浏览所有题目

这些题目考的数字,按章节排在可打印的彩色高密度页面上: 速记册,$9.99 →

拥有完整的 CSLB Law & Business 学习指南 —— PDF + EPUB,$24.99 →

查看每道题的答案和解析——可按主题或全部一起学习。

商业财务

245 道题
101. 持照人可以根据Bus. & Prof. Code §7071.12向州财政官存入现金或等价证券,代替提交承包商执照保证金。要完全以现金替代$25,000执照保证金,持照人必须存入:
a.$5,000 现金,按面值 5:1 的杠杆比率
b.全额 $25,000 交由州财政官保管✓
c.$10,000 现金加 $15,000 担保保证金
d.$25,000 存入有息的银行托管账户

B&P §7071.12 允许持照人以现金、本票或指定证券按其所替代保证金的全额缴存,且必须存入州财政官处;该存款按与担保保证金相同的规则应对索赔,若不足以全额清偿,则依 §7071.11(a) 按比例分配。法条中没有杠杆比率,因此 $5,000 的存款担保不了任何金额。也不存在部分替代:不能用现金与担保保证金拼凑出所需数额。私人银行的托管账户即使有存款保险,也不是向州财政官缴存。

Bus. & Prof. Code §7071.12; §7071.11(a)
102. 负责管理员工(RME)与负责管理主管(RMO)的区别在于RME必须:
a.与持照实体的所有者之一有血缘或婚姻关系
b.完全拥有持照实体10%以上的股权
c.以本人名义持A类执照
d.是真正的员工,每周至少工作32小时✓

RMO 是持照实体的主管人员;RME 则是该实体长期雇用的真正员工,而 16 CCR §823 要求非真正所有人的合格人员每周至少32小时、或企业营业总时数的80%(以较少者为准)实施直接监督与控制。持股10%以上恰恰是免除该工时要求的条件,因此那一项描述的是豁免情形而非 RME 本身。§7068.1 中根本没有亲属关系的要求。执照类别取决于该实体所取得的资质,而不是 RME 个人必须持有的执照。

B&P §7068.1; 16 CCR §823
103. 一家总承包商将其现场框架工分类为独立承包人并签发1099-NEC而非W-2。如果该框架工后来根据AB-5和联邦普通法测试被认定为W-2雇员,总承包商可能承担:
a.补缴工资税款,外加错误分类的处罚✓
b.只要工人签了确认书就毫无责任
c.仅 1099 与 W-2 净额之间的差额
d.仅一笔 $250 的信息申报罚款

错误分类会叠加两类责任。税务一侧是 IRC §3402 与 §3111 项下的联邦所得税预扣和雇主、雇员两部分 FICA,§3301 项下的 FUTA,以及通过 EDD 缴纳的加州 PIT、SDI 与 UI;只有在并非故意时才能适用 IRC §3509 的降低税率。劳动一侧是《劳工法》§226.8 每次故意违规 $5,000 至 $15,000、构成惯常做法时 $10,000 至 $25,000 的罚款,外加 §226(e) 的工资单罚款和无保险雇主的工伤赔偿风险。签署确认书毫无作用,因为《劳工法》§2775(a) 明确不理会当事人所用的名义。信息申报罚款与上述数额相比只是零头。

Labor Code §226.8; §2775(a); IRC §3509
104. 对于在 2026 年 1 月 1 日当日或之后订立的私人工程合同,每笔付款最多可扣留多少留置金?
a.合同怎么写就怎么扣;私人工程留置金没有法定上限
b.不超过 5%,另有两项范围狭窄的法定例外✓
c.不超过 10%,这是私人工程长期沿用的惯例
d.不超过 5%,但该上限只适用于公共工程

加州民法典 §8811 由 SB 61 新增,适用于 2026 年 1 月 1 日当日或之后订立的合同,将私人工程的留置金上限定为 5%——既是每笔付款的 5%,也是合同总价的 5%——并且适用于每一层级:业主对总承包商、总承包商对分包商,以及再往下(b)。「范围狭窄」指的两项例外是:非混合用途且不超过四层的住宅项目;以及在投标时或之前已收到书面通知、却未能提供由核准保险人出具的履约及付款保证金的分包商。为执行该条提起诉讼的胜诉方可获判律师费。(a) 说的是 2026 年之前的法律状态,那时私人工程的留置金确实纯属合同约定。(c) 正是该法要终结的 10% 惯例;如今它只在上述两项例外之内、以及 2026 年之前签订的合同上继续存在。(d) 数字对但范围错——公共合同法典 §7201 多年来已将多数州与地方公共工程限制在 5%,而 §8811 把同一上限延伸到了私人工程。

