Browse all questions

The figures these questions turn on, laid out by section on dense colour pages you can print: CSLB Law & Business cheat sheet PDF — $9.99 →

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Every question with its answer and explanation — study by topic or all at once.

Insurance & Liens

198 questions
169. A contractor's umbrella or excess liability policy is designed to:
a.Take the place of the workers' compensation policy entirely
b.Add limits above the underlying policies once exhausted✓
c.Act as the primary policy for every kind of claim
d.Cover only the contractor's own defective work

An umbrella or excess policy sits above scheduled underlying policies — commercial general liability, commercial auto, often employers' liability — and pays only after those limits are exhausted, which is how a contractor reaches catastrophic-claim limits without buying them at the primary layer. (c) inverts that structure. (a) confuses liability limits with workers' compensation, which is statutory, separate, and not something an umbrella replaces. (d) names the risk the CGL's 'your work' exclusion leaves with the contractor, and an umbrella follows the underlying policy's terms rather than curing its exclusions.

—
170. Which of these must a valid recorded mechanics lien contain?
a.The claimant's demand, after just credits and offsets✓
b.A copy of the claimant's workers' compensation certificate
c.The owner's construction loan and account numbers
d.The claimant's profit margin on the contract

Civil Code §8416(a) requires a written statement, signed and verified by the claimant, containing the claimant's demand after deducting all just credits and offsets, the name of the owner or reputed owner if known, a general statement of the kind of work furnished, the name of the person who employed the claimant, a description of the site sufficient for identification, the claimant's address, and a proof of service affidavit; the statutory Notice of Mechanics Lien must be served with it. §8422 forgives erroneous information about the demand, the credits, the work, or the site unless the court finds the claimant intended to defraud, or a party without actual knowledge was misled to its prejudice. The other three answers are records no lien requires and that do nothing to identify the claim.

Civ. Code §8416(a) / §8422
171. A subcontractor who is added as additional insured on NO ONE's policy and carries its own CGL is protected for third-party claims:
a.Not at all, since protection depends on the prime contractor's policy
b.Only for injuries to its own employees, through workers' compensation
c.Only to the extent the general contractor's policy chooses to respond
d.By its own CGL policy, subject to its terms and limits✓

A contractor's own commercial general liability policy insures it against covered third-party bodily injury and property damage arising from its operations, whether or not anyone has named it on another policy. (a) and (c) reverse the direction of additional insured coverage — that status usually runs upward, giving the owner and prime access to the sub's insurer, not the other way round. (b) confuses the two coverages: workers' compensation answers injuries to the contractor's own employees, and third parties are not employees.

172. The construction lender must be served with a preliminary notice by a claimant lacking an owner contract primarily so the claimant can later:
a.Serve a bonded stop payment notice for undisbursed funds✓
b.Record a mechanics lien senior to the lender's deed of trust
c.Compel the lender to release the remaining loan to the owner
d.Claim on the lender's own errors and omissions coverage

Notice to the lender is what keeps the fund-based remedy alive: a bonded stop payment notice under §8532 obliges the lender to withhold loan money it has not yet disbursed. (b) is the closest trap because lien priority is a real and valuable question, but priority turns on when work commenced relative to recording of the deed of trust, not on whom the preliminary notice went to. (c) reverses the point of the notice, which is to stop money rather than release it. (d) invents a claim against the lender's own insurance.

Civil Code §8200 / §8532
173. On a public works project, subcontractors generally CANNOT record a mechanics lien against the public property. Their principal payment security instead is the:
a.Notice of non-responsibility recorded by the public entity's agent
b.Builder's risk policy the public entity carries on the improvement
c.Payment bond, plus a stop payment notice against public funds✓
d.Performance bond posted by the direct contractor at award

Public property cannot be sold to satisfy a private claim, so the legislature substituted two remedies: the direct contractor's payment bond and a stop payment notice served on the public entity against funds still unpaid. (d) is the sharpest distractor, because both bonds are posted on the same job — but the performance bond answers to the public entity for completion, and a sub is not its beneficiary. (a) concerns work ordered by someone other than the owner. (b) is first-party property insurance on the work itself and pays no one for unpaid labour or materials.

