浏览所有题目

这些题目考的数字,按章节排在可打印的彩色高密度页面上: 速记册,$9.99 →

拥有完整的 CSLB Law & Business 学习指南 —— PDF + EPUB,$24.99 →

查看每道题的答案和解析——可按主题或全部一起学习。

保险与留置权

198 道题
151. On a private work of improvement where a valid payment bond has been recorded, an unpaid subcontractor may:
a.Pursue the bond only, the lien right having been given up
b.Recover twice the amount owed, from bond and lien alike
c.Pursue the surety and, where available, a mechanics lien✓
d.Lien the property only, because the bond runs to the owner

A private-work payment bond adds a surety to pursue; it does not by itself extinguish lien rights, and a claimant may hold both remedies while recovering the debt only once. The real qualification is Civil Code §8600: where the owner in good faith files the direct contract with the county recorder and records a payment bond of at least 50 percent of the contract price before work commences, the court shall, where equitable, restrict lien enforcement to the bond. (a) states that outcome as though it were automatic, which it is not. (b) is double recovery, which no remedy permits. (d) misreads who may claim on the bond: §8608 gives the right to claimants who provided work to the direct contractor, directly or through subcontractors.

Civ. Code §8600 / §8608
152. A notice of cessation was recorded after a 30-day work stoppage. This recording affects lien deadlines by:
a.Triggering 30 days for other claimants and 60 days for the direct contractor✓
b.Triggering 60 days for other claimants and 90 days for the direct contractor
c.Leaving every claimant with 90 days from actual completion of the work
d.Extending each claimant's deadline to one year from the recording date

A recorded notice of cessation has the same effect as a notice of completion: Civil Code §8414 cuts claimants other than the direct contractor to 30 days after recording, and §8412 gives the direct contractor 60 days. (b) swaps the two figures, and reversing them is the most common error on this pair. (c) is the rule when nothing is recorded — 90 days after completion for everyone — and is exactly what the recording is meant to shorten. (d) confuses this with the §8460 outer limit for bringing a foreclosure action after a lien is recorded.

Civil Code §8412 / §8414
153. 'Completed operations' coverage under a CGL policy is important to contractors because it covers:
a.Injury to the contractor's own employees while finishing the work
b.The contractor's lost income when a completed project is shut down
c.Third-party injury or damage arising from work already turned over✓
d.The cost of repairing the contractor's own defective workmanship

Completed operations responds to bodily injury and property damage arising out of the contractor's work after that work is finished and turned over — the coverage that answers latent defects surfacing years later. (a) is workers' compensation and employers' liability, a different policy entirely. (b) is business income coverage, a first-party time-element loss. (d) is the hardest distractor and the most valuable to get right: the CGL's business-risk exclusions generally leave the cost of repairing your own faulty work uninsured, even though the resulting damage to other property may be covered.

154. A sole-owner contractor holding only a Class B license, with no employees, wants to avoid carrying workers' compensation. Under B&P §7125 as it reads until January 1, 2028, the contractor may:
a.Avoid it only as a joint venture under §7029 that has no employees
b.File the no-employee exemption statement with the Registrar✓
c.Avoid it only by adding a C-39 roofing classification
d.Avoid it by paying every worker on a 1099 instead of on payroll

Until January 1, 2028, B&P §7125(b) as amended by SB 1455 (Stats. 2024, ch. 485) lets a licensee with no employees skip the policy by filing a statement, on the Registrar's form, certifying that it employs no one subject to the workers' compensation laws — provided it holds no C-8, C-20, C-22, C-39 or D-49 classification. A Class B sole owner with no employees qualifies (b). (a) is the rule SB 216 wrote: from January 1, 2028 only a §7029 joint venture with no employees will be exempt and this sole owner will have to carry coverage. SB 1455 moved that date from 2026, so material that calls it current is out of date. (c) inverts the list: adding a C-39 roofing classification is exactly what takes the exemption away. (d) is misclassification, not exemption: Labor Code §2750.5 presumes a worker performing licensable work is an employee, and paying on a 1099 changes the paperwork rather than the status.

Bus. & Prof. Code §7125(b) (as amended by SB 1455, Stats. 2024, ch. 485); §7029; Lab. Code §2750.5
155. To keep a mechanics lien alive beyond 90 days without immediately filing suit, a claimant and owner may agree to and record an:
a.Assignment of the lien to the construction lender holding the loan
b.Extension of credit, extending time to sue up to a year✓
c.Amendment increasing the lien to include interest accruing meanwhile
d.Acknowledgement of debt, which restarts the 90 days from signing

Civil Code §8460 requires an action to enforce a lien within 90 days after recording, unless a notice of credit is recorded extending the time — and in no event may the action be brought more than one year after recording. (a) transfers the claim without touching the deadline; an assignee inherits the same clock. (c) confuses the amount with the time limit, and inflating a lien invites the §8422 overstatement problem. (d) imports a debt-acknowledgement rule from the statute of limitations, which does not restart the mechanics lien deadline.

