浏览所有题目

这些题目考的数字,按章节排在可打印的彩色高密度页面上: 速记册,$9.99 →

拥有完整的 CSLB Law & Business 学习指南 —— PDF + EPUB,$24.99 →

查看每道题的答案和解析——可按主题或全部一起学习。

保险与留置权

198 道题
169. A contractor's umbrella or excess liability policy is designed to:
a.Take the place of the workers' compensation policy entirely
b.Add limits above the underlying policies once exhausted✓
c.Act as the primary policy for every kind of claim
d.Cover only the contractor's own defective work

An umbrella or excess policy sits above scheduled underlying policies — commercial general liability, commercial auto, often employers' liability — and pays only after those limits are exhausted, which is how a contractor reaches catastrophic-claim limits without buying them at the primary layer. (c) inverts that structure. (a) confuses liability limits with workers' compensation, which is statutory, separate, and not something an umbrella replaces. (d) names the risk the CGL's 'your work' exclusion leaves with the contractor, and an umbrella follows the underlying policy's terms rather than curing its exclusions.

—
170. Which of these must a valid recorded mechanics lien contain?
a.The claimant's demand, after just credits and offsets✓
b.A copy of the claimant's workers' compensation certificate
c.The owner's construction loan and account numbers
d.The claimant's profit margin on the contract

Civil Code §8416(a) requires a written statement, signed and verified by the claimant, containing the claimant's demand after deducting all just credits and offsets, the name of the owner or reputed owner if known, a general statement of the kind of work furnished, the name of the person who employed the claimant, a description of the site sufficient for identification, the claimant's address, and a proof of service affidavit; the statutory Notice of Mechanics Lien must be served with it. §8422 forgives erroneous information about the demand, the credits, the work, or the site unless the court finds the claimant intended to defraud, or a party without actual knowledge was misled to its prejudice. The other three answers are records no lien requires and that do nothing to identify the claim.

Civ. Code §8416(a) / §8422
171. A subcontractor who is added as additional insured on NO ONE's policy and carries its own CGL is protected for third-party claims:
a.Not at all, since protection depends on the prime contractor's policy
b.Only for injuries to its own employees, through workers' compensation
c.Only to the extent the general contractor's policy chooses to respond
d.By its own CGL policy, subject to its terms and limits✓

A contractor's own commercial general liability policy insures it against covered third-party bodily injury and property damage arising from its operations, whether or not anyone has named it on another policy. (a) and (c) reverse the direction of additional insured coverage — that status usually runs upward, giving the owner and prime access to the sub's insurer, not the other way round. (b) confuses the two coverages: workers' compensation answers injuries to the contractor's own employees, and third parties are not employees.

172. The construction lender must be served with a preliminary notice by a claimant lacking an owner contract primarily so the claimant can later:
a.Serve a bonded stop payment notice for undisbursed funds✓
b.Record a mechanics lien senior to the lender's deed of trust
c.Compel the lender to release the remaining loan to the owner
d.Claim on the lender's own errors and omissions coverage

Notice to the lender is what keeps the fund-based remedy alive: a bonded stop payment notice under §8532 obliges the lender to withhold loan money it has not yet disbursed. (b) is the closest trap because lien priority is a real and valuable question, but priority turns on when work commenced relative to recording of the deed of trust, not on whom the preliminary notice went to. (c) reverses the point of the notice, which is to stop money rather than release it. (d) invents a claim against the lender's own insurance.

Civil Code §8200 / §8532
173. On a public works project, subcontractors generally CANNOT record a mechanics lien against the public property. Their principal payment security instead is the:
a.Notice of non-responsibility recorded by the public entity's agent
b.Builder's risk policy the public entity carries on the improvement
c.Payment bond, plus a stop payment notice against public funds✓
d.Performance bond posted by the direct contractor at award

Public property cannot be sold to satisfy a private claim, so the legislature substituted two remedies: the direct contractor's payment bond and a stop payment notice served on the public entity against funds still unpaid. (d) is the sharpest distractor, because both bonds are posted on the same job — but the performance bond answers to the public entity for completion, and a sub is not its beneficiary. (a) concerns work ordered by someone other than the owner. (b) is first-party property insurance on the work itself and pays no one for unpaid labour or materials.