Civil Code §9100 et seq. / §9350 et seq.
174. After an owner records a lien release bond of 125%, an unpaid subcontractor who wants to be paid must now pursue:
a.The CSLB, which holds the contractor's licence bond for claimants
b.The surety on the release bond, and the bond's principal✓
c.The construction lender, whose loan funded the improvement work
d.The real property, by foreclosing the lien the bond replaced

Recording a release bond under Civil Code §8424 substitutes the bond for the property, so the claimant's action runs against the surety and the principal rather than against title. (d) is the step the bond was recorded to foreclose, and pursuing it is the error the section exists to prevent. (a) misroutes a claim: the §7071.6 licence bond is claimed against its surety, and the CSLB holds no money. (c) reaches the wrong party — funds in the lender's hands are the target of a bonded stop payment notice, a separate remedy with its own notice conditions.

Civil Code §8424
175. 'Employers' liability' coverage, usually part of a workers' compensation policy, protects the employer against:
a.Statutory benefits owed to an employee injured at work
b.Employee-injury suits outside the exclusive remedy rule✓
c.Bodily injury to the public caused by the employer's work
d.Wage claims brought by employees for unpaid overtime hours

Coverage B of a workers' compensation policy answers employee-injury liability that the no-fault benefit system does not resolve — third-party-over actions, consequential claims by family members, and dual-capacity claims. (a) is Coverage A of the same policy, the statutory benefits themselves, and mistaking the two is the whole point of the item. (c) is commercial general liability, which excludes injury to employees precisely because this coverage handles it. (d) is a wage claim, which is neither an injury nor insured under a workers' compensation policy.

Labor Code §3600 / §3602
176. A direct contractor completed a private remodel on March 1. No notice of completion was ever recorded and the owner never occupied. The contractor's last day to record a mechanics lien is approximately:
a.March 11 (10 days)
b.March 31 (30 days)
c.May 30 (90 days)✓
d.April 30 (60 days)

With no notice of completion or cessation recorded, Civil Code §8412 gives the direct contractor 90 days from completion to record. Counting 90 days from March 1 lands near the end of May.

Civ. Code §8412
177. Requiring a subcontractor to provide a certificate of insurance BEFORE it starts work is a best practice primarily because it:
a.Makes the general contractor a policyholder from the first work day
b.Prevents the insurer from cancelling the policy during the project
c.Extends the general contractor's own coverage over the sub's work
d.Confirms the required coverage is in force before work starts✓

Checking the certificate before the sub mobilizes verifies that the required coverage exists at the moment exposure begins, when it is still possible to keep an uninsured sub off the site. (a) confuses receiving a document with buying a policy. (b) reads the certificate as controlling the insurer, which it does not — cancellation rights live in the policy. (c) reverses the transfer: the purpose is to reach the sub's insurer for the sub's work, not to spend the general contractor's own limits on it.

178. Which best describes the difference between the payment bond and the performance bond on the SAME project?
a.The payment bond guarantees the schedule; the performance bond the budget
b.The payment bond protects subs from nonpayment; the performance bond protects the owner✓
c.The payment bond protects the owner from liens; the performance bond protects the surety
d.The payment bond pays the contractor; the performance bond pays the subcontractors

The two bonds are issued together and answer different failures: the payment bond guarantees that subcontractors and suppliers are paid, and the performance bond guarantees to the owner that the work is completed according to the contract. (a) invents schedule and budget guarantees neither bond gives. (c) is half-right and therefore the strongest distractor — reduced lien exposure is a real benefit to the owner, but it is a consequence of subs being paid, and no bond exists to protect the surety. (d) reverses both beneficiaries.

Civil Code §8600 et seq.

Want these explained in order? CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

179. A mechanics lien recorded on a private project must describe the property with:
a.The contractor's license number and classification
b.The project's estimated fair market value today
c.A description of the site sufficient to identify it✓
d.The owner's mailing address and telephone number

Civil Code §8416(a)(5) requires a description of the site sufficient for identification; a street address usually does, and a legal description removes all doubt. §8422 then forgives an erroneous site description unless the court finds the claimant intended to defraud, or that a party without actual knowledge of the mistake was misled to its prejudice. (a) and (b) appear nowhere in the section. (d) is close enough to be tempting — §8416(a)(2) requires the owner's name if known and (a)(6) requires the CLAIMANT's address — but the owner's mailing address and phone number are not what identifies the property.

Civ. Code §8416(a)(5) / §8422
180. 'Additional insured' status is most valuable to an upstream party (like an owner or GC) because it:
a.Releases the upstream party from carrying its own liability coverage
b.Lowers the downstream party's premium by spreading the same risk
c.Guarantees that the downstream party will complete its scope of work
d.Gives access to the sub's insurer for defense and indemnity✓

An additional insured endorsement lets the owner or general contractor tender a claim arising out of the subcontractor's work to the subcontractor's insurer and obtain a defense and indemnity under that policy, subject to its terms and limits. (a) is the dangerous reading: risk transfer supplements your own coverage and never excuses it. (b) confuses insurance with cost allocation — adding insureds does not reduce the premium. (c) describes a performance bond, which is a surety obligation rather than an insurance one.

