Which trap is prohibited under IRC §P3201.5?
- a.A trap integral with a water closet
- b.A tubular trap with a slip joint
- c.A P trap
- d.An S trap✓
Prohibited traps include bell traps, drum traps, S traps, crown-vented traps and traps with moving parts or interior partitions. S traps siphon their own seal.IRC §P3201.5
Under IRC §P3201.6, the vertical distance from a fixture outlet to its trap weir may not exceed:
- a.96 inches
- b.60 inches
- c.4 inches
- d.24 inches✓
The vertical distance from the fixture outlet to the trap weir is not more than 24 inches, and the horizontal distance not more than 30 inches. A longer drop gives the waste enough velocity to siphon the trap.IRC §P3201.6
Under IRC §P3201.6, one trap may serve a kitchen sink with how many compartments at most?
- a.Eight
- b.Six
- c.Three✓
- d.Ten
One trap may serve a single fixture with not more than three compartments, or up to three lavatories or sinks, where the outlets are within 30 inches of the trap.IRC §P3201.6
Under IRC §P3201.4, a building trap (a running trap on the building drain) is:
- a.Required with a basement
- b.Prohibited✓
- c.Optional with a cleanout
- d.Required on every house
Building traps are not installed, except in special cases where sewer gases are extremely corrosive or noxious, as directed by the building official.IRC §P3201.4
Under IRC Table P3201.7, the minimum trap size for a lavatory is:
- a.1-1/4 inches✓
- b.1/2 inch
- c.3-1/2 inches
- d.2-1/2 inches
A lavatory uses a 1-1/4 inch trap; bathtubs, showers, kitchen sinks and laundry tubs use 1-1/2 inches.IRC Table P3201.7
Under IRC Table P3201.7, the minimum trap size for a clothes washer standpipe is:
- a.1 inch
- b.2 inches✓
- c.1/2 inch
- d.3/4 inch
A clothes washer standpipe has a 2-inch trap, because the washer pump discharges at a high rate.IRC Table P3201.7
A floor drain in a house is rarely used and its trap could dry out. Under IRC §P3201.2.1, the trap seal must be protected by:
- a.A trap seal primer valve or other approved trap seal protection✓
- b.A second trap installed directly below the first one
- c.A coat of oil-based paint on the inside of the trap
- d.A threaded brass plug that is left in place at all times except cleaning
Traps subject to evaporation are protected by a potable water-supplied trap seal primer valve, a waste-supplied primer, or an approved barrier-type trap seal protection device.IRC §P3201.2.1
Under IRC Table P3105.1, the maximum distance from the weir of a 1-1/2 inch trap to its vent is:
- a.1 foot
- b.20 feet
- c.6 feet✓
- d.40 feet
At 1/4 inch per foot the limits are 5 feet for a 1-1/4 inch trap, 6 feet for 1-1/2 inch, 8 feet for 2 inch and 12 feet for 3 inch.IRC Table P3105.1
Under IRC Table P3105.1, the maximum distance from the weir of a 2-inch trap to its vent is:
- a.8 feet✓
- b.2 feet
- c.50 feet
- d.25 feet
A 2-inch trap arm sloped at 1/4 inch per foot may run 8 feet to its vent.IRC Table P3105.1
Under IRC §P3105.2, the total fall in a fixture drain from the trap weir to the vent fitting may not exceed:
- a.Four pipe diameters
- b.Six pipe diameters
- c.Ten pipe diameters
- d.One pipe diameter✓
If the trap arm falls more than one pipe diameter, the top of the pipe at the vent drops below the trap weir and the arm can run full and siphon the trap.IRC §P3105.2
Under IRC §P3105.3, a vent may not connect to the trap arm closer to the trap weir than:
- a.Twelve pipe diameters
- b.Twenty pipe diameters
- c.Eight pipe diameters
- d.Two pipe diameters✓
A vent within two pipe diameters of the trap weir is a crown vent; it clogs with waste and is prohibited.IRC §P3105.3
Under IRC §P3103.1.1, an open vent pipe through the roof of a house must extend above the roof at least:
- a.6 inches✓
- b.1/2 inch
- c.36 inches
- d.72 inches
Vent terminals extend at least 6 inches above the roof or above the anticipated snow accumulation; where the roof is used as a deck or similar space, they extend 7 feet.IRC §P3103.1.1
Under IRC §P3103.5, a vent terminal may not be located directly beneath a door, openable window or air intake, and may not be within what horizontal distance of one unless it is raised well above the opening?