Civil Code §8460
156. Which best explains why a general contractor requires each subcontractor to carry its OWN workers' compensation insurance?
a.Because a subcontractor cannot hold a CSLB license without coverage
b.Because the sub's employees are covered by its own policy✓
c.Because the general contractor's policy excludes construction work
d.Because the mechanics lien statute conditions lien rights on coverage

If a subcontractor has no workers' compensation coverage, its injured workers can be treated as employees of the hiring contractor, whose own policy then pays and whose experience rating carries the loss. Requiring each sub to insure its own people keeps that exposure where it belongs. (a) overstates the licensing rule: under B&P §7125(b) a licensee with no employees may still file an exemption unless it holds one of the excluded classifications. (c) is false — a contractor's policy covers its own construction employees. (d) mixes workers' compensation with the lien statute, which says nothing about it.

Labor Code §2750.5 / §3600
157. The 125% bond required to accompany a stop payment notice served on a construction LENDER exists to:
a.Satisfy the surety requirement that CSLB imposes on every licensee
b.Protect the lender's costs if the withheld claim proves invalid✓
c.Guarantee the claimant's recovery if the borrower later defaults
d.Substitute for the preliminary notice the claimant failed to serve

Civil Code §8532 makes the bond the price of forcing a lender, a stranger to the dispute, to freeze loan funds: if the claim turns out to be bad, the bond answers the lender's resulting damages and costs. (a) confuses it with the §7071.6 license bond, which is a licensing condition unrelated to any project. (c) reverses the beneficiary — the bond protects the lender against the claimant, not the claimant against the borrower. (d) is the misconception that a bond can cure a missed notice; it cannot, and a claimant who never noticed the lender has nothing to serve.

Civil Code §8532
158. Which of the following parties is typically the OBLIGEE on a contractor's performance bond for a private project?
a.The subcontractor
b.The material supplier
c.The surety company
d.The project owner✓

On a performance bond, the obligee is the party protected by the guarantee of completion — typically the project owner. The contractor is the principal and the bonding company is the surety. Subs and suppliers are protected instead by the payment bond.

159. The recorded mechanics lien must be served on the owner within what time relative to recording, along with the Notice of Mechanics Lien?
a.At or shortly after recording, with a proof of service affidavit✓
b.Within twenty days before recording, mirroring the preliminary notice
c.Within ninety days after recording, when the foreclosure action is filed
d.At any time before trial, since service is a matter of proof

Civil Code §8416 requires the claimant to serve the owner or reputed owner with a copy of the lien and the statutory Notice of Mechanics Lien, and to record a proof of service affidavit with the lien; failure makes the lien unenforceable. (b) borrows the 20-day preliminary notice rule, which is a different notice served before the lien exists. (c) conflates service with the §8460 deadline for filing suit. (d) treats a recording condition as an evidentiary detail, which is precisely the mistake §8416 was written to punish.

Civil Code §8416
160. A hold-harmless clause where a subcontractor agrees to indemnify the general contractor even for the GC's OWN active negligence is:
a.Limited by the California anti-indemnity construction statutes✓
b.Enforceable only on residential work, and void on commercial projects
c.Fully enforceable, provided the subcontract states the intent clearly
d.Unnecessary, because an additional insured endorsement does the same

Civil Code §2782 voids a construction contract clause purporting to indemnify a party for its own sole negligence or willful misconduct, and §2782.05 further restricts indemnity by subcontractors for the active negligence of the general contractor. (b) inverts the statutes, which reach residential work rather than exempting it. (c) is the pre-statute common-law position, which clear drafting no longer rescues. (d) is a real and important distinction stated as an equivalence — additional insured coverage is subject to policy terms and limits, and does not do the work of an indemnity clause.

Civil Code §2782 / §2782.05
161. Civil Code §2782 generally makes VOID a construction contract provision requiring one party to indemnify another for that other party's:
a.Failure to get the required building permit
b.Delay in completing the work as scheduled
c.Sole negligence or willful misconduct✓
d.Failure to pay its own subcontractors

Civil Code §2782(a) makes void and unenforceable, as against public policy, a construction contract provision purporting to indemnify the promisee against liability for death or bodily injury, injury to property, or any other loss arising from the promisee's own sole negligence or willful misconduct, or from defects in design furnished by the promisee. §2782.05 goes further inside subcontracts, voiding a subcontractor's indemnity of the general contractor for the general contractor's active negligence, subject to the exceptions the section lists. (a), (b) and (d) are ordinary commercial risks that parties remain free to allocate by contract — which is why the item turns on fault, not on inconvenience.

Civ. Code §2782(a) / §2782.05
162. A subcontract requires 'primary and noncontributory' coverage when the sub names the GC as additional insured. That means the sub's policy should:
a.Not respond to the general contractor's own claims at all
b.Pay first, without contribution from the GC's policy✓
c.Pay only after the GC's own policy has been fully exhausted
d.Cover the sub's employees for their own injuries

Primary and noncontributory means the subcontractor's policy answers first for claims arising out of the subcontractor's work, and does not ask the additional insured's own insurer to share the loss — which is what makes the risk transfer real rather than nominal. (c) is the excess or umbrella position, the exact inverse of what the requirement buys. (a) describes where the general contractor stands with no additional insured endorsement at all. (d) is workers' compensation, a coverage no liability endorsement supplies.