181. An architect provided design services for a private work of improvement, authorized by the owner. The architect:
a.Never has lien rights, in any circumstances
b.May give a stop payment notice, but never a lien
c.Must carry builder's risk insurance instead
d.May have lien rights for those services✓

Civil Code §8400(f) lists the design professional among the persons with a mechanics lien right for work provided to a work of improvement, subject to the same preliminary notice condition in §8410 and the recording deadlines in §8412 and §8414. California also gives design professionals a separate remedy in §8300 et seq. for design services furnished before construction starts, which §8302(c) allows only where a building permit or other governmental approval has been obtained using those services. (a) ignores both routes. (b) reverses the remedies, and a design professional's stop payment notice rights are expressly preserved in §8608(b). (c) confuses property insurance with a payment remedy.

Civ. Code §8400(f) / §8302(c)
182. An owner wants to be an additional insured on the contractor's policy. For the owner actually to have that status, the certificate must be accompanied by:
a.A recorded copy of the claimant's mechanics lien
b.A recent statement from the contractor's own bank
c.An additional insured endorsement to the policy✓
d.A thirty-day notice of cancellation clause

Only the insurer can add an insured to a policy, and it does so by endorsement; a certificate is a broker's evidence of coverage and its own wording disclaims amending the policy. (d) is the substitute owners most often settle for — a notice provision tells the owner when coverage is ending, it does not make the owner an insured or give it a right to defense. (a) and (b) belong to other transactions entirely, one in the lien law and the other in a credit file.

—
183. A stop payment notice, unlike a mechanics lien, does NOT need to be:
a.Supported by a valid claim
b.Given by someone who furnished work
c.Served on the correct party
d.Recorded with the county recorder✓

A stop payment notice is served, not recorded; it directs the owner or lender to withhold funds. A mechanics lien, by contrast, is recorded against the property. Both require a valid underlying claim by someone who furnished work and proper service.

Civ. Code §8500
184. A contractor pays day laborers in cash, calls them independent contractors, and carries no workers' compensation. A laborer is injured. The contractor most likely:
a.Owes the CSLB an administrative fine and nothing more
b.Has no exposure at all, the laborers being independent
c.Is liable as an uninsured employer for the injury✓
d.Is covered by the general liability policy instead

Labor Code §2775(b)(1) treats a worker as an employee unless the hiring entity proves all three parts of the ABC test, and §2781 sets the narrower conditions for construction subcontractors; the label on the paperwork settles nothing. An employer that owed coverage and had none faces the civil action §3706 allows, in which §3708 presumes the injury was caused by the employer's negligence and removes the usual defenses, plus §3700.5 misdemeanor exposure and suspension of the license under B&P §7125.2. (a) understates the exposure by orders of magnitude. (b) is the label-as-conclusion error the ABC test forecloses. (d) misreads the commercial general liability policy, which excludes bodily injury to the insured's own employees precisely because workers' compensation answers it.

Lab. Code §2775(b)(1) / §2781 / §3706 / §3708
185. A supplier first delivered materials on Day 1 but served its preliminary notice on Day 40. For which materials may it claim?
a.Only for the materials delivered after the 60th day of work
b.For nothing at all, the notice being fatally late
c.For every delivery, back to the very first one
d.For deliveries from about Day 20 forward, but not before✓

Civil Code §8204(a) provides that a claimant who did not give preliminary notice is not precluded from giving one later, but is then entitled to claim only for work performed within the 20 days prior to service of the notice, and at any time thereafter. Service on Day 40 therefore protects deliveries from roughly Day 20 forward, and the deliveries from Day 1 to Day 19 fall outside the window. (b) treats a late notice as fatal, which the subdivision expressly says it is not. (c) ignores the look-back altogether. (a) counts 20 days forward from service instead of backward, which protects nothing the statute protects.

Civ. Code §8204(a)
186. Which of the following is generally the LAST resort remedy because it requires foreclosing on real property?
a.Certificate of insurance
b.Mechanics lien✓
c.Stop payment notice
d.Payment bond claim

A mechanics lien ultimately requires a foreclosure action against the owner's real property to collect, making it more cumbersome than a stop payment notice (reaching funds) or a payment bond claim (reaching a surety). Claimants often pursue funds or bonds first.

