Browse all questions

The figures these questions turn on, laid out by section on dense colour pages you can print: CSLB Law & Business cheat sheet PDF — $9.99 →

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Every question with its answer and explanation — study by topic or all at once.

Contracts & Execution

339 questions
71. A contractor's bid totals $90,000, of which $54,000 is direct cost. What percentage of the bid is gross profit and overhead combined?
a.40%✓
b.60%
c.20%
d.166%

The amount above direct cost is $90,000 - $54,000 = $36,000. As a percentage of the bid: $36,000 / $90,000 = 40%, which covers both overhead and profit.

72. A contractor estimates a job will take 320 labor hours at a fully burdened rate of $55 per hour. What is the estimated labor cost?
a.$5,818
b.$17,600✓
c.$1,760
d.$176,000

Estimated labor cost equals hours times the burdened hourly rate: 320 x $55 = $17,600. The burdened rate already includes payroll taxes, insurance, and benefits.

73. Three contractors submit sealed bids of $182,000, $176,500, and $189,300 for the same defined scope. The lowest responsible, responsive bid is:
a.$176,500✓
b.$189,300
c.$182,000
d.The average of the three bids

Competitive bidding awards the contract to the lowest responsible and responsive bidder. Among $182,000, $176,500, and $189,300, the lowest is $176,500.

74. A general contractor uses a critical path method (CPM) schedule mainly to:
a.Allocate monthly overhead across the job's cost codes
b.Compare actual labor hours against the bid estimates
c.Identify the sequence that sets the completion date✓
d.Set the retention percentage withheld each month

The critical path is the longest chain of dependent activities in the schedule, so its length is the shortest time the project can take and it fixes the completion date; finding that chain is what a CPM schedule is built for. Spreading overhead across cost codes and comparing actual hours to the bid are job-costing exercises done from the accounting records, not from the schedule network. The retention percentage comes from the contract, not from any schedule calculation.

75. On a fixed-price contract, the contractor's estimate was $100,000 but actual costs reached $112,000. The owner still pays only the agreed price. The contractor's profit or loss is:
a.A $12,000 profit
b.A $12,000 loss✓
c.Break-even, no profit or loss
d.Determined later by the owner

In a fixed-price contract the price is locked. With costs of $112,000 and revenue of $100,000, the contractor absorbs a $12,000 loss; cost-risk falls entirely on the contractor.

76. If a contractor performs home improvement work without a written contract or with a noncompliant contract, the most likely consequence is:
a.License discipline by the CSLB and difficulty enforcing payment✓
b.The contract automatically becomes a public works contract
c.The homeowner must pay double the contract price as a penalty
d.The CSLB issues the contractor a higher licence classification

A home improvement contract that is missing or noncompliant is grounds for CSLB discipline under B&P §7159, and it leaves the contractor arguing an unenforceable or unprovable bargain when it tries to collect. Nothing converts a private remodel into a public works contract - that turns on public funds and the prevailing wage statutes, not on paperwork. No statute doubles the price for the owner; the doubling idea comes from §7031(a), which runs the other way by barring an unlicensed contractor from collecting at all. And the CSLB issues classifications on examination and experience, never as a consequence of a defective contract.

B&P Code §7159; §7031(a)
77. An owner asks a contractor to add an unforeseen scope of work mid-project. To be paid for the extra work, the contractor should FIRST:
a.Get a written change order signed by both parties before starting it✓
b.Perform the extra work and add its cost to the final invoice
c.Get the owner's verbal go-ahead on site and note it in the daily log
d.Bill the extra work as a time-and-materials allowance at closeout

On a home improvement contract, B&P §7159(c)(5) makes a change order part of the contract only if it is in writing and signed by the parties before any work covered by it begins, and §7159(d) says the same of any change to the contract. Doing the work first and adding it to the final invoice leaves the contractor arguing over an unauthorized extra. A verbal go-ahead with a log entry is not a signed writing, however contemporaneous the note. Calling the extra an allowance at closeout relabels the billing without supplying the signature the statute requires.

B&P Code §7159(c)(5), (d)
78. California prompt payment laws are designed primarily to:
a.Set the prevailing wage rates paid on public works
b.Decide which bidder wins a public works contract
c.Move payment down the chain on fixed deadlines✓
d.Cap the retention an owner may withhold

Prompt payment statutes do one thing: they put deadlines on money moving down the contracting chain, with penalties for missing them. Civil Code §8800 gives a private owner 30 days after a demand for payment under the contract to pay the direct contractor, at a 2% per month penalty on anything wrongfully withheld; B&P §7108.5 gives a direct contractor 7 days from a progress payment to pay each subcontractor; Civil Code §8814 gives 10 days for passing retention through. Prevailing wage rates are set by the DIR, the award of a bid turns on the bidding statutes, and the 5% retention cap is Civil Code §8811 - none of those are prompt-payment rules.