Civil Code §9100 et seq. / §9350 et seq.
174. After an owner records a lien release bond of 125%, an unpaid subcontractor who wants to be paid must now pursue:
a.The CSLB, which holds the contractor's licence bond for claimants
b.The surety on the release bond, and the bond's principal✓
c.The construction lender, whose loan funded the improvement work
d.The real property, by foreclosing the lien the bond replaced

Recording a release bond under Civil Code §8424 substitutes the bond for the property, so the claimant's action runs against the surety and the principal rather than against title. (d) is the step the bond was recorded to foreclose, and pursuing it is the error the section exists to prevent. (a) misroutes a claim: the §7071.6 licence bond is claimed against its surety, and the CSLB holds no money. (c) reaches the wrong party — funds in the lender's hands are the target of a bonded stop payment notice, a separate remedy with its own notice conditions.

Civil Code §8424
175. 'Employers' liability' coverage, usually part of a workers' compensation policy, protects the employer against:
a.Statutory benefits owed to an employee injured at work
b.Employee-injury suits outside the exclusive remedy rule✓
c.Bodily injury to the public caused by the employer's work
d.Wage claims brought by employees for unpaid overtime hours

Coverage B of a workers' compensation policy answers employee-injury liability that the no-fault benefit system does not resolve — third-party-over actions, consequential claims by family members, and dual-capacity claims. (a) is Coverage A of the same policy, the statutory benefits themselves, and mistaking the two is the whole point of the item. (c) is commercial general liability, which excludes injury to employees precisely because this coverage handles it. (d) is a wage claim, which is neither an injury nor insured under a workers' compensation policy.

Labor Code §3600 / §3602
176. A direct contractor completed a private remodel on March 1. No notice of completion was ever recorded and the owner never occupied. The contractor's last day to record a mechanics lien is approximately:
a.March 11 (10 days)
b.March 31 (30 days)
c.May 30 (90 days)✓
d.April 30 (60 days)

With no notice of completion or cessation recorded, Civil Code §8412 gives the direct contractor 90 days from completion to record. Counting 90 days from March 1 lands near the end of May.

Civ. Code §8412
177. Requiring a subcontractor to provide a certificate of insurance BEFORE it starts work is a best practice primarily because it:
a.Makes the general contractor a policyholder from the first work day
b.Prevents the insurer from cancelling the policy during the project
c.Extends the general contractor's own coverage over the sub's work
d.Confirms the required coverage is in force before work starts✓

Checking the certificate before the sub mobilizes verifies that the required coverage exists at the moment exposure begins, when it is still possible to keep an uninsured sub off the site. (a) confuses receiving a document with buying a policy. (b) reads the certificate as controlling the insurer, which it does not — cancellation rights live in the policy. (c) reverses the transfer: the purpose is to reach the sub's insurer for the sub's work, not to spend the general contractor's own limits on it.

178. Which best describes the difference between the payment bond and the performance bond on the SAME project?
a.The payment bond guarantees the schedule; the performance bond the budget
b.The payment bond protects subs from nonpayment; the performance bond protects the owner✓
c.The payment bond protects the owner from liens; the performance bond protects the surety
d.The payment bond pays the contractor; the performance bond pays the subcontractors

The two bonds are issued together and answer different failures: the payment bond guarantees that subcontractors and suppliers are paid, and the performance bond guarantees to the owner that the work is completed according to the contract. (a) invents schedule and budget guarantees neither bond gives. (c) is half-right and therefore the strongest distractor — reduced lien exposure is a real benefit to the owner, but it is a consequence of subs being paid, and no bond exists to protect the surety. (d) reverses both beneficiaries.

Civil Code §8600 et seq.
179. A mechanics lien recorded on a private project must describe the property with:
a.The contractor's license number and classification
b.The project's estimated fair market value today
c.A description of the site sufficient to identify it✓
d.The owner's mailing address and telephone number

Civil Code §8416(a)(5) requires a description of the site sufficient for identification; a street address usually does, and a legal description removes all doubt. §8422 then forgives an erroneous site description unless the court finds the claimant intended to defraud, or that a party without actual knowledge of the mistake was misled to its prejudice. (a) and (b) appear nowhere in the section. (d) is close enough to be tempting — §8416(a)(2) requires the owner's name if known and (a)(6) requires the CLAIMANT's address — but the owner's mailing address and phone number are not what identifies the property.

Civ. Code §8416(a)(5) / §8422
180. 'Additional insured' status is most valuable to an upstream party (like an owner or GC) because it:
a.Releases the upstream party from carrying its own liability coverage
b.Lowers the downstream party's premium by spreading the same risk
c.Guarantees that the downstream party will complete its scope of work
d.Gives access to the sub's insurer for defense and indemnity✓

An additional insured endorsement lets the owner or general contractor tender a claim arising out of the subcontractor's work to the subcontractor's insurer and obtain a defense and indemnity under that policy, subject to its terms and limits. (a) is the dangerous reading: risk transfer supplements your own coverage and never excuses it. (b) confuses insurance with cost allocation — adding insureds does not reduce the premium. (c) describes a performance bond, which is a surety obligation rather than an insurance one.