187. On a project where a notice of completion is recorded, missing the 30-day lien deadline (for a non-direct claimant) generally means:
a.The claimant may still record within 60 days, as the direct contractor may
b.The claimant loses the mechanics lien, but other remedies may survive✓
c.The claimant may record within 90 days from actual completion instead
d.The claimant has 90 days from recording to file suit on the lien

Civil Code §8414 gives a claimant other than the direct contractor 30 days after a recorded notice of completion; miss it and the lien remedy is gone, though a payment bond claim, a timely stop payment notice, or a plain breach-of-contract action may remain. (a) borrows the direct contractor's 60-day period under §8412, which is not available to lower-tier claimants. (c) is the no-notice rule the recording displaced. (d) states the §8460 deadline for suing on a lien already recorded, which never revives a lien that was recorded too late.

Civil Code §8414 / §8460
188. A general contractor's CGL policy typically will NOT respond to which claim?
a.The contractor's crane damaging the neighboring building
b.A visitor tripping on debris and breaking an arm
c.A pedestrian struck by material falling from the frame
d.The contractor's own employee injured while framing✓

A commercial general liability policy excludes bodily injury to an employee arising out of employment, because that injury belongs to workers' compensation, with Coverage B employers' liability picking up the suits the no-fault system does not resolve. (a), (b) and (c) are exactly what the CGL is bought for: third-party bodily injury and property damage arising out of the contractor's operations. The line is who was hurt, not how badly or where — an employee framing the same wall as the injured visitor produces a workers' compensation claim, not a CGL claim.

—
189. A claim on a private-project payment bond generally requires the claimant to have:
a.Posted a bond of 125 percent of the claim before making it
b.Given the preliminary notice lien rights require, unless excused✓
c.Recorded a mechanics lien against the property before claiming
d.Obtained a judgment against the direct contractor before claiming

Under Civil Code §8600 et seq. the right to recover on a private-work payment bond tracks the notice conditions for a mechanics lien, so a claimant who had to give a preliminary notice must have given it — laborers and others excused from notice are excused here too. (a) imports the §8532 bond that accompanies a stop payment notice to a lender. (c) treats the remedies as sequential when they are alternative; a claimant may go against the bond without ever recording. (d) would make the bond useless, since its value is being payable without first litigating to judgment.

Civil Code §8600 et seq.
190. The most accurate reason insurance and surety bonds are BOTH used on construction projects is that they:
a.Are both two-party transfers, so carrying both doubles available limits
b.Both let the provider absorb the loss without seeking reimbursement
c.Both protect the contractor against claims made by the project owner
d.Address different risks: insurance covers loss, bonds guarantee duties✓

Insurance transfers the insured's own fortuitous losses to an insurer that does not expect repayment; a bond is a three-party guarantee running to an obligee, and the surety expects the principal to reimburse what it pays. Projects carry both because the risks do not overlap. (a) and (b) each describe insurance and then attach the label to both instruments. (c) mistakes who a bond protects — the owner is typically the obligee the bond runs to, so the bond protects the owner from the contractor, not the reverse.

191. A lien claimant who has been paid in full but refuses to release a recorded mechanics lien may be liable to the owner for:
a.Nothing, since a satisfied lien expires on its own schedule
b.Three times the value of the project, as a penalty
c.The owner's costs and attorney's fees to remove the lien✓
d.The contractor's lost profit on the delayed property sale

A claimant that has been paid should execute and record a release, and an unreleased lien clouds the owner's title until it does. The owner's statutory remedy is the petition in Civil Code §8480: once the claimant has let the 90 days in §8460 pass without commencing an action to enforce the lien, the owner may petition for an order releasing the property, the claimant carries the burden of proving the lien's validity under §8488(a), and §8488(c) awards the prevailing party reasonable attorney's fees. §8494 then strips an expired lien of any effect as notice. (a) ignores the practical problem the statute addresses, since the cloud on title bites long before anything expires. (b) invents a treble-damages penalty this remedy does not carry. (d) names the wrong party's loss: the harm runs to the owner whose title is clouded, not to the contractor.

Civil Code §8480 / §8488(c) / §8494
192. The $25,000 figure most commonly associated with California contractor licensing is:
a.The largest mechanics lien the statute allows
b.The project size that requires a payment bond
c.The contractor's license bond amount✓
d.The builder's risk limit the CSLB sets

$25,000 is the contractor's bond every active licensee must keep on file under B&P §7071.6 — and the same figure is the minimum disciplinary bond under §7071.8 and the amount of the qualifying individual's bond under §7071.9. (b) is the real neighbor and the reason this item is worth asking: Civil Code §9550(a) requires a payment bond on a public works contract involving an expenditure in excess of $25,000, the identical number doing an unrelated job. (a) invents a statutory cap on liens; a lien is in the amount of the claimant's demand. (d) invents a CSLB insurance requirement — the only insurance the license law compels is workers' compensation under §7125, plus the limited liability company's liability policy under §7071.19.