- a.50 feet
- b.100 feet
- c.1 foot
- d.10 feet✓
A vent terminal is kept 4 feet below, or 10 feet horizontally from, an opening into the building, or is carried up above the top of the opening.IRC §P3103.5
Under IRC §P3102.1, every house plumbing drainage system must have:
- a.At least one vent pipe that extends to the outdoors✓
- b.At least two vent stacks of 4 inches each
- c.At least one air admittance valve in the attic space
- d.At least one building trap at the foundation
The drainage system has at least one vent that runs undiminished to the open air, connected to a drainage stack or the building drain. Air admittance valves cannot replace it.IRC §P3102.1
Under IRC §P3104.4, a dry vent rising from a fixture drain must rise vertically before it offsets horizontally to at least:
- a.6 inches above the flood level rim of the fixture✓
- b.The underside of the floor joists below the fixture
- c.6 inches below the trap weir of the fixture
- d.36 inches above the finished ceiling of the room
Vents rise vertically to at least 6 inches above the flood level rim of the highest fixture served before offsetting, so that waste cannot flow into a horizontal vent if the drain stops up.IRC §P3104.4
Under IRC §P3104.2, vent pipes must be graded so that:
- a.Moisture collects in a low loop below each fixture
- b.Moisture drains back to the soil or waste pipe by gravity✓
- c.They rise 1 inch per foot toward the fixture trap
- d.They are perfectly level from the fixture to the stack
Vent and branch vent pipes are graded and connected so as to drain back to the drainage pipe by gravity; sags hold condensate and block the vent.IRC §P3104.2
Under IRC §P3104.3, where a vent connects to a horizontal drain, the connection is made:
- a.Through a saddle on the side of the pipe
- b.Above the centerline of the horizontal drain pipe✓
- c.Downstream of the building drain cleanout
- d.At the bottom of the horizontal drain pipe, through a wye
Every dry vent connecting to a horizontal drain connects above the centerline of the drain, so waste does not flow into and foul the vent.IRC §P3104.3
Under IRC §P3113.1, the diameter of a vent must be at least 1-1/4 inches and not less than:
- a.Three times the diameter of the drain it serves
- b.One-half the diameter of the drain it serves✓
- c.Twice the diameter of the drain it serves
- d.One-tenth the diameter of the drain it serves
Individual vents, branch vents, circuit vents, vent stacks and stack vents are at least one-half the required diameter of the drain served, and no vent pipe is smaller than 1-1/4 inches.IRC §P3113.1
Under IRC §P3113.1, a vent with a developed length of more than 40 feet must be:
- a.Replaced with two air admittance valves
- b.Fitted with a cleanout at the midpoint of the run
- c.Reduced by one nominal pipe size for its entire developed length
- d.Increased by one nominal pipe size for its entire length✓
Vents longer than 40 feet in developed length are increased one nominal pipe size for the entire developed length.IRC §P3113.1
Two lavatories are set back to back and connect at the same level to one vertical drain. Under IRC §P3107.1, the single vent serving both traps is called:
- a.A stack vent
- b.A common vent✓
- c.A circuit vent
- d.A relief vent
An individual vent may vent two traps or trapped fixtures as a common vent, where the fixtures are on the same floor level.IRC §P3107.1
Under IRC §P3108.1, a horizontal wet vent may serve any combination of fixtures within:
- a.Any group of fixtures located on two adjoining floors
- b.One kitchen and one laundry on the same floor level
- c.Two bathroom groups located on the same floor level✓
- d.Six bathroom groups located on any floor levels
Any combination of fixtures within two bathroom groups on the same floor level may be vented by a horizontal wet vent; kitchen sinks and clothes washers are not bathroom group fixtures.IRC §P3108.1
Under IRC Table P3108.3, a 2-inch wet vent may carry a drainage load of not more than:
- a.24 drainage fixture units
- b.14 drainage fixture units