Civil Code §8800; B&P Code §7108.5; Civil Code §8814; Civil Code §8811
79. A contractor wishes to require a larger down payment than the law allows because a custom-ordered material must be paid for up front. The proper way to handle this is to:
a.Collect 50% down and label the deposit 'custom materials'
b.Have the homeowner waive the downpayment limit in writing
c.Post an approved bond or joint control, which lifts the cap✓
d.Collect the whole contract price before ordering anything

B&P §7159.5(a)(3) caps the downpayment at $1,000 or 10 percent of the contract amount, whichever is less, and §7159.5(a)(8) exempts from that cap a contractor who provides a performance and payment bond or joint control approved by the registrar - that, not a bigger deposit, is how a special-order purchase gets funded, with any finance charge set out separately from the contract amount. The cap is a consumer protection the homeowner cannot waive. Relabelling an oversized deposit does not make it lawful. And §7159.5(a)(5) bars requesting or accepting payment beyond the value of work performed or material delivered.

B&P Code §7159.5(a)(3), (a)(5), (a)(8)
80. A contractor's overhead is best described as:
a.The direct labor and material charged to one specific job
b.Indirect business costs not charged to one specific job✓
c.The markup added to direct costs to produce the profit
d.The retention the owner withholds until completion

Overhead is the indirect cost of running the business - office rent, insurance, licenses, administrative salaries - that no single job carries and that has to be recovered through markup on direct costs. Labor and material charged to one job are direct job costs. The markup is how overhead is recovered, not the overhead itself. And retention is money the owner holds back from a payment, not a cost of doing business.

Overhead vs direct cost (estimating practice)

Want these explained in order? CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

81. On a home improvement contract, the start date and completion date provisions exist primarily to:
a.Let the contractor set the final price once work is under way
b.Start the three-day cancellation period running at the start date
c.Fix the date any retention becomes payable to the contractor
d.Give the homeowner an enforceable expectation of the project schedule✓

B&P §7159(d)(10) requires an 'Approximate Start Date' heading with a statement of what counts as substantial commencement of work, and §7159(d)(11) requires an 'Approximate Completion Date'. Together they give the homeowner a timeline she can hold the contractor to, and they are how a delay becomes measurable as abandonment. The price is set by the contract's price and payment-schedule terms, not by the dates. The buyer's three business days to cancel run from receipt of a signed and dated copy of the contract, not from the start date. And retention is a payment term; the date provisions do not control when it comes due.

B&P Code §7159(d)(10), (d)(11)
82. Which item is generally considered a direct (job) cost rather than overhead?
a.The contractor's monthly office telephone bill
b.The annual general liability insurance premium
c.The company bookkeeper's monthly salary
d.Lumber installed on a specific framing job✓

A direct (job) cost is traceable to one job — the lumber that goes into that framing job, the labour on that site, the equipment rented for it. The office telephone, the annual liability premium and the bookkeeper's salary are all incurred to run the company rather than to build any one job, so they are indirect overhead recovered through a markup spread across all jobs. The test is not whether the cost is large or recurring; it is whether you can point to the job that consumed it.

Job-cost accounting (no statute)
83. A contractor marks up direct costs by 35%. If the markup amount on a job is $14,000, what were the direct costs?
a.$40,000✓
b.$49,000
c.$4,900
d.$54,000

Markup amount equals direct cost times the markup rate: $14,000 = cost x 0.35, so cost = $14,000 / 0.35 = $40,000. The selling price would be $54,000.

84. On a unit-price paving contract at $3.20 per square foot, the field measures 9,500 square feet actually paved. What is the contractor entitled to be paid?
a.$28,500
b.$30,400✓
c.$304,000
d.$3,040

A unit-price contract pays the unit price times the measured quantity: $3.20 x 9,500 sq ft = $30,400. $28,500 is the same quantity at $3.00, a rounded-down unit price. $304,000 comes from reading the rate as $32.00 per square foot, and $3,040 from $0.32 — both are decimal-point slips of one place in opposite directions.