B&P Code §7071.6 / Civ. Code §9550(a)
193. SB 1455 (Stats. 2024, ch. 485) moved the date on which B&P §7125 requires every licensee, with or without employees, to carry workers' compensation. From what date does that requirement apply?
a.January 1, 2026
b.January 1, 2028✓
c.January 1, 2027
d.July 1, 2026

SB 216 (Stats. 2022, ch. 978) wrote a version of §7125 that requires every licensee to carry workers' compensation or self-insurance whatever its classification, leaving only a §7029 joint venture with no employees exempt, and set it to start on January 1, 2026. SB 1455 (Stats. 2024, ch. 485) rewrote that start date: the new section "shall become operative on January 1, 2028" (b), and the interim §7125 — a no-employee exemption available to everyone except C-8, C-20, C-22, C-39 and D-49 holders — stays in effect until then. (a) is the original SB 216 date, which is why so much study material still states the all-licensee rule as current. (c) is a real date in the same bill, but for something else: by January 1, 2027 §7125.7 requires the board to establish a process to verify that licensees claiming the no-employee exemption are eligible. (d) is not a date either bill uses.

Bus. & Prof. Code §7125 (Stats. 2024, ch. 485, SEC. 12–13); §7125.7
194. Until January 1, 2028, which of these licensees, working alone with no employees, may file the exemption from workers' compensation instead of carrying a policy?
a.A C-39 roofing contractor
b.A C-8 concrete contractor
c.A C-33 painting contractor✓
d.A D-49 tree service contractor

Until January 1, 2028, B&P §7125(b), as amended by SB 1455 (Stats. 2024, ch. 485), exempts an applicant or licensee that has no employees and files the Registrar's exemption statement — but only if it does not hold a C-8 (concrete), C-20 (warm-air heating, ventilating and air-conditioning), C-22 (asbestos abatement), C-39 (roofing) or D-49 (tree service) license. A C-33 painter is not on that list, so (c) may file. (a), (b) and (d) are on it: those holders must carry workers' compensation or a certification of self-insurance whether or not they employ anyone, and CSLB will not accept an exemption from them. From January 1, 2028 the list stops mattering, because the SB 216 version of §7125 requires every licensee to carry coverage except a §7029 joint venture with no employees — the painter included.

Bus. & Prof. Code §7125(b) (as amended by SB 1455, Stats. 2024, ch. 485)
195. A stop order is served on a contractor found employing six workers with no workers' compensation coverage. One of the six is later found to have a compensable injury from the uninsured period. Which assessments does Labor Code §3722 authorize?
a.$1,500 per employee with the stop order, and $10,000 per employee once the claim is compensable✓
b.$1,500 per employee with the stop order, and nothing further once the claim is found compensable
c.$10,000 per employee with the stop order, and $1,500 per employee for the compensable claim
d.One flat $100,000 assessment, which is the only figure §3722 authorizes in either situation

Section 3722 assesses twice, on two different triggers. Subdivision (a) is issued together with the stop order, before anyone is hurt, at $1,500 per employee employed when the order is issued and served. Subdivision (d)(2) then adds $10,000 per employee employed on the date of injury once a claim is found compensable. The $100,000 in subdivision (f) is a CEILING on the total of these assessments, not a penalty in its own right, and the criminal exposure under §3700.5 sits on top of all of it.

Labor Code §3722(a), (d)(2), (f)
196. A carpenter is hurt when a scaffold plank he himself installed carelessly gives way. His employer carries workers' compensation. He now wants to sue that employer in court for negligent site maintenance. What is the position?
a.Benefits are denied because he caused his own injury, so a negligence suit is his only route
b.Benefits are denied and no suit lies either, since compensation is the exclusive remedy
c.Benefits are paid, and he may also sue the employer, because the site itself was unsafe
d.Benefits are paid despite his own carelessness, and the claim is his only remedy in court✓

These are the two halves of one bargain. Section 3600(a) makes the employer liable for compensation WITHOUT REGARD TO NEGLIGENCE, so an injured worker who was partly or wholly careless still collects. Section 3602(a) is the price of that: the compensation claim is the sole and exclusive remedy against the employer, so the negligence suit does not lie. The narrow exceptions are elsewhere — a willful physical assault by the employer, fraudulent concealment, a defective product the employer made, or an employer that never secured coverage at all.