Civil Code §8811; Public Contract Code §7201
105. 自2023年1月1日起生效,加州承包商执照保证金提高至:
a.$25,000✓
b.$50,000
c.$15,000
d.$12,500

B&P §7071.6 经 SB 607 修订,自2023年1月1日起把承包商执照保证金从 $15,000 提高到 $25,000,§7071.9 项下的合格个人保证金同时提高到 $25,000;§7071.6.5 项下的 LLC 员工与工人保证金为 $100,000。$15,000 与 $12,500 都是2023年之前的数额,其中 $12,500 是2016年之前的水平。没有任何执照类别的保证金是 $50,000。

Bus. & Prof. Code §7071.6 (SB 607, 2021)
106. 何时需要除标准$25,000承包商执照保证金之外的合格个人保证金(BQI)?
a.持照人雇用的工人超过10名时
b.持照人同时经营两个 CSLB 分类时
c.持照人自行承保工伤赔偿保险时
d.合格人员持股低于该实体10%时✓

B&P §7071.9 规定,只要 RMO 或 RME 不是持照实体至少10%的真正所有人,就必须另行缴存 $25,000 的合格个人保证金:没有实际股权的合格人员在监督失职时损失有限,该保证金为公众提供第二条追偿途径。员工人数与 §7071.9 无关。持有多个分类改变的是可承接的工作范围,而不是保证金要求。自行承保工伤赔偿是《劳工法》§3700 另设的程序,有其自身的担保要求。

Bus. & Prof. Code §7071.9
107. A contractor's direct job costs are $8,000. He applies a 25% markup on cost. What is the total price he charges the customer?
a.$6,000
b.$10,666
c.$10,000✓
d.$8,250

Markup is calculated on cost. $8,000 x 25% = $2,000 markup. Price = $8,000 + $2,000 = $10,000. (Note: a 25% markup is NOT the same as a 25% margin; a 25% margin would produce a price of $8,000 / 0.75 = $10,666.)

108. A job costs $12,000 and is sold for $15,000. What is the gross PROFIT MARGIN (as a percentage of the selling price)?
a.20%✓
b.12.5%
c.25%
d.15%

Gross profit = $15,000 - $12,000 = $3,000. Margin is profit divided by SELLING price: $3,000 / $15,000 = 0.20 = 20%. (The markup, by contrast, would be $3,000 / $12,000 = 25%.)

109. A contractor wants a 40% gross margin on a job whose direct costs are $6,000. What selling price must he set?
a.$8,400
b.$9,000
c.$8,000
d.$10,000✓

For a target margin, divide cost by (1 - margin). Selling price = $6,000 / (1 - 0.40) = $6,000 / 0.60 = $10,000. Check: profit = $10,000 - $6,000 = $4,000, and $4,000 / $10,000 = 40% margin. Marking up 40% on cost ($8,400) would give only a 28.6% margin, a common and costly error.

110. A 50% markup on cost is equivalent to what gross profit margin?
a.40%
b.25%
c.50%
d.33.3%✓

Take cost = $100. A 50% markup adds $50, giving a price of $150. Margin = profit / price = $50 / $150 = 33.3%. Markup and margin are different: markup is on cost, margin is on price.

111. A contractor's price is $20,000 and direct cost is $16,000. What is the markup percentage on cost?
a.16%
b.80%
c.20%
d.25%✓

Markup = profit / cost. Profit = $20,000 - $16,000 = $4,000. Markup = $4,000 / $16,000 = 0.25 = 25%. (The margin on price would be $4,000 / $20,000 = 20%.)

112. To achieve a 30% gross margin, what markup on cost must a contractor apply?
a.42.9%✓
b.70%
c.30%
d.23.1%

The markup that yields a given margin = margin / (1 - margin). Here 0.30 / 0.70 = 0.4286 = 42.9%. Check with cost $100: 42.9% markup gives price $142.90; margin = $42.90 / $142.90 = 30%.

113. A contractor buys materials for $2,000 and applies a 35% markup. What is the marked-up material price?
a.$2,700✓
b.$2,070
c.$2,350
d.$3,077

$2,000 x 35% = $700 markup. Price = $2,000 + $700 = $2,700. Markup is added to cost.