181. An architect provided design services for a private work of improvement, authorized by the owner. The architect:
a.Never has lien rights, in any circumstances
b.May give a stop payment notice, but never a lien
c.Must carry builder's risk insurance instead
d.May have lien rights for those services✓

Civil Code §8400(f) lists the design professional among the persons with a mechanics lien right for work provided to a work of improvement, subject to the same preliminary notice condition in §8410 and the recording deadlines in §8412 and §8414. California also gives design professionals a separate remedy in §8300 et seq. for design services furnished before construction starts, which §8302(c) allows only where a building permit or other governmental approval has been obtained using those services. (a) ignores both routes. (b) reverses the remedies, and a design professional's stop payment notice rights are expressly preserved in §8608(b). (c) confuses property insurance with a payment remedy.

Civ. Code §8400(f) / §8302(c)
182. An owner wants to be an additional insured on the contractor's policy. For the owner actually to have that status, the certificate must be accompanied by:
a.A recorded copy of the claimant's mechanics lien
b.A recent statement from the contractor's own bank
c.An additional insured endorsement to the policy✓
d.A thirty-day notice of cancellation clause

Only the insurer can add an insured to a policy, and it does so by endorsement; a certificate is a broker's evidence of coverage and its own wording disclaims amending the policy. (d) is the substitute owners most often settle for — a notice provision tells the owner when coverage is ending, it does not make the owner an insured or give it a right to defense. (a) and (b) belong to other transactions entirely, one in the lien law and the other in a credit file.

—
183. A stop payment notice, unlike a mechanics lien, does NOT need to be:
a.Supported by a valid claim
b.Given by someone who furnished work
c.Served on the correct party
d.Recorded with the county recorder✓

A stop payment notice is served, not recorded; it directs the owner or lender to withhold funds. A mechanics lien, by contrast, is recorded against the property. Both require a valid underlying claim by someone who furnished work and proper service.

Civ. Code §8500
184. A contractor pays day laborers in cash, calls them independent contractors, and carries no workers' compensation. A laborer is injured. The contractor most likely:
a.Owes the CSLB an administrative fine and nothing more
b.Has no exposure at all, the laborers being independent
c.Is liable as an uninsured employer for the injury✓
d.Is covered by the general liability policy instead

Labor Code §2775(b)(1) treats a worker as an employee unless the hiring entity proves all three parts of the ABC test, and §2781 sets the narrower conditions for construction subcontractors; the label on the paperwork settles nothing. An employer that owed coverage and had none faces the civil action §3706 allows, in which §3708 presumes the injury was caused by the employer's negligence and removes the usual defenses, plus §3700.5 misdemeanor exposure and suspension of the license under B&P §7125.2. (a) understates the exposure by orders of magnitude. (b) is the label-as-conclusion error the ABC test forecloses. (d) misreads the commercial general liability policy, which excludes bodily injury to the insured's own employees precisely because workers' compensation answers it.

Lab. Code §2775(b)(1) / §2781 / §3706 / §3708
185. A supplier first delivered materials on Day 1 but served its preliminary notice on Day 40. For which materials may it claim?
a.Only for the materials delivered after the 60th day of work
b.For nothing at all, the notice being fatally late
c.For every delivery, back to the very first one
d.For deliveries from about Day 20 forward, but not before✓

Civil Code §8204(a) provides that a claimant who did not give preliminary notice is not precluded from giving one later, but is then entitled to claim only for work performed within the 20 days prior to service of the notice, and at any time thereafter. Service on Day 40 therefore protects deliveries from roughly Day 20 forward, and the deliveries from Day 1 to Day 19 fall outside the window. (b) treats a late notice as fatal, which the subdivision expressly says it is not. (c) ignores the look-back altogether. (a) counts 20 days forward from service instead of backward, which protects nothing the statute protects.

Civ. Code §8204(a)
186. Which of the following is generally the LAST resort remedy because it requires foreclosing on real property?
a.Certificate of insurance
b.Mechanics lien✓
c.Stop payment notice
d.Payment bond claim

A mechanics lien ultimately requires a foreclosure action against the owner's real property to collect, making it more cumbersome than a stop payment notice (reaching funds) or a payment bond claim (reaching a surety). Claimants often pursue funds or bonds first.