Labor Code §3600(a); §3602(a)
197. A laborer cuts his hand on Monday and needs stitches. He files the DWC-1 claim form on Wednesday. The carrier has neither accepted nor rejected the claim. What must the employer do, and how far does its liability run?
a.Wait for the carrier's decision, because no treatment need be authorized while a claim is pending
b.Authorize treatment by Thursday, with liability limited to $10,000 until the claim is decided✓
c.Authorize treatment by Thursday, and carry the full cost of whatever medical care is ordered
d.Authorize treatment within 90 days, which is also the deadline for rejecting the claim outright

Two clocks run from two different events. The employer had one working day from notice of the injury to hand the worker a claim form. Once the worker FILES that form, §5402(c) gives the employer one working day to authorize all treatment consistent with the applicable guidelines, so a Wednesday filing means Thursday. Liability for that treatment is limited to $10,000 until the claim is accepted or rejected — the money is spent before anyone decides the claim, which is the point of it. Ninety days is a different deadline: it is when an unrejected claim becomes presumed compensable.

Labor Code §5401(a); §5402(b), (c)
198. An owner hired a registered professional engineer under a written contract to design a warehouse and obtained the building permit with those drawings, then shelved the project and never paid the fee. The owner still owns the site. May the engineer record a lien?
a.No, because no work of improvement ever commenced, so nothing exists for a lien to attach to
b.Yes, an ordinary mechanics' lien, because the drawings are services furnished to the improvement
c.Yes, a design professional's lien, because a building permit was obtained and the owner still owns the site✓
d.Yes, but only if the engineer had served a preliminary notice within 20 days of starting the drawings

Civil Code §8302 creates a lien on the site for a design professional NOTWITHSTANDING the absence of commencement of the planned work of improvement — that is exactly the situation the chapter exists for. The conditions are all present here: a person described in §8014 (a registered professional engineer), services under a written contract with the landowner, a building permit or other governmental approval obtained in furtherance of the work, and the contracting landowner still owning the site when the claim of lien is recorded. Had no permit been obtained, no lien could be created at all.

Civil Code §8302; §8300; §8014

Contracts & Execution

339 questions
1. Under California law, a home improvement contract is required for residential work when the total contract price (labor AND materials) is at least:
a.$200
b.$500✓
c.$1,000
d.$2,500

California requires a written home improvement contract for any work on a residential property totaling $500 or more, including both labor and materials (B&P §7159). Note: this $500 written-contract threshold is a DIFFERENT number from the $1,000 unlicensed minor-work threshold under §7048 — SB 517 amended §7159 for 2026 (subcontractor-disclosure rules), but left this $500 figure in place, so do not confuse the two.

Bus. & Prof. Code §7159
2. A homeowner can cancel a home improvement contract that was solicited at their home within:
a.24 hours
b.3 business days✓
c.5 business days
d.7 calendar days

The three-day right of rescission applies to contracts solicited and signed at the consumer's home. The homeowner has until midnight of the third business day to cancel without penalty.

Bus. & Prof. Code §7159(b)
3. Which of the following MUST be included in a California home improvement contract?
a.The architect's stamp on the plans and specifications
b.A list of every subcontractor and its license number
c.The contractor's name, business address and license number✓
d.The contractor's workers' compensation policy number

B&P §7159(d)(1) requires the home improvement contract to carry the contractor's name, business address and license number; the rest of the (d) list adds the contract price, the description of the project and significant materials, the schedule of progress payments and the approximate start and completion dates. The statute does not ask for the license expiration date. Nor does it ask for an architect's stamp, which belongs to plan check; a roster of subcontractors, which stays in the contractor's own files; or a workers' compensation policy number, which the insurer's certificate carries.

B&P Code §7159(d)(1)
4. A contractor and homeowner agree to change the scope of work during a project. This agreement must be:
a.Verbal, then confirmed on the next invoice sent to the owner
b.Written and signed by both parties before the changed work starts✓
c.Approved by the local building department before it takes effect
d.Filed with CSLB within 10 days of the price increase it causes

B&P §7159(d) requires a home improvement contract and any change to it to be in writing and signed by the parties before the work covered by the change begins, and §7159(c)(5) says a change-order form becomes part of the contract only on those terms. An invoice sent afterwards documents a bill, not an agreement made in advance. The building department reviews code compliance and issues permits; it has no role in making a price change enforceable between owner and contractor. And no section requires change orders to be filed with CSLB, on a 10-day clock or any other.