114. Which statement about markup and margin is correct?
a.Margin exceeds markup for the same dollar profit
b.Margin is figured on price, markup on cost✓
c.Markup is figured on the selling price
d.Markup and margin are the same percentage

Margin states profit as a percentage of the selling PRICE; markup states the same dollar profit as a percentage of COST. Because price is the larger base, margin is always the smaller percentage, which is why the first option has it backwards. The third option swaps the bases outright. The fourth would hold only if cost equalled price, which would mean no profit at all.

115. A job sells for $50,000 with a 20% gross margin. What are the direct job costs?
a.$10,000
b.$41,667
c.$40,000 markup base only
d.$40,000✓

Margin 20% means profit is 20% of the $50,000 price = $10,000. Costs = price - profit = $50,000 - $10,000 = $40,000.

116. A contractor applies a 100% markup on a $3,000 cost. What margin does that represent, and what is the price?
a.Price $6,000; margin 100%
b.Price $6,000; margin 33%
c.Price $6,000; margin 50%✓
d.Price $3,000; margin 50%

100% markup doubles cost: price = $3,000 + $3,000 = $6,000. Margin = profit / price = $3,000 / $6,000 = 50%. A 100% markup always equals a 50% margin.

117. A contractor's annual overhead is $120,000 and he expects $600,000 in direct job costs this year. What overhead rate should he add to each job's direct cost to recover overhead?
a.25%
b.12%
c.5%
d.20%✓

Overhead recovery rate = annual overhead / annual direct costs = $120,000 / $600,000 = 0.20 = 20%. He adds 20% of each job's direct cost to cover overhead, then adds profit on top.

118. Which of the following is an example of OVERHEAD (indirect cost) rather than a direct job cost?
a.A subcontractor's plumbing invoice for the project
b.Office rent and the bookkeeper's salary✓
c.Wages of a carpenter framing the house
d.Lumber delivered to the jobsite

Overhead consists of indirect costs that keep the business running but are not tied to one specific job, such as office rent, administrative salaries, insurance, and utilities. Materials, on-site labor, and subcontractors are direct costs charged to a particular job.

119. A contractor's job has $10,000 direct costs. He adds 15% for overhead and then 10% profit on the resulting subtotal. What is the final price?
a.$12,500
b.$11,650
c.$12,650✓
d.$12,750

Direct cost $10,000 + 15% overhead ($1,500) = $11,500 subtotal. Then 10% profit on $11,500 = $1,150. Final price = $11,500 + $1,150 = $12,650. Order matters: overhead first, then profit on the total.

120. Overhead costs are best described as:
a.Ongoing costs not chargeable to a job✓
b.Costs that rise and fall with each job's size
c.The materials and labour bought for one job
d.The money left over after every cost is paid

Overhead is the indirect, ongoing cost of running the business — rent, office wages, insurance, trucks, licences — which cannot be billed to any single job and must be recovered across all of them through markup. Costs that scale with the job are direct costs, and materials and labour for a job are the clearest example of direct cost. What is left after every cost is paid is net profit, which comes after overhead rather than being it.

121. A contractor completes $800,000 in revenue with $560,000 direct costs and $160,000 overhead. What is the net profit and net profit margin?
a.$240,000; 30%
b.$80,000; 10%✓
c.$80,000; 14.3%
d.$80,000; 12.5%

Net profit = revenue - direct costs - overhead = $800,000 - $560,000 - $160,000 = $80,000. Net profit margin = $80,000 / $800,000 = 10%.

122. If a contractor underestimates his overhead rate when bidding, the most likely result is:
a.Bids come in high and he wins fewer jobs
b.Jobs are underpriced and the company loses money✓
c.His income taxes fall along with the reported profit
d.Overhead is absorbed by his subcontractors

When the overhead rate built into the markup is too low, every bid is priced below the true cost of doing business: the job can show a profit on its own sheet while the company loses money once real overhead is paid. Bidding high is the result of the opposite error, over-recovering overhead. Lower taxes follow a lower profit but are a symptom, not the harm. And subcontractors price their own overhead into their own numbers; nothing shifts the general contractor's overhead onto them.