—
163. On a private project with no notice of completion or cessation recorded and the work simply finished, ALL claimants (direct contractor, subs, and suppliers alike) have how long to record a lien?
a.30 days from completion
b.60 days from completion
c.One year from completion
d.90 days from completion✓

When no notice of completion or cessation is recorded, Civil Code §8412 and §8414 give every claimant 90 days after actual completion to record a mechanics lien. The 30/60-day distinctions apply only once such a notice is recorded.

Civ. Code §8412
164. Why might an owner prefer that the general contractor obtain a payment bond rather than rely solely on the contractor to pay subs?
a.Unpaid subs can claim on the surety instead of liening the property✓
b.The surety takes over and completes the work if the contractor defaults
c.The bond premium is refunded to the owner when the project closes
d.The bond releases the owner from retention obligations on the contract

A payment bond gives unpaid subcontractors and suppliers a solvent source other than the owner's real property, which reduces the owner's exposure to liens and to paying twice for the same work. (b) describes the performance bond, which answers non-completion — the two bonds are issued together and protect against different failures. (c) misunderstands surety pricing: the premium is earned, and in any case it is a cost the contractor carries into the contract price. (d) is unrelated, since retention is governed by the contract and by Civil Code §8811.

Civil Code §8600 et seq.
165. 'Inland marine' insurance for a contractor most commonly covers:
a.The finished building against fire once the owner takes occupancy
b.Injury to employees using the contractor's tools on the jobsite
c.Bodily injury to members of the public visiting the jobsite
d.Tools, equipment, and materials in transit or at the jobsite✓

Contractor's inland marine — the equipment floater and installation floater — covers movable property while it travels and while it sits at a jobsite, which ordinary fixed-location property policies will not follow. (a) is the owner's permanent property insurance, which takes over where builder's risk ends. (b) is workers' compensation; the tools are incidental to who was hurt. (c) is commercial general liability. The common thread among the wrong answers is that each is a real policy a contractor carries, which is what makes placing the loss the skill being tested.

166. An equipment rental company rents a crane to a subcontractor on a private project. To preserve a mechanics lien for unpaid rent, it should:
a.Do nothing at all, because an equipment lessor's lien is automatic
b.Serve a notice on the subcontractor that rented the crane
c.Serve a preliminary notice on owner, contractor, and lender✓
d.Record a claim of lien before the crane is delivered

Civil Code §8400(d) gives an equipment lessor a lien right, but §8410 makes enforcement depend on having given the preliminary notice, and §8200 sends that notice to the owner, the direct contractor, and the construction lender, no later than 20 days after first furnishing under §8204(a). (a) is the automatic-lien belief: the right exists and is unenforceable without the notice. (b) serves only the party upstream, which is the most common fatal error — the lessor has no contract with the owner, so the owner is exactly who must be told. (d) records too early: §8414 allows the claim of lien only after the claimant ceases to provide work, and before the earlier of 90 days after completion or 30 days after a recorded notice of completion.

Civ. Code §8400(d) / §8410 / §8204(a)
167. The primary function of a 'certificate of insurance' in the contracting process is to allow one party to:
a.Become an insured under the other party's liability policy
b.Require the insurer to notify it before the policy is cancelled
c.Verify the other party's required coverage types and limits✓
d.Shift its own insurance obligation onto the other party's insurer

A certificate is a verification document: it lets a hiring party confirm, before work starts, that the other side carries the coverages and limits the contract demands. (a) requires an additional insured endorsement, and the certificate only reports one if it exists. (b) reads the cancellation-notice box as an enforceable promise, when most modern forms expressly disclaim it. (d) describes what the underlying insurance requirement and indemnity clause are meant to accomplish — the certificate merely evidences that the machinery is in place.

168. Under California's workers' compensation system, an employee injured on the job generally receives benefits:
a.On a no-fault basis, as the exclusive remedy against the employer✓
b.Only after a court apportions fault between employer and employee
c.Only where the employer's negligence caused the injury at work
d.Only where the employee bore no share of the fault involved

Labor Code §3600 provides benefits without regard to fault for injuries arising out of and in the course of employment, and §3602 makes those benefits the employee's exclusive remedy against the employer — the bargain at the centre of the system. (b) and (c) describe the tort regime workers' compensation replaced, where the worker had to prove negligence and litigate fault. (d) imports contributory negligence, which is exactly what the no-fault rule abolishes; an employee's ordinary carelessness does not forfeit benefits.