B&P Code §7159(c)(5), (d)
5. A contractor may demand final payment from the homeowner:
a.Upon substantial completion of the project✓
b.When 50% of the work is complete
c.After all materials are delivered to the site
d.At the start of the project

A contractor may not demand or accept final payment until the project is substantially complete. Demanding payment before this point is a violation of California Contractors' Law.

Bus. & Prof. Code §7159.5(a)(5)
6. Which statement about arbitration clauses in construction contracts is TRUE?
a.They are illegal in California
b.They can be included but must be clear and conspicuous✓
c.They are required in all home improvement contracts
d.They automatically waive the right to a jury trial in all cases

Arbitration clauses are permitted in construction contracts but must be clearly disclosed, written in at least 10-point boldface type in home improvement contracts, and separately initialed by the homeowner.

Bus. & Prof. Code §7191
7. A contractor abandons a job without justification after receiving a substantial deposit. The contractor may face:
a.A civil fine from CSLB, but no risk to the license itself
b.An order to refund the deposit, with no discipline to follow
c.License suspension or revocation and criminal charges✓
d.A warning letter and a note placed in the license file

Abandonment of a project without legal excuse is by itself a cause for disciplinary action under B&P §7107, so suspension or revocation is on the table; and a deposit taken for the work and spent elsewhere can be prosecuted under Penal Code §484b as diversion of construction funds, a misdemeanor at $2,350 or less and punishable more heavily above that. A fine that leaves the license untouched, a bare refund order, and a warning letter each stop short of the license discipline §7107 authorizes.

B&P Code §7107; Penal Code §484b
8. Who is primarily responsible for obtaining building permits on a construction project?
a.The property owner
b.The architect
c.The local building department
d.The prime contractor✓

While permits can technically be pulled by the owner, it is the contractor's professional responsibility to ensure all required permits are obtained before work begins. Working without required permits is a license violation.

Bus. & Prof. Code §7090
9. A contract clause that shifts responsibility for delays outside the contractor's control to the owner is called:
a.A force majeure clause✓
b.A liquidated damages clause
c.An indemnification clause
d.A no-damage-for-delay clause

A force majeure clause excuses a party from performance when extraordinary events beyond their control (weather, acts of God, pandemics) prevent timely completion. It protects the contractor from delay damages.

10. An owner includes a liquidated damages clause of $500 per day for late completion. This clause is enforceable if:
a.It was a reasonable estimate of probable damages when signed✓
b.The daily amount is high enough to deter late completion
c.The owner proves the exact actual delay damages at trial
d.The contractor initialed the clause and waived its arbitration

Civil Code §1671(b) makes a liquidated damages provision valid unless the party attacking it establishes that the amount was unreasonable under the circumstances existing at the time the contract was made, so reasonableness is judged as of signing. An amount set high to deter or punish is the classic penalty that fails that test. Requiring proof of the exact actual damages defeats the purpose of liquidating them in advance. And initialing the clause or waiving arbitration has nothing to do with §1671.

Civil Code §1671(b)
11. A contractor must provide an owner with a "Notice to Owner" (preliminary notice) primarily to:
a.Notify the owner that a stop payment notice has been recorded
b.Meet a condition of the permit issued for the work site
c.Preserve the right to record a mechanics' lien if not paid✓
d.Extend the 90-day deadline for recording the lien

Civil Code §8200 makes the preliminary notice a condition of lien rights: give it and the claimant may record a mechanics' lien if the bill goes unpaid; skip it and the lien is lost no matter what the work was worth. It is not a demand for payment and not a stop payment notice - that is the separate remedy served to freeze undisbursed construction funds. The building permit is issued by the building department for code compliance and has nothing to do with it. And the notice buys no time: the 90-day window to record a lien after completion runs on its own schedule under §8412.

Civil Code §8200; §8412
12. Under a "time and materials" (T&M) contract, the owner pays:
a.A fixed price agreed before any work starts on site
b.Only material costs; labour is the contractor's own risk
c.A set hourly rate with no reimbursement of materials
d.Actual labour and material costs plus an agreed markup✓

A time-and-materials contract pays the contractor for the labour hours actually worked at an agreed rate, plus the actual cost of materials, plus an agreed markup or fee for overhead and profit; the total is not fixed in advance. A price fixed before work starts is a lump sum or stipulated sum contract, the opposite arrangement. Paying only for materials describes a supply-only purchase, not a construction contract. And an hourly rate with no material reimbursement is a labour-only or unit-rate deal, which leaves the contractor absorbing every material cost.