123. A contractor has fixed costs of $90,000 per year. His contribution margin (price minus variable cost) is 30% of revenue. What annual revenue does he need to break even?
a.$300,000✓
b.$27,000
c.$117,000
d.$270,000

Break-even revenue = fixed costs / contribution margin ratio = $90,000 / 0.30 = $300,000. At $300,000 revenue, the 30% contribution margin ($90,000) exactly covers fixed costs, leaving zero profit.

124. A contractor's fixed (overhead) costs are $60,000/year. Each job nets $2,000 of contribution margin. How many jobs must he complete to break even?
a.12 jobs
b.20 jobs
c.30 jobs✓
d.60 jobs

Break-even units = fixed costs / contribution margin per job = $60,000 / $2,000 = 30 jobs. Below 30 jobs he loses money; above 30 he earns profit.

125. The break-even point is best defined as the level of sales at which:
a.Gross revenue equals the year's overhead alone
b.Variable costs exactly equal the fixed costs
c.Total revenue equals total costs exactly✓
d.Profit per job hits its highest point

Break-even is the sales volume at which total revenue equals total costs, fixed and variable together, so the result is neither profit nor loss. Covering overhead alone is not break-even, because direct job costs still have to be paid. Variable costs equalling fixed costs is an arbitrary coincidence with no meaning for profit. Maximum profit is a different point entirely, and it lies well above break-even.

126. A contractor has $100,000 fixed costs and a contribution margin ratio of 25%. If he wants a $50,000 profit, what revenue is required?
a.$400,000
b.$200,000
c.$150,000
d.$600,000✓

Required revenue = (fixed costs + target profit) / contribution margin ratio = ($100,000 + $50,000) / 0.25 = $150,000 / 0.25 = $600,000.

127. If a contractor's fixed costs rise while his contribution margin ratio stays the same, the break-even point will:
a.Increase✓
b.Stay the same
c.Decrease
d.Become zero

Break-even revenue = fixed costs / contribution margin ratio. Raising the numerator (fixed costs) while holding the ratio constant increases the break-even sales volume: he must sell more just to cover the higher fixed costs.

128. A framing job needs 3,200 board feet of lumber at $0.85 per board foot, plus 40 labor hours at $45/hour. What is the estimated direct cost?
a.$4,520✓
b.$3,920
c.$4,840
d.$2,720

Materials are 3,200 x $0.85 = $2,720 and labour is 40 x $45 = $1,800, so the direct cost is $4,520. $3,920 comes from pricing the labour at $30 an hour instead of $45. $4,840 comes from reading the lumber at $0.95 a board foot. $2,720 is the materials alone, with the labour line left out of the estimate.

129. A contractor estimates a job at 120 labor hours. Actual hours worked were 150. By what percentage did labor hours exceed the estimate?
a.25%✓
b.15%
c.30%
d.20%

Overrun = (actual - estimate) / estimate = (150 - 120) / 120 = 30 / 120 = 0.25 = 25%. Job costing compares estimated to actual to reveal a 25% labor overrun.

130. The primary purpose of JOB COSTING is to:
a.Spread the overhead evenly over every job
b.Track real costs against the estimate✓
c.Determine the sales tax owed on the materials
d.Set an hourly price for the next job to bid

Job costing records the labour, material, subcontract and equipment cost actually incurred on each project and sets it beside the estimate, so the contractor learns which jobs made money and bids the next one better. Spreading overhead is what the overhead rate does, and it is an input to the bid rather than the purpose of job costing. Sales tax is computed from purchase invoices. And an hourly price for the next job is guesswork unless the job history behind it has been costed.

131. A concrete slab is 30 ft x 40 ft x 4 inches thick. How many cubic yards of concrete are needed? (1 cubic yard = 27 cubic feet)
a.44.4 cubic yards
b.12.3 cubic yards
c.48 cubic yards
d.14.8 cubic yards✓

Volume in cubic feet = 30 x 40 x (4/12) = 30 x 40 x 0.333 = 400 cubic feet. Convert to cubic yards: 400 / 27 = 14.8 cubic yards.

132. A contractor pays a mason $28/hour. With payroll burden (taxes, insurance, benefits) adding 35%, what is the fully burdened labor rate?
a.$28.00
b.$36.40
c.$37.80✓
d.$42.00

Burden adds 35% to the base wage: $28 x 1.35 = $37.80 per hour. Estimators must use the fully burdened rate, not the base wage, or labor will be underestimated.