187. On a project where a notice of completion is recorded, missing the 30-day lien deadline (for a non-direct claimant) generally means:
a.The claimant may still record within 60 days, as the direct contractor may
b.The claimant loses the mechanics lien, but other remedies may survive✓
c.The claimant may record within 90 days from actual completion instead
d.The claimant has 90 days from recording to file suit on the lien

Civil Code §8414 gives a claimant other than the direct contractor 30 days after a recorded notice of completion; miss it and the lien remedy is gone, though a payment bond claim, a timely stop payment notice, or a plain breach-of-contract action may remain. (a) borrows the direct contractor's 60-day period under §8412, which is not available to lower-tier claimants. (c) is the no-notice rule the recording displaced. (d) states the §8460 deadline for suing on a lien already recorded, which never revives a lien that was recorded too late.

Civil Code §8414 / §8460
188. A general contractor's CGL policy typically will NOT respond to which claim?
a.The contractor's crane damaging the neighboring building
b.A visitor tripping on debris and breaking an arm
c.A pedestrian struck by material falling from the frame
d.The contractor's own employee injured while framing✓

A commercial general liability policy excludes bodily injury to an employee arising out of employment, because that injury belongs to workers' compensation, with Coverage B employers' liability picking up the suits the no-fault system does not resolve. (a), (b) and (c) are exactly what the CGL is bought for: third-party bodily injury and property damage arising out of the contractor's operations. The line is who was hurt, not how badly or where — an employee framing the same wall as the injured visitor produces a workers' compensation claim, not a CGL claim.

—
189. A claim on a private-project payment bond generally requires the claimant to have:
a.Posted a bond of 125 percent of the claim before making it
b.Given the preliminary notice lien rights require, unless excused✓
c.Recorded a mechanics lien against the property before claiming
d.Obtained a judgment against the direct contractor before claiming

Under Civil Code §8600 et seq. the right to recover on a private-work payment bond tracks the notice conditions for a mechanics lien, so a claimant who had to give a preliminary notice must have given it — laborers and others excused from notice are excused here too. (a) imports the §8532 bond that accompanies a stop payment notice to a lender. (c) treats the remedies as sequential when they are alternative; a claimant may go against the bond without ever recording. (d) would make the bond useless, since its value is being payable without first litigating to judgment.

Civil Code §8600 et seq.
190. The most accurate reason insurance and surety bonds are BOTH used on construction projects is that they:
a.Are both two-party transfers, so carrying both doubles available limits
b.Both let the provider absorb the loss without seeking reimbursement
c.Both protect the contractor against claims made by the project owner
d.Address different risks: insurance covers loss, bonds guarantee duties✓

Insurance transfers the insured's own fortuitous losses to an insurer that does not expect repayment; a bond is a three-party guarantee running to an obligee, and the surety expects the principal to reimburse what it pays. Projects carry both because the risks do not overlap. (a) and (b) each describe insurance and then attach the label to both instruments. (c) mistakes who a bond protects — the owner is typically the obligee the bond runs to, so the bond protects the owner from the contractor, not the reverse.

191. A lien claimant who has been paid in full but refuses to release a recorded mechanics lien may be liable to the owner for:
a.Nothing, since a satisfied lien expires on its own schedule
b.Three times the value of the project, as a penalty
c.The owner's costs and attorney's fees to remove the lien✓
d.The contractor's lost profit on the delayed property sale

A claimant that has been paid should execute and record a release, and an unreleased lien clouds the owner's title until it does. The owner's statutory remedy is the petition in Civil Code §8480: once the claimant has let the 90 days in §8460 pass without commencing an action to enforce the lien, the owner may petition for an order releasing the property, the claimant carries the burden of proving the lien's validity under §8488(a), and §8488(c) awards the prevailing party reasonable attorney's fees. §8494 then strips an expired lien of any effect as notice. (a) ignores the practical problem the statute addresses, since the cloud on title bites long before anything expires. (b) invents a treble-damages penalty this remedy does not carry. (d) names the wrong party's loss: the harm runs to the owner whose title is clouded, not to the contractor.

Civil Code §8480 / §8488(c) / §8494
192. The $25,000 figure most commonly associated with California contractor licensing is:
a.The largest mechanics lien the statute allows
b.The project size that requires a payment bond
c.The contractor's license bond amount✓
d.The builder's risk limit the CSLB sets

$25,000 is the contractor's bond every active licensee must keep on file under B&P §7071.6 — and the same figure is the minimum disciplinary bond under §7071.8 and the amount of the qualifying individual's bond under §7071.9. (b) is the real neighbor and the reason this item is worth asking: Civil Code §9550(a) requires a payment bond on a public works contract involving an expenditure in excess of $25,000, the identical number doing an unrelated job. (a) invents a statutory cap on liens; a lien is in the amount of the claimant's demand. (d) invents a CSLB insurance requirement — the only insurance the license law compels is workers' compensation under §7125, plus the limited liability company's liability policy under §7071.19.