- c.4 drainage fixture units✓
- d.40 drainage fixture units
The wet vent sizes are 1-1/2 inch for 1 dfu, 2 inch for 4 dfu, 2-1/2 inch for 6 dfu and 3 inch for 12 dfu.IRC Table P3108.3
A kitchen island sink cannot have a conventional vent rising in a wall. Under IRC §P3112, the island fixture vent must rise:
- a.No higher than the cabinet floor before turning down
- b.Above the roof through the center of the countertop and ceiling
- c.Above the drainage outlet of the fixture before turning down✓
- d.No higher than the trap weir before turning down
An island fixture vent rises vertically to above the drainage outlet of the fixture before offsetting horizontally or vertically downward, and has cleanouts for rodding.IRC §P3112.2
Under IRC §P3114.4, an individual air admittance valve must be located above the horizontal branch drain or fixture drain it vents by at least:
- a.4 inches✓
- b.48 inches
- c.1/4 inch
- d.96 inches
Individual and branch-type air admittance valves are at least 4 inches above the horizontal branch drain or fixture drain being vented; stack-type valves are at least 6 inches above the flood level rim of the highest fixture.IRC §P3114.4
An air admittance valve is installed in an attic. Under IRC §P3114.4, it must be above the insulation by at least:
- a.1/2 inch
- b.6 inches✓
- c.48 inches
- d.72 inches
Air admittance valves installed in attics are at least 6 inches above insulation materials, so that the insulation does not block the air inlet.IRC §P3114.4
Under IRC §P3114.5, an air admittance valve must be installed in a location that:
- a.Is sealed airtight inside the wall cavity
- b.Is below the flood level rim of the fixture served
- c.Is accessible and allows air to enter the valve✓
- d.Is inside a supply or return air plenum
Access is provided to all air admittance valves, and the valve is in a ventilated space that allows air to enter it. Valves are not installed in supply or return air plenums.IRC §§P3114.5, P3114.8
Under IRC §P3114.3, air admittance valves are installed:
- a.After the DWV testing required at rough-in is finished✓
- b.Only after the house has been occupied for 30 days
- c.Before the slab is poured, below the finished floor
- d.Before the rough-in water test, to seal the vent openings
The valves are installed after the DWV testing required by the code has been performed, because the test pressure can damage or unseat the valve.IRC §P3114.3
Under IRC §P3111, a combination waste and vent system in a house may serve:
- a.Food waste disposers and bathtubs
- b.Roof drains and area drains
- c.Floor drains, sinks and lavatories✓
- d.Water closets and clothes washers
A combination waste and vent system is limited to floor drains, sinks and lavatories, and does not receive the discharge of a food waste disposer.IRC §P3111.1
Under IRC §P3103.2, where the winter design temperature is below 0°F, a vent extension through the roof must be at least:
- a.8 inches in diameter, to carry snow melt
- b.3 inches in diameter, to resist frost closure✓
- c.12 inches in diameter, to allow inspection
- d.1 inch in diameter, to reduce heat loss
Where the 97.5-percent winter design temperature is less than 0°F, vent extensions through a roof or wall are at least 3 inches in diameter, with any increase made inside the building. Most of Texas is warmer than this threshold.IRC §P3103.2
New gas piping in a house is pressure tested. Under IRC §G2417.4.1, the test pressure must be at least 1-1/2 times the working pressure and not less than:
- a.1/4 psig
- b.3 psig✓
- c.60 psig
- d.150 psig
The test pressure is not less than 1-1/2 times the proposed maximum working pressure and never less than 3 psig.IRC §G2417.4.1 (IFGC §406.4.1)
Under IRC §G2417.4.2, the pressure test on residential gas piping must be held for at least:
- a.10 seconds
- b.10 minutes✓
- c.48 hours
- d.12 hours
The test duration is not less than 10 minutes, with no drop in pressure shown on the gauge.IRC §G2417.4.2 (IFGC §406.4.2)
Which may NOT be used as the test medium for gas piping under IRC §G2417.2?