Labor Code §3600 / §3602
169. A contractor's umbrella or excess liability policy is designed to:
a.Take the place of the workers' compensation policy entirely
b.Add limits above the underlying policies once exhausted✓
c.Act as the primary policy for every kind of claim
d.Cover only the contractor's own defective work

An umbrella or excess policy sits above scheduled underlying policies — commercial general liability, commercial auto, often employers' liability — and pays only after those limits are exhausted, which is how a contractor reaches catastrophic-claim limits without buying them at the primary layer. (c) inverts that structure. (a) confuses liability limits with workers' compensation, which is statutory, separate, and not something an umbrella replaces. (d) names the risk the CGL's 'your work' exclusion leaves with the contractor, and an umbrella follows the underlying policy's terms rather than curing its exclusions.

—
170. Which of these must a valid recorded mechanics lien contain?
a.The claimant's demand, after just credits and offsets✓
b.A copy of the claimant's workers' compensation certificate
c.The owner's construction loan and account numbers
d.The claimant's profit margin on the contract

Civil Code §8416(a) requires a written statement, signed and verified by the claimant, containing the claimant's demand after deducting all just credits and offsets, the name of the owner or reputed owner if known, a general statement of the kind of work furnished, the name of the person who employed the claimant, a description of the site sufficient for identification, the claimant's address, and a proof of service affidavit; the statutory Notice of Mechanics Lien must be served with it. §8422 forgives erroneous information about the demand, the credits, the work, or the site unless the court finds the claimant intended to defraud, or a party without actual knowledge was misled to its prejudice. The other three answers are records no lien requires and that do nothing to identify the claim.

Civ. Code §8416(a) / §8422
171. A subcontractor who is added as additional insured on NO ONE's policy and carries its own CGL is protected for third-party claims:
a.Not at all, since protection depends on the prime contractor's policy
b.Only for injuries to its own employees, through workers' compensation
c.Only to the extent the general contractor's policy chooses to respond
d.By its own CGL policy, subject to its terms and limits✓

A contractor's own commercial general liability policy insures it against covered third-party bodily injury and property damage arising from its operations, whether or not anyone has named it on another policy. (a) and (c) reverse the direction of additional insured coverage — that status usually runs upward, giving the owner and prime access to the sub's insurer, not the other way round. (b) confuses the two coverages: workers' compensation answers injuries to the contractor's own employees, and third parties are not employees.

172. The construction lender must be served with a preliminary notice by a claimant lacking an owner contract primarily so the claimant can later:
a.Serve a bonded stop payment notice for undisbursed funds✓
b.Record a mechanics lien senior to the lender's deed of trust
c.Compel the lender to release the remaining loan to the owner
d.Claim on the lender's own errors and omissions coverage

Notice to the lender is what keeps the fund-based remedy alive: a bonded stop payment notice under §8532 obliges the lender to withhold loan money it has not yet disbursed. (b) is the closest trap because lien priority is a real and valuable question, but priority turns on when work commenced relative to recording of the deed of trust, not on whom the preliminary notice went to. (c) reverses the point of the notice, which is to stop money rather than release it. (d) invents a claim against the lender's own insurance.

Civil Code §8200 / §8532
173. On a public works project, subcontractors generally CANNOT record a mechanics lien against the public property. Their principal payment security instead is the:
a.Notice of non-responsibility recorded by the public entity's agent
b.Builder's risk policy the public entity carries on the improvement
c.Payment bond, plus a stop payment notice against public funds✓
d.Performance bond posted by the direct contractor at award

Public property cannot be sold to satisfy a private claim, so the legislature substituted two remedies: the direct contractor's payment bond and a stop payment notice served on the public entity against funds still unpaid. (d) is the sharpest distractor, because both bonds are posted on the same job — but the performance bond answers to the public entity for completion, and a sub is not its beneficiary. (a) concerns work ordered by someone other than the owner. (b) is first-party property insurance on the work itself and pays no one for unpaid labour or materials.

Civil Code §9100 et seq. / §9350 et seq.
174. After an owner records a lien release bond of 125%, an unpaid subcontractor who wants to be paid must now pursue:
a.The CSLB, which holds the contractor's licence bond for claimants
b.The surety on the release bond, and the bond's principal✓
c.The construction lender, whose loan funded the improvement work
d.The real property, by foreclosing the lien the bond replaced

Recording a release bond under Civil Code §8424 substitutes the bond for the property, so the claimant's action runs against the surety and the principal rather than against title. (d) is the step the bond was recorded to foreclose, and pursuing it is the error the section exists to prevent. (a) misroutes a claim: the §7071.6 licence bond is claimed against its surety, and the CSLB holds no money. (c) reaches the wrong party — funds in the lender's hands are the target of a bonded stop payment notice, a separate remedy with its own notice conditions.