Unit-price contract arithmetic (no statute)
85. A contractor finishes substantially all work on a private project and submits a proper final invoice for $30,000 (the retention). The owner refuses to pay although there is no genuine dispute. The contractor's BEST first step is to:
a.Re-enter the property and remove the materials already installed
b.File a CSLB complaint and let the Board collect the retention for it
c.Serve a stop payment notice on the owner for the unpaid retention
d.Demand the retention in writing, then pursue the 2% penalty and a lien✓

With no good faith dispute, the owner must release retention within 45 days after completion (Civil Code §8812) and owes 2 percent per month on what is wrongfully withheld, plus attorney's fees (§8818); a written demand documents that claim while the 90-day lien deadline of §8412 runs. Re-entering to strip out installed work is unlawful self-help. The CSLB disciplines licensees but does not collect money owed to a contractor. And a stop payment notice under §8520 belongs to claimants other than the direct contractor, so the prime cannot use one against the owner.

Civil Code §8812; §8818; §8412; §8520
86. An AIA-style "Application and Certificate for Payment" (commonly G702/G703) is used to:
a.Certify substantial completion and release all retention held
b.List the subcontractors and suppliers in a bid package
c.Request a progress payment against the schedule of values✓
d.Record a mechanics' lien claim with the county recorder

The G702 application and certificate for payment, with its G703 continuation sheet, itemizes the schedule of values and the percentage of each line item completed — that is how a progress payment is requested and certified. Substantial completion is certified on a separate form and does not by itself release retention. Subcontractor and supplier listings belong to the bid documents, not the payment application. And a mechanics' lien is a statutory claim recorded with the county, not an AIA payment form.

AIA G702/G703 (industry practice); Civil Code §8412 (lien recording)
87. A contractor budgets a job at $250,000 total cost and is 60% complete. To stay on budget, total spending to date should be approximately:
a.$60,000
b.$150,000✓
c.$250,000
d.$100,000

If progress and spending track together, spending at 60% complete should be about 60% of the $250,000 budget: 0.60 x $250,000 = $150,000. Spending much above this signals a possible overrun.

88. A homeowner signs a home improvement contract at the contractor's place of business after visiting the showroom. Which statement is most accurate?
a.The three-day home solicitation cancellation notice is required
b.The required home improvement contract terms still apply✓
c.No written contract is needed for a sale at a business office
d.The $1,000 down payment cap does not apply at a showroom sale

What B&P §7159 requires inside a home improvement contract does not depend on where it is signed: a job over $500 needs the same signed writing sold in a kitchen or in a showroom, and the §7159.5(a)(3) down payment cap of $1,000 or 10% of the price, whichever is less, applies the same way. What does depend on the setting is the cancellation notice - §7159 excuses the Three-Day Right to Cancel notice where the contract is negotiated at the contractor's place of business, because those three business days come from the home solicitation rules of Civil Code §1689.5 and §1689.6, which reach contracts made away from the seller's trade premises.

Bus. & Prof. Code §7159; §7159.5(a)(3); Civil Code §1689.5, §1689.6(a)(2)
89. A 'no-damage-for-delay' clause in a contract typically:
a.Requires the owner to pay the contractor's delay costs
b.Limits the contractor to added time, not to money✓
c.Sets a daily amount the contractor owes for late finish
d.Excuses the contractor from the completion date

A no-damage-for-delay clause leaves added time as the contractor's only remedy for the delays it covers, so extended overhead and idle-equipment costs stay with the contractor. Owner payment of delay costs is what a compensable-delay or changes clause does — the opposite result. A daily amount owed for finishing late is liquidated damages, which runs against the contractor rather than limiting its remedy. And the clause does not excuse the completion date: the schedule stays, only the money claim goes. On public work, Public Contract Code §7102 stops an agency from enforcing such a clause for delay the agency itself caused.

Common law contract clause; cf. Public Contract Code §7102 (public entities may not enforce a no-damage-for-delay clause against delay the entity itself caused)
90. An indemnification (hold harmless) clause in a construction contract generally:
a.Caps each party's total money damages at the contract price
b.Shifts defined liability or defense duties to the other party✓
c.Names the other party as an additional insured on its own policy
d.Requires that disputes be decided by an arbitrator, not a court

An indemnity (hold harmless) clause allocates risk: one party agrees to protect, defend, or reimburse the other against specified claims arising from the work. Capping damages at the contract price is a limitation-of-liability clause. Being named an additional insured is an insurance endorsement, which moves the cost to a carrier rather than between the parties. Sending disputes to an arbitrator is a dispute-resolution clause. Civil Code §2782(a) sets the outer limit: a construction indemnity reaching the promisee's sole negligence or willful misconduct is void.

