- c.By a green finish that is visible with the screw installed✓
- d.By a listing mark stamped on the screw threads
Section 250.28(B) requires a main or system bonding jumper that is a screw only to have a green finish that can be seen with the screw installed. White or gray would suggest a grounded conductor, and a tag or a stamped mark is not what this section calls for.2026 NEC §250.28(B)
One common grounding electrode conductor of the wire type serves several separately derived systems. What is the smallest copper conductor permitted for the common grounding electrode conductor under the main rule?
- a.1/0 AWG
- b.2/0 AWG
- c.3/0 AWG✓
- d.250 kcmil
Section 250.30(A)(6)(a)(1) requires a wire type common grounding electrode conductor to be not smaller than 3/0 AWG copper or 250 kcmil aluminum. Picking 250 kcmil mixes up the aluminum value with the copper value. The taps from each system are sized separately from the derived conductors of the system they serve.2026 NEC §250.30(A)(6)