Civil Code §8424
175. 'Employers' liability' coverage, usually part of a workers' compensation policy, protects the employer against:
a.Statutory benefits owed to an employee injured at work
b.Employee-injury suits outside the exclusive remedy rule✓
c.Bodily injury to the public caused by the employer's work
d.Wage claims brought by employees for unpaid overtime hours

Coverage B of a workers' compensation policy answers employee-injury liability that the no-fault benefit system does not resolve — third-party-over actions, consequential claims by family members, and dual-capacity claims. (a) is Coverage A of the same policy, the statutory benefits themselves, and mistaking the two is the whole point of the item. (c) is commercial general liability, which excludes injury to employees precisely because this coverage handles it. (d) is a wage claim, which is neither an injury nor insured under a workers' compensation policy.

Labor Code §3600 / §3602
176. A direct contractor completed a private remodel on March 1. No notice of completion was ever recorded and the owner never occupied. The contractor's last day to record a mechanics lien is approximately:
a.March 11 (10 days)
b.March 31 (30 days)
c.May 30 (90 days)✓
d.April 30 (60 days)

With no notice of completion or cessation recorded, Civil Code §8412 gives the direct contractor 90 days from completion to record. Counting 90 days from March 1 lands near the end of May.

Civ. Code §8412
177. Requiring a subcontractor to provide a certificate of insurance BEFORE it starts work is a best practice primarily because it:
a.Makes the general contractor a policyholder from the first work day
b.Prevents the insurer from cancelling the policy during the project
c.Extends the general contractor's own coverage over the sub's work
d.Confirms the required coverage is in force before work starts✓

Checking the certificate before the sub mobilizes verifies that the required coverage exists at the moment exposure begins, when it is still possible to keep an uninsured sub off the site. (a) confuses receiving a document with buying a policy. (b) reads the certificate as controlling the insurer, which it does not — cancellation rights live in the policy. (c) reverses the transfer: the purpose is to reach the sub's insurer for the sub's work, not to spend the general contractor's own limits on it.

178. Which best describes the difference between the payment bond and the performance bond on the SAME project?
a.The payment bond guarantees the schedule; the performance bond the budget
b.The payment bond protects subs from nonpayment; the performance bond protects the owner✓
c.The payment bond protects the owner from liens; the performance bond protects the surety
d.The payment bond pays the contractor; the performance bond pays the subcontractors

The two bonds are issued together and answer different failures: the payment bond guarantees that subcontractors and suppliers are paid, and the performance bond guarantees to the owner that the work is completed according to the contract. (a) invents schedule and budget guarantees neither bond gives. (c) is half-right and therefore the strongest distractor — reduced lien exposure is a real benefit to the owner, but it is a consequence of subs being paid, and no bond exists to protect the surety. (d) reverses both beneficiaries.

Civil Code §8600 et seq.
179. A mechanics lien recorded on a private project must describe the property with:
a.The contractor's license number and classification
b.The project's estimated fair market value today
c.A description of the site sufficient to identify it✓
d.The owner's mailing address and telephone number

Civil Code §8416(a)(5) requires a description of the site sufficient for identification; a street address usually does, and a legal description removes all doubt. §8422 then forgives an erroneous site description unless the court finds the claimant intended to defraud, or that a party without actual knowledge of the mistake was misled to its prejudice. (a) and (b) appear nowhere in the section. (d) is close enough to be tempting — §8416(a)(2) requires the owner's name if known and (a)(6) requires the CLAIMANT's address — but the owner's mailing address and phone number are not what identifies the property.

Civ. Code §8416(a)(5) / §8422
180. 'Additional insured' status is most valuable to an upstream party (like an owner or GC) because it:
a.Releases the upstream party from carrying its own liability coverage
b.Lowers the downstream party's premium by spreading the same risk
c.Guarantees that the downstream party will complete its scope of work
d.Gives access to the sub's insurer for defense and indemnity✓

An additional insured endorsement lets the owner or general contractor tender a claim arising out of the subcontractor's work to the subcontractor's insurer and obtain a defense and indemnity under that policy, subject to its terms and limits. (a) is the dangerous reading: risk transfer supplements your own coverage and never excuses it. (b) confuses insurance with cost allocation — adding insureds does not reduce the premium. (c) describes a performance bond, which is a surety obligation rather than an insurance one.

181. An architect provided design services for a private work of improvement, authorized by the owner. The architect:
a.Never has lien rights, in any circumstances
b.May give a stop payment notice, but never a lien
c.Must carry builder's risk insurance instead
d.May have lien rights for those services✓

Civil Code §8400(f) lists the design professional among the persons with a mechanics lien right for work provided to a work of improvement, subject to the same preliminary notice condition in §8410 and the recording deadlines in §8412 and §8414. California also gives design professionals a separate remedy in §8300 et seq. for design services furnished before construction starts, which §8302(c) allows only where a building permit or other governmental approval has been obtained using those services. (a) ignores both routes. (b) reverses the remedies, and a design professional's stop payment notice rights are expressly preserved in §8608(b). (c) confuses property insurance with a payment remedy.