Civil Code §2782(a)
91. A home improvement contract must disclose the contractor's license number primarily so that the homeowner can:
a.Calculate the contractor tax liability for the job
b.Check license status, classification and complaints at CSLB✓
c.Determine the contractor profit margin on the job
d.Apply for the building permit in the contractor's name

The license number is how the homeowner reaches the CSLB record: whether the license is active, what classification it covers, the bond and workers' compensation on file, and any disciplinary or complaint history — all checkable before work starts. It says nothing about the contractor's tax liability or profit margin, which live in the contractor's own books. And a permit is pulled by the licensed contractor or by the owner as owner-builder; a homeowner cannot apply in the contractor's name just because the number appears in the contract.

B&P Code §7159(d)(1)
92. A subcontract should clearly state the scope of work primarily to:
a.To fix the price the owner pays for every change order made
b.To keep disputes from arising over what counts as extra✓
c.To settle which of the parties must pull the building permits
d.To decide which trades must carry their own license

A precise scope prevents gaps and overlaps, making clear which work the subcontract price already covers and which is extra work that needs a change order. What a change order costs is set by the contract's pricing terms, not by the scope. Permit responsibility is its own provision. And license classification is a legal requirement that the parties cannot assign to each other in a scope clause.

Subcontract scope / change orders (industry practice); B&P §7159 (change orders in writing)
93. When an owner signs a contract by accepting a contractor's written bid exactly as offered, the agreement is formed by:
a.A change order
b.A liquidated damages clause
c.Offer and acceptance✓
d.A preliminary notice

A binding contract requires an offer and an acceptance of that offer's terms, supported by consideration. Accepting a written bid as offered creates the contract through offer and acceptance.

94. A home improvement contract may NOT include which of the following provisions?
a.A schedule of progress payments tied to work already completed
b.A dated statement waiving cancellation for an emergency repair
c.A clause making the homeowner waive statutory protections✓
d.A start date and an approximate date of completion

A pre-printed clause that strips the homeowner of what B&P §7159 grants is unenforceable: Civil Code §3513 says a law established for a public reason cannot be contravened by private agreement. The other three belong in the file. Progress payments tied to work already completed are how §7159.5(a)(5) expects payment to be staged, and a start date with an approximate completion date is required contract content. Civil Code §1689.13 does allow one narrow waiver of the cancellation right - but only by a separate dated, signed statement describing the situation that needs immediate remedy, never by a clause in the contract.

Civil Code §3513; Civil Code §1689.13; Bus. & Prof. Code §7159, §7159.5(a)(5)
95. A contractor's bid bond on a public project primarily guarantees that:
a.The finished work will stay free of defects for ten years
b.Every subcontractor and supplier on the job will be paid
c.The contractor will complete the work for the contract price
d.The winning bidder will sign and post the required bonds✓

A bid bond guarantees only that a bidder who is awarded the contract will enter into that contract and furnish the required performance and payment bonds; if the bidder walks away, the bond answers for the cost of reletting the work. Completing the work for the contract price is what a performance bond guarantees. Paying subcontractors and suppliers is the payment bond. And a ten-year defect guarantee is a warranty or maintenance bond.

Bid bond vs performance/payment bond (public contracting practice); Public Contract Code §20103.5
96. A homeowner exercises the three-day right to cancel a home improvement contract. The contractor had already delivered some materials. The contractor:
a.Must refund the buyer's payments and may reclaim the materials✓
b.May keep up to $1,000 of the down payment as a cancellation fee
c.May bill the buyer for the materials delivered before the notice
d.May hold the refund until the buyer returns the delivered materials

A timely cancellation must be honored. The Notice of Cancellation required by B&P §7159, and Civil Code §1689.10, give the contractor 10 days from receipt of the notice to return every payment; the buyer need only make delivered goods available at their own residence, and if the contractor does not pick them up within 20 days the buyer may keep them without further obligation. No cancellation fee is authorized - the $1,000 figure is the §7159.5 down-payment cap, not money the contractor may retain. Materials delivered before the notice cannot be billed, and the refund cannot be held hostage to their return: the 10-day refund duty does not wait on the 20-day pickup window.

Bus. & Prof. Code §7159 (Notice of Cancellation); Civil Code §1689.10, §1689.11
97. A contractor wants to recover $96,000 of annual overhead and earn 8% net profit on sales. If projected annual sales are $800,000, the profit dollars expected are:
a.$8,000
b.$96,000
c.$104,000
d.$64,000✓

Net profit equals the profit rate times sales: 8% x $800,000 = $64,000. Overhead recovery ($96,000) is separate; profit is what remains after both direct costs and overhead are covered.