13. Which contract type places the MOST financial risk on the contractor?
a.Cost-plus-a-fixed-fee contract
b.Fixed-price lump sum contract✓
c.Time and materials contract
d.Unit price per item contract

Under a fixed-price lump sum contract the contractor promises a finished result for one price, so every overrun - labor productivity, material escalation, rework - lands on the contractor. Cost-plus-a-fixed-fee reverses that: the owner reimburses actual costs and the fee is fixed, so the owner carries the overrun. Time and materials bills hours and materials as they are incurred, which again leaves the cost risk with whoever pays the invoices. A unit price contract fixes only the rate per unit installed; the quantity risk stays with the owner, and the contractor is exposed only on its own productivity per unit.

-
14. A subcontractor fails to complete their scope of work on a project. The prime contractor's primary recourse is:
a.Report the sub to CSLB and wait for the Registrar to order completion
b.Complete the scope with another sub and bill the excess to that sub✓
c.Stop all work and treat the prime contract as terminated by the owner
d.Ask the owner for a change order covering the replacement sub's higher price

When a subcontractor defaults, the prime's contract remedy is to terminate that subcontract, have the scope finished by others, and recover the difference from the defaulting sub — or from its performance bond, if one was furnished. (a) CSLB discipline can suspend or revoke the sub's license, but the Registrar has no power to order the work completed or to make the prime whole; that is a court's or an arbitrator's job. (d) A change order moves the cost onto the owner, who neither caused the default nor agreed to pay twice for the same scope. (c) Walking off is worse than useless: abandoning a project without legal excuse is itself cause for discipline under B&P §7107, so the prime would trade a collection claim for a license problem.

Bus. & Prof. Code §7107 (abandonment); §7108.5 (payments to subcontractors)
15. California's "prompt payment" law requires owners to pay general contractors within how many days of a proper invoice?
a.7 days
b.30 days✓
c.45 days
d.60 days

On private works, owners must pay general contractors within 30 days of a proper undisputed invoice. On public works the period is 30 days from invoice or 39 days from billing, depending on the agency.

Civil Code §8800
16. On a private project, a direct (general) contractor receives a progress payment from the owner. Within how many days must it pay each subcontractor that subcontractor's share?
a.3 days
b.7 days✓
c.10 days
d.30 days

B&P §7108.5 gives the direct contractor 7 days from receipt of a progress payment to pass each subcontractor its share (b), and §7108.5(b) charges a 2%-per-month penalty plus attorney's fees on amounts wrongfully withheld. (c) 10 days is the separate deadline in Civil Code §8814 for releasing withheld RETENTION to a subcontractor once the owner releases it — a different payment under a different statute, which is why the stem names the progress payment. (a) 3 days and (d) 30 days appear in neither section; 30 days is the kind of term a private contract might try to impose, but §7108.5 cannot be bargained down to it.

Bus. & Prof. Code §7108.5
17. A contractor is hired to build a room addition. After completion, the homeowner claims defects. The contractor's written warranty on new residential construction must be at least:
a.90 days
b.1 year✓
c.2 years
d.The contractor sets the term freely

California's Right to Repair Act (SB 800) establishes statutory warranties for new residential construction: 1 year for most components, 4 years for plumbing/electrical/mechanical, 10 years for structural defects.

Civil Code §896
18. On a $40,000 home improvement contract, what is the maximum down payment a contractor may legally demand or accept before work begins?
a.$4,000 (10% of the contract)
b.$2,000 (5% of the contract)
c.$1,000✓
d.$10,000 (25% of the contract)

California limits the down payment on a home improvement contract to $1,000 or 10% of the contract price, whichever is LESS. Here 10% would be $4,000, so the smaller cap of $1,000 controls.

Bus. & Prof. Code §7159.5
19. On a $6,000 home improvement contract, what is the maximum allowable down payment?
a.$600✓
b.$1,000
c.$1,500
d.$3,000

The down payment may not exceed $1,000 or 10% of the contract price, whichever is less. Ten percent of $6,000 is $600, which is less than $1,000, so $600 is the legal maximum.

Bus. & Prof. Code §7159.5
20. Which of the following is NOT a required element of a California home improvement contract?
a.An approximate start date and completion date
b.A schedule of payments tied to work performed
c.The homeowner's annual household income✓
d.A description of the work to be performed

Home improvement contracts must state the work description, payment schedule, and start/completion dates, among other items. A homeowner's income is private financial information and is never a required contract term.

Bus. & Prof. Code §7159
Report