B&P Code §7071.6 / Civ. Code §9550(a)
193. SB 1455 (Stats. 2024, ch. 485) moved the date on which B&P §7125 requires every licensee, with or without employees, to carry workers' compensation. From what date does that requirement apply?
a.January 1, 2026
b.January 1, 2028✓
c.January 1, 2027
d.July 1, 2026

SB 216 (Stats. 2022, ch. 978) wrote a version of §7125 that requires every licensee to carry workers' compensation or self-insurance whatever its classification, leaving only a §7029 joint venture with no employees exempt, and set it to start on January 1, 2026. SB 1455 (Stats. 2024, ch. 485) rewrote that start date: the new section "shall become operative on January 1, 2028" (b), and the interim §7125 — a no-employee exemption available to everyone except C-8, C-20, C-22, C-39 and D-49 holders — stays in effect until then. (a) is the original SB 216 date, which is why so much study material still states the all-licensee rule as current. (c) is a real date in the same bill, but for something else: by January 1, 2027 §7125.7 requires the board to establish a process to verify that licensees claiming the no-employee exemption are eligible. (d) is not a date either bill uses.

Bus. & Prof. Code §7125 (Stats. 2024, ch. 485, SEC. 12–13); §7125.7
194. Until January 1, 2028, which of these licensees, working alone with no employees, may file the exemption from workers' compensation instead of carrying a policy?
a.A C-39 roofing contractor
b.A C-8 concrete contractor
c.A C-33 painting contractor✓
d.A D-49 tree service contractor

Until January 1, 2028, B&P §7125(b), as amended by SB 1455 (Stats. 2024, ch. 485), exempts an applicant or licensee that has no employees and files the Registrar's exemption statement — but only if it does not hold a C-8 (concrete), C-20 (warm-air heating, ventilating and air-conditioning), C-22 (asbestos abatement), C-39 (roofing) or D-49 (tree service) license. A C-33 painter is not on that list, so (c) may file. (a), (b) and (d) are on it: those holders must carry workers' compensation or a certification of self-insurance whether or not they employ anyone, and CSLB will not accept an exemption from them. From January 1, 2028 the list stops mattering, because the SB 216 version of §7125 requires every licensee to carry coverage except a §7029 joint venture with no employees — the painter included.

Bus. & Prof. Code §7125(b) (as amended by SB 1455, Stats. 2024, ch. 485)
195. 某承包商被查出雇用六名工人却没有工伤保险,因而收到停工令。其后,六人中的一人被认定在无保险期间发生了应予赔付的工伤。《劳工法》第 3722 条授权征收哪些罚款?
a.随停工令每名雇员 1,500 美元;应予赔付后每人再加 10,000 美元✓
b.随停工令按每名雇员 1,500 美元;工伤即使被认定应予赔付也不再另行加罚
c.随停工令按每名雇员 10,000 美元;对应予赔付的工伤再按每人 1,500 美元
d.只征收一笔 100,000 美元的固定罚款,这是第 3722 条唯一授权的数额

第 3722 条在两个不同的触发点上分两次征收。第 (a) 款随停工令一并作出,发生在任何人受伤之前,按签发并送达停工令时在雇人数每人 1,500 美元计。随后,第 (d)(2) 款在工伤被认定应予赔付时,按受伤之日在雇人数每人再加 10,000 美元。第 (f) 款的 100,000 美元是这些罚款「总额的上限」,本身不是一项罚款;而第 3700.5 条的刑事责任还叠加在这一切之上。

Labor Code §3722(a), (d)(2), (f)
196. 一名木工因自己粗心搭设的脚手架跳板断裂而受伤。其雇主投有工伤保险。他现在想以工地维护存在过失为由起诉该雇主。法律上会怎样处理?
a.不予赔付,因为伤是他自己造成的,所以只能走过失侵权诉讼这条路
b.既不予赔付也不能起诉,因为工伤赔偿是唯一救济途径
c.予以赔付,同时他也可以起诉雇主,因为工地本身确实不安全
d.尽管他本人有疏忽仍予赔付,而该赔偿请求是他对雇主的唯一救济✓