98. A contractor stops work on a project for two weeks because the owner has not made an undisputed progress payment that is clearly due. This work stoppage is:
a.Abandonment under §7107, whatever the reason for leaving
b.Grounds for automatic license revocation by the Registrar
c.Permitted only after a 10-day written notice to the owner
d.A lawful suspension, not abandonment, since payment was due✓

B&P §7107 makes abandonment - leaving a project without legal excuse - a cause for discipline, so a stoppage the owner's own failure to pay a clearly due, undisputed amount justifies is a suspension rather than abandonment. The reason for leaving is exactly what §7107 turns on, so 'whatever the reason' misreads it. Discipline is never automatic: the Registrar must proceed by accusation. And no statute conditions a justified suspension on 10 days' written notice.

B&P Code §7107
99. An estimate that totals all material and labor quantities from the plans, item by item, to build up a price is BEST described as:
a.A square-foot or conceptual estimate
b.An assembly or systems-level estimate
c.A detailed quantity-takeoff estimate✓
d.A schedule of values for billing

A detailed estimate is built from a quantity takeoff: every material and labour item is measured off the plans and priced, item by item. A square-foot or conceptual estimate skips that and multiplies area by a historical rate, which is why it is used early and is far less accurate. An assembly or systems estimate sits between the two, pricing whole assemblies rather than individual quantities. A schedule of values is not an estimate at all — it is the breakdown of the agreed price used to support progress billings.

Estimating practice (no statute)
100. The home solicitation contract rules that give a three-day cancellation right apply to a contract that is:
a.Negotiated and signed at the contractor's own place of business, not the buyer's
b.Awarded by a public agency to the low bidder after competitive bidding
c.For goods or services of $500 or more, no matter where it is signed
d.For goods or services of $25 or more, signed away from trade premises✓

Civil Code §1689.5(a) defines a home solicitation contract as one for the sale, lease or rental of goods or services 'in an amount of twenty-five dollars ($25) or more' made at other than appropriate trade premises, and §1689.5(b) defines those premises as where the seller normally carries on business. The PLACE of the transaction plus a very low dollar floor is what triggers the three-business-day right under §1689.6 — not the size of the job. (a) states the exception rather than the rule: a contract negotiated and signed at the contractor's own office is made at appropriate trade premises and carries no §1689.6 cancellation right. (c) inflates the $25 floor to $500 and drops the place element, which is the operative one. (b) is not a consumer transaction at all; §1689.5(c) limits 'goods' to things bought primarily for personal, family or household purposes.

Civil Code §1689.5(a)-(d), §1689.6(a)
101. A contractor's bid is $120,000. After the contract is signed, the owner requests an approved change order adding $15,000 of work and a deductive change order removing $4,000. The adjusted contract price is:
a.$120,000
b.$135,000
c.$116,000
d.$131,000✓

Change orders adjust the contract price up and down: $120,000 + $15,000 - $4,000 = $131,000. The adjusted price reflects all signed change orders.

102. Which contract type generally gives the owner the LEAST cost certainty at the time of signing?
a.Fixed-price (lump sum) contract
b.Guaranteed maximum price contract
c.Cost-plus-fixed-fee contract
d.Cost-plus-percentage contract✓

Under cost-plus-percentage the fee itself grows with the cost, so the owner learns the final price only when the work is finished - the least certainty of the four, and the reason many owners refuse the form. Cost-plus-fixed-fee is the near miss: the costs are still open but the fee is capped, so escalation at least stops adding to the contractor's margin. A guaranteed maximum price puts a ceiling over the same open costs, and a fixed price fixes the whole number at signing.

103. A home improvement contract must be legible and any blank spaces should be:
a.Left blank for the contractor to complete after signing
b.Filled in only by the building department
c.Completed before the owner signs the contract✓
d.Filled in after the project is finished

The contract must be fully completed before the owner signs, so the homeowner sees and agrees to all material terms. Leaving blanks to be filled in later is improper and unfair to the consumer.

Bus. & Prof. Code §7159
104. An owner-contractor agreement and a subcontract are kept consistent through:
a.An indemnity clause moving the prime's liability to the sub
b.A flow-down clause passing prime-contract duties to the sub✓
c.A pay-when-paid clause tying payment to the owner's payment
d.A no-damages-for-delay clause barring the sub's delay claims

A flow-down (or conduit) clause incorporates the prime contract's relevant terms into the subcontract, so the sub owes the general the same obligations the general owes the owner for that scope. An indemnity clause allocates liability for claims; it does not import the prime contract's terms. A pay-when-paid clause governs only the timing of payment. And a no-damages-for-delay clause limits one remedy. None of those three keeps the two contracts consistent.

