Texas Air Conditioning and Refrigeration Contractor Exam — All Questions

18 questions

Piping

Under IMC §307.2.1, a horizontal condensate drain line must slope toward its discharge at a minimum of:

  • a.1/4 inch per foot
  • b.1/8 inch per foot✓
  • c.1/2 inch per foot
  • d.1/16 inch per foot

The minimum slope is one-eighth unit vertical in 12 units horizontal, about 1%. More slope is fine; less allows water to stand and the line to clog.IMC §307.2.1

Piping

Under IMC §307.2.2, the smallest condensate drain line allowed from an air conditioning coil is:

  • a.3/4 inch nominal✓
  • b.1 inch nominal
  • c.3/8 inch nominal
  • d.1/2 inch nominal

Condensate piping may not be smaller than 3/4 inch internal diameter and may not be reduced in size from the pan connection to the point of disposal. Larger loads use the sizing table in the same section.IMC §307.2.2

Piping

Under 16 TAC §75.100, an air conditioning licensee may connect a condensate drain that ends inside the building if the connection is made:

  • a.On the outlet side of a properly installed trap
  • b.Directly to the building sewer cleanout
  • c.Directly to a vent stack above the roof line
  • d.On the inlet side of a properly installed trap✓

The Texas rule lets a licensee install drain piping that ends outside the building, and make an indoor connection only on the inlet side of a properly installed trap. Work on the sanitary drainage side belongs to the plumbing trade.16 TAC §75.100(b)(2)

Piping

A condensate trap is required on a draw-through air handler because the drain pan is:

  • a.Under positive pressure, which would blow water up the drain
  • b.Below the coil, which would collect dirt from the filter
  • c.Under negative pressure, which would pull air up the drain✓
  • d.Above the blower, which would spray water on the motor

In a draw-through unit the pan is on the suction side of the blower. Without a trap deep enough to offset that negative pressure, air is drawn in through the drain and holds the water in the pan until it overflows.

Piping

ACR copper tubing is identified by its:

  • a.Weight per linear foot
  • b.Wall thickness in mils
  • c.Actual outside diameter✓
  • d.Nominal inside diameter

Refrigeration (ACR) tubing is sized by actual outside diameter, so 7/8-inch ACR tube measures 7/8 inch across. Plumbing tube is named by a nominal size that is about 1/8 inch less than its outside diameter.

Piping

ACR tubing is shipped cleaned, capped and charged with nitrogen in order to:

  • a.Keep the copper soft enough to be flared
  • b.Keep the tube from flattening when it is bent
  • c.Keep moisture and oxidation out of the tube✓
  • d.Show that the tube has passed a leak test

The nitrogen holding charge and caps keep air, moisture and dirt out until installation. Contaminants left in tubing end up in the compressor oil, the drier and the metering device.

Piping

Which filler metal is commonly used to braze copper-to-copper refrigerant joints without flux?

  • a.95/5 tin-antimony solder
  • b.50/50 tin-lead soft solder with flux
  • c.Phosphorus-copper alloy (BCuP)✓
  • d.Aluminum-silicon rod

BCuP alloys are self-fluxing on copper and melt above 1,100°F, giving joints strong enough for refrigerant pressures. Soft solders melt below 840°F and are used on water and condensate lines, and copper to brass or steel needs flux and a silver alloy.

Piping

The difference between brazing and soldering is that brazing filler metals melt:

  • a.Below 840°F
  • b.Above 840°F✓
  • c.Above 2,000°F
  • d.Below 450°F

By definition, soldering uses filler that melts below 840°F and brazing uses filler that melts above 840°F but below the melting point of the base metal.

Piping

A refrigerant flare fitting for ACR tubing is made with a flare angle of:

  • a.30 degrees
  • b.60 degrees
  • c.37 degrees
  • d.45 degrees✓

Refrigeration flares are 45 degrees. The 37-degree flare is used in hydraulic service and will not seal on a refrigeration fitting.