这是同一笔交易的两个半边。第 3600(a) 条规定雇主的赔偿责任「不问过失」,因此受伤工人即便部分甚至全部出于自身疏忽,仍可获得赔付。第 3602(a) 条则是这笔交易的对价:工伤赔偿请求是针对雇主的「唯一且排他」的救济,因此那起过失诉讼不能成立。狭窄的例外规定在别处——雇主故意殴打、欺诈性隐瞒伤情、雇主自制并出售的缺陷产品,或者雇主根本未投保。

Labor Code §3600(a); §3602(a)
197. 一名工人周一割伤手部需要缝合,周三递交了 DWC-1 索赔表。保险公司尚未接受或拒绝该索赔。雇主此时必须做什么,其责任到什么程度为止?
a.等保险公司作出决定,索赔待决期间无需授权任何治疗
b.须在周四前授权治疗,责任以 10,000 美元为限✓
c.须在周四前授权治疗,并承担所开具全部医疗费用的完整成本
d.须在 90 天内授权治疗,这同时也是拒绝该索赔的最后期限

两个期限从两个不同的事件起算。雇主自知悉工伤起有一个工作日交付索赔表。工人「递交」该表后,第 5402(c) 条要求雇主在一个工作日内授权符合适用诊疗指南的全部治疗,因此周三递交意味着周四之前。在索赔被接受或拒绝之前,这部分治疗责任以 10,000 美元为限——这笔钱正是在结论作出之前先花出去的,这就是该条的用意。90 天是另一个期限:未被拒绝的索赔到那时即被推定为应予赔付。

Labor Code §5401(a); §5402(b), (c)
198. 某业主以书面合同聘请一名注册专业工程师设计仓库,并凭这套图纸取得了建筑许可,随后搁置项目且从未支付设计费。该业主目前仍拥有这块地。工程师可以登记留置权吗?
a.不可以,因为工程从未开工,也就不存在可供留置权附着的对象
b.可以,登记普通机械师留置权,因为图纸是为工程提供的服务
c.可以,登记设计专业人员留置权,因为已取得建筑许可且业主仍持有该地块✓
d.可以,但前提是工程师在开始绘图后 20 天内送达过预备通知

《民法典》第 8302 条为设计专业人员在「计划中的工程尚未开工」的情况下,仍在场地上设定留置权——该章存在的意义正在于此。本题的条件全部齐备:符合第 8014 条定义的人员(注册专业工程师)、与土地所有人之间的书面合同、为推进该工程而取得的建筑许可或其他政府批准,以及登记留置权主张时订约的土地所有人仍持有该地块。若当初未取得许可,则依该章根本不产生留置权。

Civil Code §8302; §8300; §8014

合同与履行

339 道题
1. 根据加州法律,当住宅工程的合同总价(人工和材料合计)达到至少多少时,需要签订家居改善合同?
a.200美元
b.500美元✓
c.1,000美元
d.2,500美元

加州要求对任何住宅工程总计500美元或以上(包括人工和材料)的工作签订书面家居改善合同(B&P §7159)。注意:这个500美元的“书面合同”门槛与§7048的1,000美元“无照小额工程”门槛是两个不同的数字——SB 517在2026年修订了§7159(分包商披露规则),但保留了这个500美元数字,别把两者混淆。

Bus. & Prof. Code §7159
2. 在其家中签订的家居改善合同,房主可以在多少时间内取消?
a.24小时
b.3个工作日✓
c.5个工作日
d.7个日历日

三天撤销权适用于在消费者家中征求和签署的合同。房主可以在第三个工作日午夜之前无罚款取消。

Bus. & Prof. Code §7159(b)
3. 以下哪项必须包含在加州家居改善合同中?
a.图纸与技术规格上的建筑师印章
b.每个分包商及其执照号的清单
c.承包商的名称、营业地址和执照号✓
d.承包商的工伤补偿保险单号

B&P §7159(d)(1)要求家居改善合同载明承包商的名称、营业地址和执照号;(d)款其余部分还要求合同价、工程与主要材料的说明、进度付款时间表以及大致开工与完工日期。法条并未要求执照到期日。它也未要求建筑师印章(属于图纸审查)、分包商名单(留在承包商自己的档案中)或工伤补偿保险单号(由保险人出具的证明载明)。

B&P Code §7159(d)(1)
4. 承包商和房主在项目进行中同意变更工作范围。该协议必须:
a.口头约定,随后在下一张发票上加以确认
b.在变更工作开始前采用书面形式并由双方签署✓
c.在生效之前取得当地建筑部门的批准
d.在其引起价格上涨后10天内向CSLB备案