Flow-down/conduit clause (industry practice); Civil Code §2782 (indemnity limits)
105. A contractor's job-cost report shows materials are 15% over budget while labor is on budget at the 50% completion point. The contractor should:
a.Wait for closeout to investigate the material variance
b.Stop buying material until the owner approves a change order
c.Investigate the variance now and correct the purchasing plan✓
d.Bill the owner for the overage without a change order

Job costing exists to surface a problem while there is still time to act: a 15 percent material overrun at the halfway point should be investigated at once, and purchasing or scope corrected before the second half doubles the loss. Waiting for closeout throws away the only chance to correct it. Halting the work over an internal cost variance risks abandonment under B&P §7107, because the owner has changed nothing. And an overrun the owner did not cause is not extra work, so it cannot be billed - with or without a change order.

Job-cost variance analysis (industry practice); B&P §7107 (abandonment)
106. A subcontractor signs a CONDITIONAL waiver and release on progress payment under Civil Code §8132 in exchange for a check that later bounces. What is the legal effect on the waiver?
a.The waiver is fully enforceable because it was signed in writing
b.The waiver does not become effective until the check is actually honored by the bank✓
c.The waiver is automatically converted to an unconditional waiver after 30 days
d.The waiver is enforceable but the subcontractor may sue separately for the bounced check

A conditional waiver under Civil Code §8132 only becomes effective when there is evidence of actual payment, meaning the check clears the bank. If payment fails, the waiver has no legal force and the subcontractor retains full lien rights.

Civ. Code §8132
107. A prime contractor's subcontract requires the subcontractor to indemnify the prime for ALL claims, including those arising from the prime's SOLE negligence. Under Civil Code §2782, this broad-form indemnity provision is:
a.Enforceable if signed by a licensed subcontractor
b.Enforceable only on public works projects
c.Void and unenforceable as against public policy✓
d.Enforceable only when the subcontract is over $50,000

Civil Code §2782 voids any construction contract clause that purports to indemnify a party for liability caused by its sole negligence or willful misconduct. This anti-broad-form-indemnity rule cannot be waived.

Civ. Code §2782
108. A homeowner verbally asks the contractor to upgrade tile during a bathroom remodel. The contractor proceeds without a written change order. Under B&P §7159, the contractor's ability to collect the extra $3,200 is:
a.At risk: an unsigned change order is unenforceable✓
b.Secure, because the daily log proves what was agreed
c.Secure, because verbal changes are valid up to $5,000
d.At risk only if the homeowner files a CSLB complaint

B&P §7159(c)(5) makes a change-order form part of the contract only if it is in writing and signed by the parties before the work covered by it starts, and the opening words of §7159(d) say the same of the contract and any changes to it — so an unsigned verbal upgrade leaves the extra at risk. A daily log is the contractor's own record, not the owner's signature. No dollar figure turns a verbal change order into an enforceable one; there is no $5,000 line in §7159. And the risk is not the complaint: the money is at risk in a collection action whether or not the homeowner ever contacts the CSLB.

B&P Code §7159(c)(5); §7159(d)
109. An owner records a valid Notice of Completion 12 days after actual completion of the work under Civil Code §8182. What is the effect on the time direct contractors have to record a mechanics lien?
a.90 days, counted from the recording of the Notice
b.No lien at all, since the Notice cuts off lien rights
c.30 days, the window that applies to subcontractors
d.60 days, counted from the recording of the Notice✓

Civil Code §8182 lets an owner record a notice of completion on or within 15 days after completion, so a notice recorded on day 12 is valid - as the stem says it is. What it does is set by §8412: a direct contractor must record its lien before the EARLIER of 90 days after completion or 60 days after the owner records the notice, so once the notice is on record the 60-day clock governs, because it runs out first. The 90-day period is real but measured from completion, not from the recording. The 30-day window is real too, but §8414 gives it to claimants other than the direct contractor - subcontractors and suppliers. And a notice of completion shortens a deadline; it never extinguishes the lien right.

Civil Code §8182; §8412; §8414
110. On a private works project, when a valid Notice of Completion IS timely recorded, a direct (prime) contractor must record its mechanics lien within how many days under Civil Code §8412?
a.30 days
b.60 days✓
c.90 days
d.120 days

Under Civil Code §8412, a direct contractor has 60 days after recording of a Notice of Completion or Notice of Cessation to record a mechanics lien. Without such a notice, the period is 90 days after actual completion.