Piping

Under IMC Table 305.4, horizontal copper tubing 1-1/4 inches and smaller must be supported at intervals of no more than:

  • a.12 feet
  • b.6 feet✓
  • c.4 feet
  • d.10 feet

Small copper tubing is supported at least every 6 feet horizontally and 10 feet vertically; 1-1/2 inch and larger tubing may go to 10 feet horizontally. Hangers must not damage the tube or cause galvanic corrosion.IMC Table 305.4

Piping

An undersized suction line causes:

  • a.High suction pressure at the compressor
  • b.Liquid floodback to the compressor
  • c.Excess pressure drop and a loss of capacity✓
  • d.Low vapor velocity and poor oil return to the compressor

A suction line that is too small has a high pressure drop, which lowers pressure at the compressor, raises the compression ratio and cuts capacity. Poor oil return is the problem with an oversized line, where velocity is too low.

Piping

Excessive pressure drop in a liquid line, or a long vertical lift, can cause:

  • a.Liquid slugging at the compressor
  • b.High head pressure at the condenser outlet
  • c.Oil logging in the receiver
  • d.Flash gas ahead of the metering device✓

If liquid pressure falls below saturation for its temperature, some of it flashes to vapor, starving the metering device. Adequate subcooling and proper line sizing prevent it.

Piping

A service valve that is fully backseated:

  • a.Opens the line and the gauge port together
  • b.Closes the line and opens the gauge port
  • c.Closes the line and the gauge port together
  • d.Closes the gauge port and opens the line✓

Backseating (stem all the way out) shuts off the gauge port while leaving the line open to the system. Frontseating closes the line, and a mid position opens everything.

Piping

Under IFGC §408.4, a sediment trap on the gas supply to a furnace is installed:

  • a.At the lowest point of the building's gas piping system only
  • b.Downstream of the appliance gas valve, at the burner manifold inlet
  • c.Upstream of the gas meter, as close to the utility's service regulator as practical
  • d.Downstream of the shutoff valve, as close to the appliance inlet as practical✓

The sediment trap is a tee with a capped nipple at the bottom placed after the appliance shutoff valve and as close to the appliance inlet as practical, to catch debris before it reaches the gas control.IFGC §408.4

Piping

Under IFGC §409.5, the shutoff valve for a gas appliance must be in the same room as the appliance and within:

  • a.12 feet of it
  • b.3 feet of it
  • c.10 feet of it
  • d.6 feet of it✓

The appliance shutoff valve is located in the same room, within 6 feet of the appliance, upstream of the union or connector, and must be accessible.IFGC §409.5

Piping

A listed flexible gas appliance connector may not be:

  • a.Installed in the same room as the appliance
  • b.Used on an appliance with a draft hood
  • c.Run through a wall, floor or ceiling✓
  • d.Connected downstream of the shutoff valve

Connectors must be entirely in the same room as the appliance and may not be concealed in or pass through walls, floors, partitions or ceilings. They are limited in length and connect to the outlet of the shutoff valve.IFGC §411.1

Piping

Under IFGC §406.4.1, new gas piping is pressure tested at not less than 1.5 times the proposed maximum working pressure and never less than:

  • a.10 psig
  • b.1 psig
  • c.30 psig
  • d.3 psig✓

The test pressure is at least one and one-half times the maximum working pressure but not less than 3 psig, held on a gauge suited to that pressure. Appliances and their controls are isolated from the test.IFGC §406.4.1

Piping

What is used as the test medium for a pressure test of fuel gas piping?

  • a.The fuel gas at line pressure
  • b.Air, nitrogen or another inert gas✓
  • c.Water at city main pressure
  • d.Oxygen from a welding cylinder at low pressure

Gas piping is tested with air, nitrogen, carbon dioxide or an inert gas. Oxygen must never be used, since it can react explosively with oil and fuel residue.IFGC §406.4