B&P第7159(d)条要求家居改善合同及其任何变更,在该变更所涵盖的工作开工之前,采用书面形式并由双方签署;第7159(c)(5)条则规定,变更令表格只有在满足这些条件时才成为合同的一部分。事后寄出的发票记录的是一笔账,而不是事先达成的协议。当地建筑部门审查规范符合性并签发许可证,它在使价格变更于业主与承包商之间产生约束力这件事上没有角色。也没有任何条文要求把变更令报送CSLB,无论是10天还是其他期限。

B&P Code §7159(c)(5), (d)
5. 承包商可以在何时向房主要求最终付款?
a.在项目基本完成后✓
b.当工程完成50%时
c.在所有材料送达工地后
d.在项目开始时

承包商不得在项目基本完成之前要求或接受最终付款。在此之前要求付款是违规行为。

Bus. & Prof. Code §7159.5(a)(5)
6. 关于建设合同中的仲裁条款,以下哪项陈述是正确的?
a.在加州是非法的
b.可以包含但必须清晰显著✓
c.所有家居改善合同都需要
d.在所有情况下自动放弃陪审团审判权

仲裁条款是允许的,但必须清楚披露,在家居改善合同中以至少10磅粗体字书写,并由房主单独草签。

Bus. & Prof. Code §7191
7. 承包商在收取大量定金后无故放弃工作。承包商可能面临:
a.仅CSLB的民事罚款,执照本身不受影响
b.仅命令退还定金,此后不会有纪律处分
c.执照被暂停或吊销,并附带刑事指控✓
d.一封警告信并在执照档案中记录一次

无正当理由放弃工程,依B&P第7107条本身即构成纪律处分的事由,因此暂停或吊销执照是现实可能;而为工程收取的定金被挪作他用,可依《刑法典》第484b条以挪用建设资金罪起诉——2,350美元及以下为轻罪,超过该数额处罚更重。只罚款而执照无恙、只退定金、只发警告信,三者都低估了第7107条允许的对执照本身的处分。

B&P Code §7107; Penal Code §484b
8. 谁主要负责在建设项目上获取建筑许可证?
a.业主
b.建筑师
c.当地建筑部门
d.主承包商✓

确保在工作开始前取得所有必要许可证是承包商的职业责任。在没有所需许可证的情况下施工是违规行为。

Bus. & Prof. Code §7090
9. 将承包商控制范围之外的延误责任转移给业主的合同条款称为:
a.不可抗力条款✓
b.违约金条款
c.赔偿条款
d.延误无损害条款

不可抗力条款在超出当事方控制的非常规事件阻止按时完成时,免除当事方的履约义务。

10. 业主在合同中加入了每天500美元的逾期完工违约金条款。该条款可强制执行的条件是:
a.该金额是签约时对可能损失的合理估计✓
b.该金额高到足以阻止承包商逾期完工
c.业主在庭审中证明实际延误损失的确切数额
d.承包商已在该条款处签名并放弃仲裁权

民法典第1671(b)条规定,违约金条款有效,除非质疑方证明该金额在订约时的情形下不合理——因此合理性以签约时为准。把金额定得很高以起阻止或惩罚作用,正是无法通过该检验的典型惩罚性条款。要求证明确切的实际损失,则违背了事先约定违约金的目的。在条款上签名或放弃仲裁与第1671条无关。

Civil Code §1671(b)
11. 承包商向业主提供"业主通知"(初步通知)的主要目的是:
a.告知业主已经记录停付款通知
b.满足该工程所发建筑许可证的条件
c.在未获付款时保留申请留置权的权利✓
d.延长完工后90天的留置权记录期限

民法典第8200条使初步通知成为留置权的前提条件:给了初步通知,未获付款时索款人才可以申请(记录)留置权;不给,无论工程价值多少,留置权都会丧失。它不是付款要求,也不是停付款通知——后者是另一种救济,用于冻结尚未支付的工程款。建筑许可证由建筑部门为符合规范而签发,与初步通知无关。初步通知也不会争取到时间:第8412条规定的完工后90天留置权记录期限,按自己的时间表进行。

Civil Code §8200; §8412
12. 在"时间和材料"(T&M)合同下,业主支付:
a.开工前商定的固定总价,日后不变
b.仅材料成本,人工由承包商自行负担
c.固定时薪,材料费用一律不报销
d.实际人工与材料成本加商定加价✓