Civ. Code §8412
111. A drywall subcontractor on a private works project finished its scope on March 1, the same day the work of improvement was actually completed. No Notice of Completion has been recorded. Under Civil Code §8414, the LATEST date the subcontractor may record a mechanics lien is approximately:
a.March 31 (30 days after its own last day)
b.April 30 (60 days after its own last day)
c.May 30 (90 days after actual completion)✓
d.August 29 (180 days after its own last day)

Civil Code §8414 gives a claimant other than the direct contractor until the earlier of 90 days after completion of the work of improvement or 30 days after the owner records a notice of completion or cessation. No notice was recorded here, so the 90-day limb controls and the lien must be recorded by about May 30. The 30-day figure is the shortened deadline that only a recorded notice triggers, and it runs from that recordation rather than from the subcontractor's last day. Sixty days is the direct contractor's post-notice window under §8412, not a subcontractor's. No deadline in the California lien statute runs 180 days.

Civil Code §8414; cf. §8412
112. Work on a private project ceases for 35 continuous days due to a financing dispute. The owner records a Notice of Cessation under Civil Code §8174. What is the effect on subcontractor lien deadlines?
a.Subcontractors must record liens within 30 days after the Notice of Cessation is recorded✓
b.Subcontractors must record liens within 90 days after the Notice of Cessation is recorded
c.The Notice of Cessation is invalid because work must cease for at least 60 days
d.The Notice of Cessation has no effect on subcontractor lien rights

A Notice of Cessation under Civil Code §8174 can be recorded after work has ceased for at least 30 continuous days. When validly recorded, it shortens the subcontractor and supplier lien deadline to 30 days from recording, the same effect as a Notice of Completion.

Civ. Code §8174
113. A consumer home-improvement contract includes a clause forcing the homeowner to pay all of the contractor's attorney fees in any dispute, while barring the homeowner from recovering her own. Under Civil Code §1670.5, a court reviewing this provision may:
a.Enforce the clause because both parties signed the contract
b.Refuse to enforce the clause, or limit how it is applied✓
c.Rewrite the clause so the fee award runs both ways
d.Send the fee dispute to CSLB arbitration before ruling

Civil Code §1670.5(a) lets a court that finds a clause unconscionable as a matter of law refuse to enforce the contract, enforce the rest of it without the clause, or so limit the clause's application as to avoid an unconscionable result. That both parties signed is not an answer: unconscionability is a doctrine about signed contracts. The statute lets the court decline or narrow the clause, not redraft it into a mutual fee provision the parties never agreed to. And §1670.5 is a question of law for the court, not something routed to a CSLB arbitration first.

Civil Code §1670.5(a)
114. A general contractor receives a joint check made payable to BOTH the subcontractor and its material supplier. Best practice in California is for the GC to:
a.Endorse the check into the GC's account and then pay out
b.Hand the check to the supplier and skip the subcontractor
c.Get a joint check agreement and waivers before release✓
d.Cash the check and split it at the GC's own discretion

The protection comes from agreeing the joint check terms before the check moves and exchanging conditional waivers and releases on the Civil Code §8132 form at release: the agreement says how the funds are allocated, and the waivers record that the money reached both payees, which is what keeps the supplier's lien off the job. Running the check through the GC's own account first turns both payees' money into the GC's and invites the very claim the joint check was meant to prevent. Paying the supplier and skipping the subcontractor leaves the sub's labor unpaid and its lien rights alive. And splitting a two-payee check at the GC's discretion is not a discretion the GC has — both payees must endorse.

Civil Code §8132
115. A prime contractor receives a $200,000 progress payment from the owner. The subcontract calls for $40,000 to a plumbing sub for completed work that was approved in the payment. Under B&P §7108.5, the prime must pay the sub within how many days of receipt?
a.Within 10 days of receiving each progress payment from the owner
b.Within 30 days of receiving each progress payment from the owner
c.Within 45 days of receiving each progress payment from the owner
d.Within 7 days of receiving each progress payment from the owner✓

B&P §7108.5(a) gives the direct contractor 7 days after receipt of each progress payment to pay each subcontractor its share, unless the parties agree otherwise in writing; wrongful withholding costs 2 percent of the amount due per month plus the prevailing party's attorney's fees (§7108.5(b)-(c)), and in a good faith dispute no more than 150 percent of the disputed amount may be held back. Each wrong number is a real California deadline for a DIFFERENT payment. (a) 10 days is Civil Code §8814, the direct contractor's deadline to pass RETENTION through to subs. (b) 30 days is Civil Code §8800, the owner's deadline to pay the direct contractor a progress payment after a demand. (c) 45 days is Civil Code §8812, the owner's deadline to release retention after completion of the work of improvement.