Civ. Code §8400(f) / §8302(c)
182. An owner wants to be an additional insured on the contractor's policy. For the owner actually to have that status, the certificate must be accompanied by:
a.A recorded copy of the claimant's mechanics lien
b.A recent statement from the contractor's own bank
c.An additional insured endorsement to the policy✓
d.A thirty-day notice of cancellation clause

Only the insurer can add an insured to a policy, and it does so by endorsement; a certificate is a broker's evidence of coverage and its own wording disclaims amending the policy. (d) is the substitute owners most often settle for — a notice provision tells the owner when coverage is ending, it does not make the owner an insured or give it a right to defense. (a) and (b) belong to other transactions entirely, one in the lien law and the other in a credit file.

—
183. A stop payment notice, unlike a mechanics lien, does NOT need to be:
a.Supported by a valid claim
b.Given by someone who furnished work
c.Served on the correct party
d.Recorded with the county recorder✓

A stop payment notice is served, not recorded; it directs the owner or lender to withhold funds. A mechanics lien, by contrast, is recorded against the property. Both require a valid underlying claim by someone who furnished work and proper service.

Civ. Code §8500
184. A contractor pays day laborers in cash, calls them independent contractors, and carries no workers' compensation. A laborer is injured. The contractor most likely:
a.Owes the CSLB an administrative fine and nothing more
b.Has no exposure at all, the laborers being independent
c.Is liable as an uninsured employer for the injury✓
d.Is covered by the general liability policy instead

Labor Code §2775(b)(1) treats a worker as an employee unless the hiring entity proves all three parts of the ABC test, and §2781 sets the narrower conditions for construction subcontractors; the label on the paperwork settles nothing. An employer that owed coverage and had none faces the civil action §3706 allows, in which §3708 presumes the injury was caused by the employer's negligence and removes the usual defenses, plus §3700.5 misdemeanor exposure and suspension of the license under B&P §7125.2. (a) understates the exposure by orders of magnitude. (b) is the label-as-conclusion error the ABC test forecloses. (d) misreads the commercial general liability policy, which excludes bodily injury to the insured's own employees precisely because workers' compensation answers it.

Lab. Code §2775(b)(1) / §2781 / §3706 / §3708
185. A supplier first delivered materials on Day 1 but served its preliminary notice on Day 40. For which materials may it claim?
a.Only for the materials delivered after the 60th day of work
b.For nothing at all, the notice being fatally late
c.For every delivery, back to the very first one
d.For deliveries from about Day 20 forward, but not before✓

Civil Code §8204(a) provides that a claimant who did not give preliminary notice is not precluded from giving one later, but is then entitled to claim only for work performed within the 20 days prior to service of the notice, and at any time thereafter. Service on Day 40 therefore protects deliveries from roughly Day 20 forward, and the deliveries from Day 1 to Day 19 fall outside the window. (b) treats a late notice as fatal, which the subdivision expressly says it is not. (c) ignores the look-back altogether. (a) counts 20 days forward from service instead of backward, which protects nothing the statute protects.

Civ. Code §8204(a)
186. Which of the following is generally the LAST resort remedy because it requires foreclosing on real property?
a.Certificate of insurance
b.Mechanics lien✓
c.Stop payment notice
d.Payment bond claim

A mechanics lien ultimately requires a foreclosure action against the owner's real property to collect, making it more cumbersome than a stop payment notice (reaching funds) or a payment bond claim (reaching a surety). Claimants often pursue funds or bonds first.

187. On a project where a notice of completion is recorded, missing the 30-day lien deadline (for a non-direct claimant) generally means:
a.The claimant may still record within 60 days, as the direct contractor may
b.The claimant loses the mechanics lien, but other remedies may survive✓
c.The claimant may record within 90 days from actual completion instead
d.The claimant has 90 days from recording to file suit on the lien

Civil Code §8414 gives a claimant other than the direct contractor 30 days after a recorded notice of completion; miss it and the lien remedy is gone, though a payment bond claim, a timely stop payment notice, or a plain breach-of-contract action may remain. (a) borrows the direct contractor's 60-day period under §8412, which is not available to lower-tier claimants. (c) is the no-notice rule the recording displaced. (d) states the §8460 deadline for suing on a lien already recorded, which never revives a lien that was recorded too late.

Civil Code §8414 / §8460
188. A general contractor's CGL policy typically will NOT respond to which claim?
a.The contractor's crane damaging the neighboring building
b.A visitor tripping on debris and breaking an arm
c.A pedestrian struck by material falling from the frame
d.The contractor's own employee injured while framing✓

A commercial general liability policy excludes bodily injury to an employee arising out of employment, because that injury belongs to workers' compensation, with Coverage B employers' liability picking up the suits the no-fault system does not resolve. (a), (b) and (c) are exactly what the CGL is bought for: third-party bodily injury and property damage arising out of the contractor's operations. The line is who was hurt, not how badly or where — an employee framing the same wall as the injured visitor produces a workers' compensation claim, not a CGL claim.