“时间和材料”合同按商定费率支付实际发生的人工工时,加上实际材料成本,再加上商定的加价或费用以涵盖管理费与利润;总价事先并不固定。开工前就定死的价格是总价(固定价)合同,恰是相反的安排。只付材料成本描述的是单纯的材料采购,而不是施工合同。固定时薪且不报销材料,则是纯人工或单价安排,材料成本全部由承包商承担。

13. 哪种合同类型对承包商的财务风险最大?
a.成本加固定费用合同
b.固定价格总价合同✓
c.时间和材料合同
d.按单价计价合同

在固定价格(总价)合同下,承包商承诺以一个价格交付完工成果,因此一切超支——人工效率、材料涨价、返工——都落在承包商身上。成本加固定费用合同正好相反:业主实报实销,费用固定,超支由业主承担。时间和材料合同按实际发生的工时和材料开单,成本风险同样留给付款一方。单价合同只固定每单位的单价,工程量风险仍在业主,承包商只承担自己每单位的生产效率风险。

-
14. 分包商未能完成项目中的工作范围。总承包商的主要追索权是:
a.向 CSLB 举报该分包商,等待注册官下令其完成工程
b.另找分包商完成该部分,并向原分包商追偿超出费用✓
c.立即停止全部施工,并视为业主已终止主合同
d.就替补分包商的更高报价向业主申请变更单

分包商违约时,主承包商的合同救济是终止该分包合同、由他人完成该部分工作,并就差额向违约分包商追偿——若其提供了履约保证金,也可向保证人索赔。(a) CSLB 的纪律处分可以中止或吊销分包商执照,但注册官无权下令完成工程,也无法让主承包商获得赔偿;那是法院或仲裁员的职责。(d) 变更单把成本转嫁给业主,而业主既没有造成违约,也没有同意为同一范围付两次钱。(c) 一走了之比无用更糟:无正当法律理由弃工本身就构成 B&P §7107 下的处分事由,主承包商等于用一个追偿请求换来一个执照问题。

Bus. & Prof. Code §7107 (abandonment); §7108.5 (payments to subcontractors)
15. 加州"及时付款"法律要求业主在收到正确发票后多少天内向总承包商付款?
a.7天
b.30天✓
c.45天
d.60天

在私人工程中,业主必须在收到正确无争议发票后30天内向总承包商付款。

Civil Code §8800
16. 在私人工程上,总承包商收到业主支付的进度款。它必须在多少天内向各分包商支付其应得份额?
a.3天
b.7天✓
c.10天
d.30天

B&P §7108.5 给总承包商 7 天时间,自收到进度款起把各分包商的份额转付出去(b);§7108.5(b) 对无故扣留的金额按每月 2% 罚息并加计律师费。(c) 10 天是加州民法典 §8814 另行规定的期限,适用于业主释放留置金后总承包商向分包商放款——那是另一笔款项、另一条法条,这正是本题在题干中指明「进度款」的原因。(a) 3 天和 (d) 30 天在这两条中都不存在;30 天像是私人合同想要写入的条款,但 §7108.5 不能被约定压到那么久。

Bus. & Prof. Code §7108.5
17. 承包商受雇建造一个房间扩建部分。完工后,房主声称存在缺陷。承包商对新住宅建筑的书面保修期至少必须为:
a.90天
b.1年✓
c.2年
d.承包商可自由设定期限

加州《修复权法》(SB 800)规定:大多数组件1年,管道/电气/机械4年,结构缺陷10年。

Civil Code §896
18. 在一份40,000美元的家居改善合同中,承包商在工作开始前合法可以要求或接受的最高首付款是多少?
a.4,000美元(合同的10%)
b.2,000美元(合同的5%)
c.1,000美元✓
d.10,000美元(合同的25%)

加州将家居改善合同的首付款限制为1,000美元或合同价格的10%,以较低者为准。此处10%为4,000美元,因此较低的1,000美元上限适用。

Bus. & Prof. Code §7159.5
19. 在一份6,000美元的家居改善合同中,允许的最高首付款是多少?
a.600美元✓
b.1,000美元
c.1,500美元
d.3,000美元

首付款不得超过1,000美元或合同价格的10%,以较低者为准。6,000美元的10%是600美元,低于1,000美元,因此600美元是合法上限。

Bus. & Prof. Code §7159.5
20. 以下哪项不是加州家居改善合同的必备要素?
a.大致的开工日期和完工日期
b.与已完成工作挂钩的付款时间表
c.房主的家庭年收入✓
d.将要执行的工作描述

家居改善合同必须载明工作描述、付款时间表以及开工/完工日期等内容。房主的收入属于私人财务信息,从来不是必备合同条款。

Bus. & Prof. Code §7159
反馈