Bus. & Prof. Code §7108.5; cf. Civil Code §8800, §8812, §8814
116. A subcontractor on a private project completes its work and the prime contractor withholds 5% retention. The owner has accepted the project and released all retention to the prime. Under Civil Code §8814, the prime must release the sub's retention within how many days?
a.Within 10 days of receipt from the owner✓
b.Within 30 days of receipt from the owner
c.Within 60 days of subcontractor completion
d.Only after final acceptance by all subcontractors

Civil Code §8814 requires a prime contractor to release retention withheld from a subcontractor within 10 days after receiving the retention from the owner (a). Wrongful withholding triggers a 2% per month penalty under Civil Code §8818, plus costs and attorney fees to the prevailing party. (b) 30 days and (c) 60 days are contract terms, not the statute's; 60 days is the Public Contract Code §7107 window for a public agency, a different project type. (d) invents a condition — no subcontractor's acceptance gates another's retention. The retention percentage itself is capped at 5% by Civil Code §8811 for contracts entered into on or after January 1, 2026.

Civil Code §8814
117. A home-improvement contract has a total contract price of $48,000. Under B&P §7159(d), the MAXIMUM down payment the contractor may demand or accept before any work or material delivery is:
a.$2,500
b.$1,000✓
c.$4,800 (10% of contract)
d.$5,000 or 10%, whichever is greater

B&P §7159(d) caps the down payment on a home improvement contract at the LESSER of $1,000 or 10% of the contract price, exclusive of finance charges. Here 10% would be $4,800 so the lesser amount of $1,000 controls.

Bus. & Prof. Code §7159(d)
118. A consumer signs a home-solicitation contract for solar panel installation at her residence on a Tuesday at 6 PM. Under Civil Code §1689.5 et seq., she may cancel without penalty until midnight on:
a.Wednesday (the next calendar day)
b.Thursday (48 hours after signing)
c.Friday (the third business day)✓
d.Tuesday next week (7 calendar days)

The Home Solicitation Sales Act, Civil Code §1689.5 et seq., lets the buyer cancel until midnight of the third business day after the day the contract was signed (§1689.6). Signed Tuesday: Wednesday is one, Thursday is two, Friday is three. The next day and a flat 48 hours are both shorter than the statute allows, and seven calendar days is the federal-style cooling-off period some buyers expect, not California's home-solicitation rule.

Civil Code §1689.5; §1689.6
119. A contractor wishes to collect progress payments on a home-improvement contract. Under B&P §7159.5, each progress payment must:
a.Equal exactly 10 percent of the contract price each time
b.Be payable when materials are ordered, before delivery
c.Cover the next phase's costs before that work starts
d.Not exceed the value of work done and materials on site✓

B&P §7159.5(a)(5) bars front-loading: apart from the downpayment, a contractor may neither request nor accept a payment exceeding the value of the work performed or the material delivered. The exact-10-percent answer borrows the §7159.5(a)(3) downpayment cap — $1,000 or 10 percent of the contract, whichever is less — and misapplies it to every progress payment. Billing when materials are merely ordered fails because §7159.5(a)(5) counts material delivered, not material promised, and billing the next phase before that work starts is the front-loading the section exists to stop.

B&P §7159.5(a)(5); cf. §7159.5(a)(3)-(4)
120. A commercial construction contract has a liquidated damages clause of $2,500 per day for late completion. Under Civil Code §1671(b), this clause is presumed:
a.Valid unless the challenger proves it was unreasonable at formation✓
b.Void as a penalty unless it equals the owner's actual daily loss
c.Valid only if the clause appears in 14-point boldface on page one
d.Void unless the CSLB approved the amount before signing

Civil Code §1671(b) makes a liquidated damages provision valid unless the party seeking to invalidate it establishes that it was unreasonable under the circumstances existing at the time the contract was made: the burden sits on the challenger and the measuring date is formation, not the day the delay happened. Requiring the sum to equal actual daily loss is the stricter treatment §1671(c)-(d) reserves for consumer contracts. Type-size requirements come from the home improvement statutes, not from §1671. And the CSLB does not approve or pre-clear contract terms.

Civil Code §1671(b), §1671(c)-(d)
Report