- a.Oxygen✓
- b.Nitrogen
- c.Air
- d.Carbon dioxide
The test medium is air, nitrogen, carbon dioxide or an inert gas. Oxygen is never used, because it reacts violently with oil and hydrocarbons.IRC §G2417.2 (IFGC §406.2)
Under IRC §G2415.12, underground gas piping must be buried at least:
- a.72 inches deep
- b.48 inches deep
- c.12 inches deep✓
- d.1 inch deep
Underground piping systems are installed at a minimum depth of 12 inches below grade; individual lines to outdoor lights and grills may be at 8 inches where approved.IRC §G2415.12 (IFGC §404.12)
Under IRC §G2415.17, plastic (polyethylene) gas pipe may be installed:
- a.Above ground on exterior walls
- b.In return air plenums and ducts
- c.Outdoors and underground only✓
- d.Indoors in walls and attics only
Plastic pipe is installed outdoors underground only, apart from listed anodeless risers and similar exceptions.IRC §G2415.17.1 (IFGC §404.17.1)
Under IRC §G2415.17.3, plastic gas pipe buried in a yard must have installed next to it:
- a.A galvanized steel support cable
- b.A yellow insulated copper tracer wire✓
- c.A perforated plastic drain tile
- d.A red plastic warning ribbon and nothing more
A yellow insulated copper tracer wire, or other approved conductor, at least 18 AWG is installed adjacent to underground non-metallic piping and brought above ground at each end, so the pipe can be located.IRC §G2415.17.3 (IFGC §404.17.3)
Under IRC §G2415.3, gas piping may NOT be installed in or through:
- a.An interior partition wall, through holes bored in the center of studs
- b.An accessible attic above the ceiling insulation
- c.A ventilated crawl space under the floor joists
- d.A circulating air duct, clothes chute, chimney or dumbwaiter✓
Piping is not installed in or through a ducted supply, return or exhaust, a clothes chute, a chimney or gas vent, a dumbwaiter or an elevator shaft.IRC §G2415.3 (IFGC §404.3)
Which fitting may NOT be used in concealed gas piping under IRC §G2415.5?
- a.A union✓
- b.A threaded tee
- c.A threaded elbow
- d.A threaded coupling
Fittings in concealed locations are limited to threaded elbows, tees and couplings, brazed fittings and listed fittings. Unions, bushings and compression couplings are not concealed.IRC §G2415.5 (IFGC §404.5)
Under IRC §G2420.5.1, the shutoff valve for a gas range must be in the same room as the appliance and within:
- a.100 feet of the appliance
- b.25 feet of the gas meter
- c.60 feet of the appliance
- d.6 feet of the appliance✓
Each appliance has a shutoff valve in the same room, within 6 feet, upstream of the union or connector it serves, with access.IRC §G2420.5.1 (IFGC §409.5.1)
Under IRC §G2422.1.2.1, a flexible gas appliance connector may be no longer than:
- a.25 feet
- b.6 feet✓
- c.50 feet
- d.1 foot
Connectors are not more than 6 feet in overall length, are not concealed and do not pass through walls, floors, partitions or appliance housings.IRC §G2422.1.2.1 (IFGC §411.1.3.1)
Under IRC §G2419.4, a sediment trap must be installed:
- a.Upstream of the gas meter, as close to the street main as is practical
- b.At the vent connector, to collect condensate from the flue gases
- c.Downstream of the appliance shutoff valve, as close to the appliance inlet as practical✓
- d.At the highest point of the piping system, to release any air trapped in the system after testing
Where a sediment trap is not part of the appliance, one is installed downstream of the shutoff valve as close to the inlet as practical. Ranges, clothes dryers, decorative appliances and outdoor grills need not have one.IRC §G2419.4 (IFGC §408.4)
Corrugated stainless steel tubing (CSST) gas piping in a house that is not listed with an arc-resistant jacket must, under IRC §G2411.2, be:
- a.Bonded to the electrical grounding electrode system✓
- b.Buried in the attic insulation for protection