133. A painting job covers 2,400 square feet. One gallon covers 350 sq ft. How many gallons (rounded up to full cans) are needed for two coats?
a.12 gallons
b.14 gallons✓
c.7 gallons
d.13 gallons

One coat: 2,400 / 350 = 6.86, round up to 7 gallons. Two coats need 2 x 6.86 = 13.7, round up to 14 gallons. Always round up when buying whole cans.

134. A subcontractor bids $18,000. The general contractor adds a 12% markup on that subcontract. What is the marked-up amount billed to the owner for that scope?
a.$2,160
b.$20,160✓
c.$18,000
d.$19,440 markup only

Markup = $18,000 x 12% = $2,160. Amount billed = $18,000 + $2,160 = $20,160. The general marks up subcontracts to cover coordination, supervision, and risk.

135. A good estimate should include a contingency allowance primarily to:
a.Raise the contractor's profit margin
b.Fund the five percent retention the owner withholds
c.Absorb unforeseen conditions and bid error✓
d.Cover the change orders the owner later requests

A contingency is money set aside inside the estimate to absorb unforeseen site conditions and the normal imprecision of estimating, so a small surprise does not have to become a claim. It is not profit: spending it leaves the margin intact, while treating it as profit means pricing the risk twice. Retention is the owner's money withheld from payments - five percent on public works under Public Contract Code section 7201, and capped at five percent on private contracts entered into on or after 1 January 2026 by Civil Code section 8811 - so it is money not yet received rather than a cost to fund. And owner-requested changes are paid through change orders at agreed prices, which is why they sit outside the contingency.

Public Contract Code §7201; Civil Code §8811
136. Working capital is calculated as:
a.Total assets minus the total liabilities owed
b.Current assets minus current liabilities✓
c.Revenue minus all of the operating expenses
d.Cash on hand minus the accounts payable

Working capital is current assets minus current liabilities, the short-term money actually available to run the business. Total assets minus total liabilities is owner's equity, which measures net worth rather than liquidity. Revenue minus operating expenses is operating profit, a period result rather than a balance. And cash minus payables ignores receivables, inventory and the rest of the current accounts, so it understates what is on hand to work with.

137. A contractor has current assets of $150,000 and current liabilities of $90,000. What is his working capital?
a.$1,667
b.$60,000✓
c.$90,000
d.$240,000

Working capital = current assets - current liabilities = $150,000 - $90,000 = $60,000. This is the cash cushion available for short-term obligations.

138. Poor cash flow on a construction project is MOST often caused by:
a.Paying suppliers early to take their discount
b.Holding retention back from all the subcontractors
c.Billing the owner monthly rather than weekly
d.Paying labour and materials before billings land✓

The structural cause is timing: wages and material invoices fall due weeks before the owner pays a progress billing, and retention delays part of the receipt further still, so cash drains even on a profitable job. Taking an early-payment discount does consume cash, but it buys a return and is a choice rather than the cause. Monthly billing lengthens the gap and makes the problem worse, without being its origin. Withholding retention from subs conserves the contractor's cash rather than draining it.

139. Why can a contractor be profitable on paper yet still run out of cash?
a.Profit is earned over time, bills fall due now✓
b.Accrued revenue is recorded twice in the ledger
c.Depreciation takes cash from the bank each month
d.Retention is booked as a loss when it is withheld

Accrual accounting books revenue when it is earned, but wages, suppliers and taxes must be paid in cash immediately, and money sitting in receivables, retention and work in progress is not available to spend. Double-recording revenue would be an error, not a reason. Depreciation is the opposite case: it reduces book profit without any cash leaving the bank. And retention is recorded as a receivable, an asset still owed, which is precisely why profit can look healthy while the bank balance does not.

140. A contractor offers 2/10, net 30 terms and pays a $10,000 supplier invoice on day 8. How much does he pay?
a.$10,000
b.$9,980
c.$9,800✓
d.$9,000

2/10, net 30 means a 2% discount if paid within 10 days. $10,000 x 2% = $200 discount. Payment = $10,000 - $200 = $9,800. Taking early-payment discounts improves margins.

141. A cash flow projection primarily helps a contractor:
a.Foresee cash shortfalls in time to arrange credit✓
b.Set the overhead rate each bid should carry
c.Value the work in progress for the balance sheet
d.Compute the depreciation on owned equipment

A cash flow projection lays expected receipts against expected disbursements week by week, so a shortfall is visible before it arrives and a line of credit or a change in billing can be arranged in time. Markup comes from the overhead rate and the target margin, not from a cash schedule. Work in progress is valued from job-cost records against the contract amounts. Depreciation follows the asset's cost and schedule and is a tax and book calculation, with no cash timing in it at all.