—
189. A claim on a private-project payment bond generally requires the claimant to have:
a.Posted a bond of 125 percent of the claim before making it
b.Given the preliminary notice lien rights require, unless excused✓
c.Recorded a mechanics lien against the property before claiming
d.Obtained a judgment against the direct contractor before claiming

Under Civil Code §8600 et seq. the right to recover on a private-work payment bond tracks the notice conditions for a mechanics lien, so a claimant who had to give a preliminary notice must have given it — laborers and others excused from notice are excused here too. (a) imports the §8532 bond that accompanies a stop payment notice to a lender. (c) treats the remedies as sequential when they are alternative; a claimant may go against the bond without ever recording. (d) would make the bond useless, since its value is being payable without first litigating to judgment.

Civil Code §8600 et seq.
190. The most accurate reason insurance and surety bonds are BOTH used on construction projects is that they:
a.Are both two-party transfers, so carrying both doubles available limits
b.Both let the provider absorb the loss without seeking reimbursement
c.Both protect the contractor against claims made by the project owner
d.Address different risks: insurance covers loss, bonds guarantee duties✓

Insurance transfers the insured's own fortuitous losses to an insurer that does not expect repayment; a bond is a three-party guarantee running to an obligee, and the surety expects the principal to reimburse what it pays. Projects carry both because the risks do not overlap. (a) and (b) each describe insurance and then attach the label to both instruments. (c) mistakes who a bond protects — the owner is typically the obligee the bond runs to, so the bond protects the owner from the contractor, not the reverse.

191. A lien claimant who has been paid in full but refuses to release a recorded mechanics lien may be liable to the owner for:
a.Nothing, since a satisfied lien expires on its own schedule
b.Three times the value of the project, as a penalty
c.The owner's costs and attorney's fees to remove the lien✓
d.The contractor's lost profit on the delayed property sale

A claimant that has been paid should execute and record a release, and an unreleased lien clouds the owner's title until it does. The owner's statutory remedy is the petition in Civil Code §8480: once the claimant has let the 90 days in §8460 pass without commencing an action to enforce the lien, the owner may petition for an order releasing the property, the claimant carries the burden of proving the lien's validity under §8488(a), and §8488(c) awards the prevailing party reasonable attorney's fees. §8494 then strips an expired lien of any effect as notice. (a) ignores the practical problem the statute addresses, since the cloud on title bites long before anything expires. (b) invents a treble-damages penalty this remedy does not carry. (d) names the wrong party's loss: the harm runs to the owner whose title is clouded, not to the contractor.

Civil Code §8480 / §8488(c) / §8494
192. The $25,000 figure most commonly associated with California contractor licensing is:
a.The largest mechanics lien the statute allows
b.The project size that requires a payment bond
c.The contractor's license bond amount✓
d.The builder's risk limit the CSLB sets

$25,000 is the contractor's bond every active licensee must keep on file under B&P §7071.6 — and the same figure is the minimum disciplinary bond under §7071.8 and the amount of the qualifying individual's bond under §7071.9. (b) is the real neighbor and the reason this item is worth asking: Civil Code §9550(a) requires a payment bond on a public works contract involving an expenditure in excess of $25,000, the identical number doing an unrelated job. (a) invents a statutory cap on liens; a lien is in the amount of the claimant's demand. (d) invents a CSLB insurance requirement — the only insurance the license law compels is workers' compensation under §7125, plus the limited liability company's liability policy under §7071.19.

B&P Code §7071.6 / Civ. Code §9550(a)
193. SB 1455 (Stats. 2024, ch. 485) moved the date on which B&P §7125 requires every licensee, with or without employees, to carry workers' compensation. From what date does that requirement apply?
a.January 1, 2026
b.January 1, 2028✓
c.January 1, 2027
d.July 1, 2026

SB 216 (Stats. 2022, ch. 978) wrote a version of §7125 that requires every licensee to carry workers' compensation or self-insurance whatever its classification, leaving only a §7029 joint venture with no employees exempt, and set it to start on January 1, 2026. SB 1455 (Stats. 2024, ch. 485) rewrote that start date: the new section "shall become operative on January 1, 2028" (b), and the interim §7125 — a no-employee exemption available to everyone except C-8, C-20, C-22, C-39 and D-49 holders — stays in effect until then. (a) is the original SB 216 date, which is why so much study material still states the all-licensee rule as current. (c) is a real date in the same bill, but for something else: by January 1, 2027 §7125.7 requires the board to establish a process to verify that licensees claiming the no-employee exemption are eligible. (d) is not a date either bill uses.

Bus. & Prof. Code §7125 (Stats. 2024, ch. 485, SEC. 12–13); §7125.7
194. Until January 1, 2028, which of these licensees, working alone with no employees, may file the exemption from workers' compensation instead of carrying a policy?
a.A C-39 roofing contractor
b.A C-8 concrete contractor
c.A C-33 painting contractor✓
d.A D-49 tree service contractor

Until January 1, 2028, B&P §7125(b), as amended by SB 1455 (Stats. 2024, ch. 485), exempts an applicant or licensee that has no employees and files the Registrar's exemption statement — but only if it does not hold a C-8 (concrete), C-20 (warm-air heating, ventilating and air-conditioning), C-22 (asbestos abatement), C-39 (roofing) or D-49 (tree service) license. A C-33 painter is not on that list, so (c) may file. (a), (b) and (d) are on it: those holders must carry workers' compensation or a certification of self-insurance whether or not they employ anyone, and CSLB will not accept an exemption from them. From January 1, 2028 the list stops mattering, because the SB 216 version of §7125 requires every licensee to carry coverage except a §7029 joint venture with no employees — the painter included.