- c.Isolated from every metal part of the building
- d.Painted yellow along its full length after installation
CSST that is not listed with an arc-resistant jacket or coating is bonded to the electrical service grounding electrode system (or the lightning protection grounding electrode system, where provided) with a bonding jumper not smaller than 6 AWG copper, no longer than 75 feet.IRC §G2411.2 (IFGC §310.2)
Under IRC §G2411.2, the bonding jumper for CSST gas piping must be at least:
- a.22 AWG copper
- b.6 AWG copper✓
- c.26 AWG copper
- d.18 AWG copper
The bonding jumper is not smaller than 6 AWG copper wire or equivalent, and is not longer than 75 feet.IRC §G2411.2.1 (IFGC §310.2.1)
Under IRC §G2412.5, exposed gas piping that is not black steel pipe must be identified by a yellow label marked "Gas" at intervals of not more than:
- a.100 feet
- b.6 inches
- c.5 feet✓
- d.50 feet
Exposed piping other than steel pipe is identified by a yellow label marked "Gas" in black letters, spaced at intervals not exceeding 5 feet.IRC §G2412.5 (IFGC §401.5)
Gas piping passes through a wall stud less than 1-1/2 inches from the face of the stud. Under IRC §G2415.7, it must be protected by:
- a.Plastic conduit
- b.Fiberglass tape
- c.Foam pipe insulation
- d.Steel shield plates✓
Where piping other than black or galvanized steel is less than 1-1/2 inches from the face of the framing, shield plates of steel at least 0.0575 inch thick cover the area, extending 4 inches beyond the member.IRC §G2415.7 (IFGC §404.7)
Under IRC Table G2424.1, 1/2-inch steel gas pipe run horizontally must be supported at intervals of not more than:
- a.30 feet
- b.20 feet
- c.1 foot
- d.6 feet✓
Steel pipe is supported every 6 feet for 1/2 inch, 8 feet for 3/4 and 1 inch, and 10 feet for 1-1/4 inch and larger horizontal runs.IRC Table G2424.1 (IFGC Table 415.1)
A house has a furnace of 80,000 Btu/h, a water heater of 40,000 Btu/h and a range of 60,000 Btu/h on natural gas with a heating value of 1,000 Btu per cubic foot. The total demand used to size the main is:
- a.1,800 cubic feet per hour
- b.18 cubic feet per hour
- c.180 cubic feet per hour✓
- d.80 cubic feet per hour
80,000 + 40,000 + 60,000 = 180,000 Btu/h; divided by 1,000 Btu per cubic foot this is 180 cubic feet per hour.IRC §G2413 (IFGC §402)
Under IRC §G2413, a section of gas piping is sized from the tables using the load it carries and:
- a.The height of the house from grade to the roof ridge
- b.The age of the house and the type of gas meter
- c.The number of elbows and tees between the meter and the first outlet
- d.The length of piping from the meter to the most remote outlet✓
In the longest-length method, every section is sized from the column for the distance from the point of delivery to the most remote outlet, using the load that section carries.IRC §G2413.4 (IFGC §402.4)
Under IRC §G2406.2, a single listed unvented room heater with an oxygen depletion safety shutoff may be installed in a bathroom where its input does not exceed:
- a.6,000 Btu/h✓
- b.600 Btu/h
- c.80,000 Btu/h
- d.40,000 Btu/h
One listed wall-mounted unvented room heater with an oxygen depletion safety shutoff is permitted in a bathroom at up to 6,000 Btu/h and in a bedroom at up to 10,000 Btu/h, where combustion air is adequate.IRC §G2406.2 (IFGC §303.3)
Under IRC §G2439, the exhaust duct of a gas clothes dryer in a house must:
- a.Connect to the water heater vent through a listed draft hood
- b.Terminate in the attic and be joined with long sheet-metal screws
- c.Terminate in the crawl space at least 3 feet from any vent
- d.Terminate outdoors and have no screws protruding into the airway✓
Dryer exhaust ducts convey moisture and combustion products outdoors, are of smooth metal, and are joined without fasteners that protrude more than 1/8 inch into the duct, where lint would collect.IRC §G2439 (IFGC §614)