142. The current ratio is calculated as:
a.Total liabilities over total owner equity
b.Cash on hand over annual sales revenue
c.Current assets over current liabilities✓
d.Net income for the year over the total assets

The current ratio is current assets over current liabilities, a measure of whether short-term obligations can be met; about 2:1 is comfortable and below 1:1 signals trouble. Liabilities over equity is the debt-to-equity ratio, which measures leverage rather than liquidity. Cash over sales is a turnover-style figure that ignores everything else owed within the year. Net income over total assets is return on assets, a profitability measure.

143. A contractor has current assets of $200,000 and current liabilities of $80,000. What is his current ratio?
a.1.6 to 1
b.2.5 to 1✓
c.3.0 to 1
d.0.4 to 1

Current ratio = $200,000 / $80,000 = 2.5, expressed as 2.5:1. This means he has $2.50 of current assets for every $1.00 of current liabilities, a healthy short-term position.

144. Which financial statement reports a company's assets, liabilities, and owner's equity at a single point in time?
a.The job cost report, by project
b.The cash flow report, by week
c.The balance sheet, as of one date✓
d.The income statement, over a period

The balance sheet is a snapshot at a single date showing assets, liabilities and owner's equity, and it obeys Assets = Liabilities + Owner's Equity. The income statement covers a span of time and reports revenue less expenses. The cash flow statement also covers a span, tracking money in and out rather than assets owned. A job cost report is internal and reports one project's costs against its estimate, not the company's financial position.

145. The fundamental accounting equation is:
a.Owner's Equity = Assets + Liabilities
b.Assets = Revenue - Expenses
c.Assets = Liabilities + Owner's Equity✓
d.Revenue = Assets + Liabilities

Assets = Liabilities + Owner's Equity is the foundation of the balance sheet. Everything the company owns is financed either by what it owes (liabilities) or by the owner's investment and retained earnings (equity).

146. A contractor's balance sheet shows total assets of $500,000 and total liabilities of $320,000. What is the owner's equity?
a.$820,000
b.$180,000✓
c.$500,000
d.$320,000

Owner's equity = total assets - total liabilities = $500,000 - $320,000 = $180,000. Equity is the owner's residual claim after all debts.

147. Which statement summarizes revenues and expenses over a PERIOD of time to show profit or loss?
a.The trial balance, as of any chosen date
b.The balance sheet, as of one moment
c.The income statement, for a span✓
d.The equity statement, over each period

The income statement, also called the profit and loss statement, reports revenue minus expenses over a month, quarter or year and ends in net profit or loss. The balance sheet is a point-in-time snapshot of assets, liabilities and equity. A trial balance is a working list of ledger balances used to check that debits equal credits, not a report of profit. The statement of owner's equity does cover a period, but it explains changes in equity rather than showing how the profit was earned.

148. A quick ratio (acid-test) differs from the current ratio because the quick ratio:
a.Includes long-term debt
b.Divides by revenue instead of liabilities
c.Adds back depreciation
d.Excludes inventory from current assets✓

The quick ratio removes inventory (and other less-liquid items) from current assets before dividing by current liabilities, giving a stricter measure of the ability to pay short-term debts with the most liquid assets. Construction inventory can be slow to convert to cash.

149. A contractor's current ratio is 0.8 to 1. This most likely indicates:
a.Liquidity is strong for a firm that is growing
b.The company owes almost no short-term debt
c.Current liabilities exceed current assets✓
d.Profits are high relative to the total assets

A current ratio of 0.8 to 1 means there are only 80 cents of current assets for every dollar of current liabilities, so the near-term bills exceed the near-term resources and lenders and sureties read it as a warning. A ratio below 1.0 is the definition of weak liquidity, not strong. A firm with no short-term debt would show a very high ratio, not a low one. And the current ratio says nothing about profit, which is measured on the income statement.

150. What is the required amount of the contractor's license bond (bond of contractor) in California?
a.$15,000
b.$100,000
c.$25,000✓
d.$12,500

Under Business & Professions Code §7071.6, an active contractor's license requires a bond of $25,000 (an amount increased from $15,000 effective January 1, 2023). The bond protects consumers and employees, not the contractor.

Business & Professions Code §7071.6
反馈