Bus. & Prof. Code §7125(b) (as amended by SB 1455, Stats. 2024, ch. 485)
195. 某承包商被查出雇用六名工人却没有工伤保险,因而收到停工令。其后,六人中的一人被认定在无保险期间发生了应予赔付的工伤。《劳工法》第 3722 条授权征收哪些罚款?
a.随停工令每名雇员 1,500 美元;应予赔付后每人再加 10,000 美元✓
b.随停工令按每名雇员 1,500 美元;工伤即使被认定应予赔付也不再另行加罚
c.随停工令按每名雇员 10,000 美元;对应予赔付的工伤再按每人 1,500 美元
d.只征收一笔 100,000 美元的固定罚款,这是第 3722 条唯一授权的数额

第 3722 条在两个不同的触发点上分两次征收。第 (a) 款随停工令一并作出,发生在任何人受伤之前,按签发并送达停工令时在雇人数每人 1,500 美元计。随后,第 (d)(2) 款在工伤被认定应予赔付时,按受伤之日在雇人数每人再加 10,000 美元。第 (f) 款的 100,000 美元是这些罚款「总额的上限」,本身不是一项罚款;而第 3700.5 条的刑事责任还叠加在这一切之上。

Labor Code §3722(a), (d)(2), (f)
196. 一名木工因自己粗心搭设的脚手架跳板断裂而受伤。其雇主投有工伤保险。他现在想以工地维护存在过失为由起诉该雇主。法律上会怎样处理?
a.不予赔付,因为伤是他自己造成的,所以只能走过失侵权诉讼这条路
b.既不予赔付也不能起诉,因为工伤赔偿是唯一救济途径
c.予以赔付,同时他也可以起诉雇主,因为工地本身确实不安全
d.尽管他本人有疏忽仍予赔付,而该赔偿请求是他对雇主的唯一救济✓

这是同一笔交易的两个半边。第 3600(a) 条规定雇主的赔偿责任「不问过失」,因此受伤工人即便部分甚至全部出于自身疏忽,仍可获得赔付。第 3602(a) 条则是这笔交易的对价:工伤赔偿请求是针对雇主的「唯一且排他」的救济,因此那起过失诉讼不能成立。狭窄的例外规定在别处——雇主故意殴打、欺诈性隐瞒伤情、雇主自制并出售的缺陷产品,或者雇主根本未投保。

Labor Code §3600(a); §3602(a)
197. 一名工人周一割伤手部需要缝合,周三递交了 DWC-1 索赔表。保险公司尚未接受或拒绝该索赔。雇主此时必须做什么,其责任到什么程度为止?
a.等保险公司作出决定,索赔待决期间无需授权任何治疗
b.须在周四前授权治疗,责任以 10,000 美元为限✓
c.须在周四前授权治疗,并承担所开具全部医疗费用的完整成本
d.须在 90 天内授权治疗,这同时也是拒绝该索赔的最后期限

两个期限从两个不同的事件起算。雇主自知悉工伤起有一个工作日交付索赔表。工人「递交」该表后,第 5402(c) 条要求雇主在一个工作日内授权符合适用诊疗指南的全部治疗,因此周三递交意味着周四之前。在索赔被接受或拒绝之前,这部分治疗责任以 10,000 美元为限——这笔钱正是在结论作出之前先花出去的,这就是该条的用意。90 天是另一个期限:未被拒绝的索赔到那时即被推定为应予赔付。

Labor Code §5401(a); §5402(b), (c)
198. 某业主以书面合同聘请一名注册专业工程师设计仓库,并凭这套图纸取得了建筑许可,随后搁置项目且从未支付设计费。该业主目前仍拥有这块地。工程师可以登记留置权吗?
a.不可以,因为工程从未开工,也就不存在可供留置权附着的对象
b.可以,登记普通机械师留置权,因为图纸是为工程提供的服务
c.可以,登记设计专业人员留置权,因为已取得建筑许可且业主仍持有该地块✓
d.可以,但前提是工程师在开始绘图后 20 天内送达过预备通知

《民法典》第 8302 条为设计专业人员在「计划中的工程尚未开工」的情况下,仍在场地上设定留置权——该章存在的意义正在于此。本题的条件全部齐备:符合第 8014 条定义的人员(注册专业工程师)、与土地所有人之间的书面合同、为推进该工程而取得的建筑许可或其他政府批准,以及登记留置权主张时订约的土地所有人仍持有该地块。若当初未取得许可,则依该章根本不产生留置权。

Civil Code §8302; §8300; §8014
反馈